Bombay High Court Dismisses Appeal by Union of India Against Arbitral Award in Contract Dispute. Court Upholds Arbitrator's Interpretation of 'Fall Clause' in Repeat Order for Supply of PSC Sleepers Under Section 34 of Arbitration and Conciliation Act, 1996.

High Court: Bombay High Court Bench: BOMBAY In Favour of Accused
  • 21
Judgement Image
Font size:
Print

Case Note & Summary

The case involves an appeal by the Union of India (Central Railway) against an order of a learned Single Judge dismissing its challenge under Section 34 of the Arbitration and Conciliation Act, 1996 to an arbitral award. The respondent, M/s. Kesharia Concrete Products Pvt. Ltd., had been supplying PSC sleepers to the Railways since 1988. In 1995, an order for 50,000 sleepers was placed, and in 1996 a repeat order was issued with a 'Fall Clause' (clause x) which stated that if a future open tender resulted in lower rates, those rates would apply to the repeat order. The rates for the repeat order were negotiated. Subsequently, the Railways invited a fresh tender and accepted a lower rate of Rs.283.50 per sleeper, and unilaterally applied that rate to the repeat order. The respondent claimed the difference between the negotiated rate (Rs.351.50) and the new rate, along with other claims. The arbitrator awarded Rs.94,50,776 towards the rate difference, rejecting the other claims. The Railways challenged the award under Section 34, which was dismissed by the Single Judge. In appeal, the Division Bench held that the arbitrator's interpretation of the Fall Clause was plausible and not perverse, and therefore not open to interference under Section 34. The appeal was dismissed.

Headnote

A) Arbitration - Section 34 Challenge - Plausible Interpretation - The court held that where the arbitrator has given a plausible interpretation of a contractual clause, the court under Section 34 of the Arbitration and Conciliation Act, 1996 cannot substitute its own view even if another interpretation is possible. The 'Fall Clause' in the repeat order was interpreted by the arbitrator to mean that lower rates from a subsequent tender would apply to the repeat order, and this interpretation was held to be plausible and not perverse. (Paras 1-10)

B) Contract Law - Fall Clause - Interpretation - The 'Fall Clause' in a repeat order for supply of PSC sleepers provided that if lower rates are accepted in a future open tender, those rates would apply to the repeat order. The court upheld the arbitrator's view that this clause was intended to benefit the Railways by ensuring lower rates, and the contractor was entitled to the difference in rates when the Railways unilaterally reduced the rate. (Paras 4-8)

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the learned Single Judge erred in not interfering with the arbitral award under Section 34 of the Arbitration and Conciliation Act, 1996, particularly regarding the interpretation of the 'Fall Clause' in the repeat order contract.

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

Appeal dismissed. The order of the learned Single Judge upholding the arbitral award is confirmed. No order as to costs.

Law Points

  • Arbitration
  • Contract Interpretation
  • Fall Clause
  • Section 34 Arbitration and Conciliation Act 1996
  • Plausible Interpretation
  • Interference with Arbitral Award
Subscribe to unlock Law Points Subscribe Now

Case Details

2015 LawText (BOM) (06) 57

Appeal No.581 of 2005 in Arbitration Petition No.184 of 2003

2015-06-26

Mohit S. Shah, C.J., A.K. Menon, J.

Mr. T. J. Pandian with Suresh Kumar for the Appellant, Mr. Snehal Shah with Ms. Mahek Bookwala & Z.A. Jariwala i/b. Thakore Jariwala & Ass. for the Respondents

Union of India through General Manager, Central Railway, CSTM, Mumbai

M/s. Kesharia Concrete Products Pvt. Ltd.

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Appeal against order of Single Judge dismissing challenge to arbitral award under Section 34 of Arbitration and Conciliation Act, 1996.

Remedy Sought

The appellant (Union of India) sought to set aside the arbitral award directing payment of Rs.94,50,776 with interest.

Filing Reason

Dispute arose regarding interpretation of 'Fall Clause' in repeat order for supply of PSC sleepers; appellant contended that the arbitrator's interpretation was erroneous.

Previous Decisions

Arbitral award dated 18 November 2001 granted Rs.94,50,776 with interest; Single Judge dismissed challenge under Section 34.

Issues

Whether the arbitrator's interpretation of the 'Fall Clause' in the repeat order was plausible and not perverse, thus not open to interference under Section 34 of the Arbitration and Conciliation Act, 1996.

Submissions/Arguments

Appellant argued that the Fall Clause only applied if a future tender resulted in lower rates, but the arbitrator erroneously interpreted it to allow the contractor to claim the difference when the Railways applied the lower rate. Respondent supported the arbitrator's interpretation that the clause was meant to benefit the Railways and the contractor was entitled to the negotiated rate until the lower rate was applied.

Ratio Decidendi

Under Section 34 of the Arbitration and Conciliation Act, 1996, the court cannot interfere with an arbitral award merely because another interpretation of a contractual clause is possible. If the arbitrator's interpretation is plausible and not perverse, it must be upheld.

Judgment Excerpts

The Arbitrator awarded Rs.94,50,776/ towards the first claim and rejected the second and the third claim. The court held that the arbitrator's interpretation of the Fall Clause was plausible and not perverse.

Procedural History

Arbitration proceedings resulted in award dated 18 November 2001. Appellant filed Arbitration Petition No.184 of 2003 under Section 34 of the Arbitration and Conciliation Act, 1996, which was dismissed by learned Single Judge. Appellant then filed Appeal No.581 of 2005 before the Division Bench.

Acts & Sections

  • Arbitration and Conciliation Act, 1996: 34
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
High Court Bombay High Court Dismisses Appeal by Union of India Against Arbitral Award in Contract Dispute. Court Upholds Arbitrator's Interpretation of 'Fall Clause' in Repeat Order for Supply of PSC Sleepers Under Section 34 of Arbitration and Conciliation Ac...
Related Judgement
High Court Madras High Court Dismisses PIL Challenging Government Order and Housing Board Proceedings Alleging Encroachment of Water Bodies — Finds No Evidence of Water Bodies and Upholds Government's Disposal of Land for Housing Scheme