Case Note & Summary
The case involves an appeal by the Union of India (Central Railway) against an order of a learned Single Judge dismissing its challenge under Section 34 of the Arbitration and Conciliation Act, 1996 to an arbitral award. The respondent, M/s. Kesharia Concrete Products Pvt. Ltd., had been supplying PSC sleepers to the Railways since 1988. In 1995, an order for 50,000 sleepers was placed, and in 1996 a repeat order was issued with a 'Fall Clause' (clause x) which stated that if a future open tender resulted in lower rates, those rates would apply to the repeat order. The rates for the repeat order were negotiated. Subsequently, the Railways invited a fresh tender and accepted a lower rate of Rs.283.50 per sleeper, and unilaterally applied that rate to the repeat order. The respondent claimed the difference between the negotiated rate (Rs.351.50) and the new rate, along with other claims. The arbitrator awarded Rs.94,50,776 towards the rate difference, rejecting the other claims. The Railways challenged the award under Section 34, which was dismissed by the Single Judge. In appeal, the Division Bench held that the arbitrator's interpretation of the Fall Clause was plausible and not perverse, and therefore not open to interference under Section 34. The appeal was dismissed.
Headnote
A) Arbitration - Section 34 Challenge - Plausible Interpretation - The court held that where the arbitrator has given a plausible interpretation of a contractual clause, the court under Section 34 of the Arbitration and Conciliation Act, 1996 cannot substitute its own view even if another interpretation is possible. The 'Fall Clause' in the repeat order was interpreted by the arbitrator to mean that lower rates from a subsequent tender would apply to the repeat order, and this interpretation was held to be plausible and not perverse. (Paras 1-10) B) Contract Law - Fall Clause - Interpretation - The 'Fall Clause' in a repeat order for supply of PSC sleepers provided that if lower rates are accepted in a future open tender, those rates would apply to the repeat order. The court upheld the arbitrator's view that this clause was intended to benefit the Railways by ensuring lower rates, and the contractor was entitled to the difference in rates when the Railways unilaterally reduced the rate. (Paras 4-8)
Issue of Consideration
Whether the learned Single Judge erred in not interfering with the arbitral award under Section 34 of the Arbitration and Conciliation Act, 1996, particularly regarding the interpretation of the 'Fall Clause' in the repeat order contract.
Final Decision
Appeal dismissed. The order of the learned Single Judge upholding the arbitral award is confirmed. No order as to costs.
Law Points
- Arbitration
- Contract Interpretation
- Fall Clause
- Section 34 Arbitration and Conciliation Act 1996
- Plausible Interpretation
- Interference with Arbitral Award




