Case Note & Summary
The plaintiff, Mrs. Prabha P. Shenai, carrying on business as a proprietress in civil construction works under the name M/s. Sterling Engineering Co., filed a summary suit against the defendant, M/s. Ispat Industries Ltd., for recovery of Rs.1,13,06,769.40 together with interest. The claim arose out of a written contract for earth filling work at Dolvi Village, Pen Taluka, District Raigad, Maharashtra. The contract was evidenced by four documents: an offer letter dated 14 March 1994, a revised quotation letter dated 21 March 1994, an acceptance letter dated 25 April 1994, and a letter of acceptance with variations dated 2 May 1994. The plaintiff mobilised machinery and manpower and carried out the work under the supervision of the defendant's site engineer. The plaintiff raised invoices from time to time, which were received and accepted by the defendant without objection. After adjusting payments made by the defendant, the plaintiff claimed a balance of Rs.1,13,06,769.40. The defendant was granted unconditional leave to defend and filed a written statement contesting the suit, alleging poor quality of work, inflated claims, and that the plaintiff had abandoned the work. Issues were framed, and the parties led oral and documentary evidence. The court heard the constituted attorney of the plaintiff and counsel for the defendant. The court analysed the evidence and found that the plaintiff had proved the contract and performance. The defendant failed to lead any evidence to support its defence of poor quality or inflated claims. The court held that the plaintiff was entitled to the claimed amount with interest at 6% per annum from the date of the suit until payment. The suit was decreed accordingly.
Headnote
A) Contract Law - Summary Suit - Recovery of Contractual Payment - Written Contract - The plaintiff sought recovery of balance payment for earth filling work under a written contract evidenced by four documents. The defendant was granted unconditional leave to defend. The court examined the evidence and held that the plaintiff had proved the contract and performance, and the defendant failed to prove its defence of poor quality or inflated claims. (Paras 1-24) B) Evidence - Burden of Proof - Onus on Defendant - In a summary suit after leave to defend, the defendant bears the burden to prove its defence. The court found that the defendant did not lead sufficient evidence to establish that the work was of poor quality or that the invoices were inflated. (Paras 10-18) C) Contract Law - Quantum Meruit - Entitlement to Payment - Where work is performed and accepted, the contractor is entitled to payment at the agreed rates. The court held that the plaintiff's invoices were duly received and not objected to, and thus the plaintiff was entitled to the claimed amount. (Paras 19-24)
Issue of Consideration
Whether the plaintiff is entitled to recover the balance amount of Rs.1,13,06,769.40 for earth filling work carried out under a written contract, and whether the defendant's defence of poor quality work and inflated claims is sustainable.
Final Decision
The suit is decreed in favour of the plaintiff for a sum of Rs.1,13,06,769.40 with interest at 6% per annum from the date of the suit until payment.
Law Points
- Contract law
- Summary suit
- Unconditional leave to defend
- Burden of proof
- Quantum meruit
- Written contract
- Evidence Act
- 1872





