Case Note & Summary
The Union of India, through the Executive Engineer, CPWD, filed a petition under Section 34 of the Arbitration and Conciliation Act, 1996 challenging an arbitral award dated 6th March 2013. The dispute arose from a contract for providing and fixing vitrified tiles flooring at Aayakar Bhavan, Mumbai. The respondent, M/s. Sarathi Enterprises, was awarded the contract after submitting the lowest bid of Rs.1,62,44,100/-. The contract included Special Condition No.8, which allowed substitution of specified brand of tiles with an equivalent brand upon proof of non-availability. The respondent claimed that the specified brand 'NUVOLTA DC/OBERON DC' was not available and used an alternative brand, leading to a dispute over rates. The arbitrator allowed some of the respondent's claims and rejected the petitioner's counterclaims. The petitioner challenged the award on grounds of patent illegality and perversity, arguing that the arbitrator erred in allowing claims for substituted items without proper rate analysis and in rejecting counterclaims for defects and delays. The court held that the arbitrator's findings were based on evidence and within the scope of the contract. The court noted that the arbitrator had correctly applied the principle of rate analysis for substituted items and that the petitioner failed to prove its counterclaims. The petition was dismissed, upholding the award.
Headnote
A) Arbitration - Section 34 Challenge - Scope of Judicial Review - The court cannot re-appreciate evidence or substitute its own view for that of the arbitrator unless the award is perverse or patently illegal. Held that the arbitrator's findings on rate analysis and rejection of counterclaims were based on evidence and not open to interference (Paras 10-15). B) Contract - Special Condition No.8 - Substituted Brand - Rate Analysis - Where the specified brand is not available, the contractor is entitled to use an equivalent brand subject to documentary evidence, and the rate for the substituted item must be determined based on market rates. Held that the arbitrator correctly applied the principle of rate analysis for the substituted tiles (Paras 16-20). C) Evidence - Burden of Proof - Counterclaims - The petitioner failed to produce sufficient evidence to prove its counterclaims for alleged defects and delays. Held that the arbitrator rightly rejected the counterclaims for lack of proof (Paras 21-25).
Issue of Consideration
Whether the arbitral award dated 6th March 2013 is liable to be set aside under Section 34 of the Arbitration and Conciliation Act, 1996 on the grounds of patent illegality, perversity, or contravention of the contract terms.
Final Decision
The petition is dismissed. The arbitral award dated 6th March 2013 is upheld.
Law Points
- Section 34 of the Arbitration and Conciliation Act
- 1996
- scope of judicial review
- interpretation of special conditions in contract
- rate analysis for substituted items
- burden of proof for counterclaims





