Bombay High Court Dismisses Section 9 Petition for Interim Relief in Development Dispute — No Prima Facie Case for Injunction Against Slum Rehabilitation Authority. Court holds that developer's unilateral action of obtaining SRA approval for redevelopment on petitioner's plot without consent does not warrant interim relief under Section 9 of Arbitration Act as the agreement contained arbitration clause and petitioner failed to show irreparable injury.

High Court: Bombay High Court Bench: BOMBAY
  • 99
Judgement Image
Font size:
Print

Case Note & Summary

The petitioner, Jai Neptune Co-operative Housing Society Limited, filed a petition under Section 9 of the Arbitration and Conciliation Act, 1996, seeking interim measures against the respondents, Lotus Logistics & Developers Pvt. Ltd. (developer) and the Slum Rehabilitation Authority (SRA). The petitioner had entered into a development agreement with the developer on 25th February 2008, and an addendum on 13th February 2009, for development of its plot bearing CTS No.310/B. The petitioner alleged that the developer, without its consent, obtained approval from the SRA for a slum rehabilitation scheme on the petitioner's plot and other adjacent plots, and commenced construction. The petitioner sought an injunction restraining the SRA from permitting further construction, directions to revoke permissions, appointment of a court receiver, and other reliefs. The court examined the facts and submissions. The developer contended that the agreement allowed it to obtain necessary approvals and that the petitioner had knowledge of the SRA scheme. The SRA submitted that permissions were granted as per law. The court held that the petitioner failed to make out a prima facie case for interim relief. The balance of convenience was against granting injunction as the project was at an advanced stage and would affect slum dwellers. The petitioner did not demonstrate irreparable injury. The court dismissed the petition, leaving the parties to pursue arbitration.

Headnote

A) Arbitration - Interim Measures under Section 9 - Prima Facie Case - The court considered whether the petitioner had made out a prima facie case for grant of interim injunction against the developer and the Slum Rehabilitation Authority. The court held that the petitioner failed to establish a strong prima facie case as the development agreement permitted the developer to obtain approvals and the petitioner had not objected to the SRA scheme earlier. (Paras 1-10)

B) Arbitration - Balance of Convenience and Irreparable Injury - The court examined the balance of convenience and irreparable injury. It held that the balance of convenience was not in favor of the petitioner as the project was at an advanced stage and any injunction would cause greater hardship to the developer and the slum dwellers. The petitioner did not demonstrate irreparable injury. (Paras 11-20)

C) Arbitration - Section 9 - Scope of Interim Relief - The court reiterated that the power under Section 9 is to protect the subject matter of arbitration and not to decide the merits. The court declined to grant the relief sought as the petitioner had an alternative remedy by way of arbitration. (Paras 21-25)

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the petitioner is entitled to interim relief under Section 9 of the Arbitration and Conciliation Act, 1996, restraining the respondents from proceeding with construction on the petitioner's plot and directing revocation of permissions granted by the Slum Rehabilitation Authority, pending arbitration.

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

The petition is dismissed. No order as to costs. The parties are at liberty to pursue arbitration.

Law Points

  • Section 9 of Arbitration and Conciliation Act
  • 1996
  • Prima Facie Case
  • Balance of Convenience
  • Irreparable Injury
  • Interim Measures
  • Development Agreement
  • Slum Rehabilitation Scheme
  • Consent of Society
Subscribe to unlock Law Points Subscribe Now

Case Details

2015:BHC-OS:11311

Arbitration Petition No.1339 of 2014

2015-09-04

R.D. Dhanuka, J.

2015:BHC-OS:11311

Mr.Ralston Fernandes for the Petitioner, Mr.Pratik Seksaria with Mr.Gauraj Shah and Mr.Arun Panikar i/b AKS Legal for Respondent No.1, Mr.G.D. Utangale with Mr.Akhil Kypade i/b Utangale & Co. for Respondent No.2

Jai Neptune Co-operative Housing Society Limited

Lotus Logistics & Developers Pvt. Ltd. and Slum Rehabilitation Authority

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Petition under Section 9 of the Arbitration and Conciliation Act, 1996 seeking interim measures pending arbitration.

Remedy Sought

Injunction against respondent no.2 from permitting further construction on S.R. Scheme No.1, direction to revoke permissions, appointment of court receiver, and other interim reliefs.

Filing Reason

Alleged breach of development agreement by respondent no.1 by obtaining SRA approval without petitioner's consent and commencing construction on petitioner's plot.

Issues

Whether the petitioner has made out a prima facie case for grant of interim injunction under Section 9 of the Arbitration Act. Whether the balance of convenience lies in favor of the petitioner and whether the petitioner would suffer irreparable injury if interim relief is not granted.

Submissions/Arguments

Petitioner argued that respondent no.1 unilaterally obtained SRA approval without consent and commenced construction, violating the development agreement. Respondent no.1 contended that the agreement permitted obtaining approvals and that petitioner had knowledge of the SRA scheme. Respondent no.2 submitted that permissions were granted as per law and that the project was at an advanced stage.

Ratio Decidendi

The court held that the petitioner failed to establish a prima facie case for interim relief under Section 9 of the Arbitration and Conciliation Act, 1996. The balance of convenience was against granting injunction as the project was at an advanced stage and would affect slum dwellers. The petitioner did not demonstrate irreparable injury. The court declined to grant the relief sought, leaving the parties to resolve disputes through arbitration.

Judgment Excerpts

By this petition filed under section 9 of the Arbitration & Conciliation Act, 1996, the petitioner has prayed for interim measures against both the respondents... The petitioner failed to make out a prima facie case for interim relief. The balance of convenience was against granting injunction as the project was at an advanced stage.

Procedural History

The petitioner filed Arbitration Petition No.1339 of 2014 under Section 9 of the Arbitration and Conciliation Act, 1996 before the Bombay High Court. The petition was reserved on 6th August 2015 and pronounced on 4th September 2015.

Acts & Sections

  • Arbitration and Conciliation Act, 1996: Section 9
  • Maharashtra Co-operative Societies Act, 1960:
  • Development Control Regulation, 1991:
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
High Court High Court of Bombay at Aurangabad Partly Allows State's Appeal in Land Acquisition Compensation Case for Katpur Dam — Market Value Determined at Rs. 450 per Square Metre Based on Sale Instances and Potentiality of Land. The court upheld the Refere...
Related Judgement
High Court Bombay High Court Dismisses Section 9 Petition for Interim Relief in Development Dispute — No Prima Facie Case for Injunction Against Slum Rehabilitation Authority. Court holds that developer's unilateral action of obtaining SRA approval for redeve...