Case Note & Summary
The dispute arose from a Coal Mining and Delivery Agreement (CMDA) executed on 16.07.2008 between Parsa Kente Collieries Limited (appellant) and Rajasthan Rajya Vidyut Utpadan Nigam Limited (respondent) for supply of coal. The contract stipulated commencement of supply by 25.06.2011, but due to delays in obtaining forest and environmental clearances (force majeure), the commencement was mutually extended to 25.03.2013. Disputes arose regarding price escalation, fixed costs, escrow account amounts, and railway siding costs. The appellant invoked arbitration, and a retired High Court judge was appointed sole arbitrator. The arbitrator allowed claims under three heads: Price Adjustment (holding that the zero year for escalation remained 2011-2012, entitling appellant to higher price), Fixed Costs (Rs.78 crores for respondent's failure to take delivery causing suboptimal plant operation), and Escrow Account (refund of amounts deducted from running bills as the contingency for forfeiture never occurred). The claim for railway siding costs was rejected. The Commercial Court under Section 34 of the Arbitration and Conciliation Act, 1996 confirmed the award. On appeal by the respondent under Section 37, the High Court set aside the award, giving its own interpretation of the contract. The Supreme Court held that the High Court exceeded its jurisdiction under Section 37, as the arbitrator's interpretation of the contract clauses was plausible and could not be substituted. The Court restored the arbitral award, emphasizing that the scope of interference in arbitration appeals is narrow and does not permit re-appreciation of evidence or alternate construction of the contract. The appeal was allowed, and the impugned judgment of the High Court was set aside.
Headnote
A) Arbitration Law - Section 37 Appeal - Scope of Interference - The High Court, while hearing an appeal under Section 37 of the Arbitration and Conciliation Act, 1996, cannot substitute its own interpretation of the contract if the arbitrator's interpretation is plausible. The narrow scope of Section 37 does not permit re-appreciation of evidence or giving an alternate construction to the contract. (Paras 5-6) B) Contract Interpretation - Price Escalation - Force Majeure - Where the commencement date of a coal supply agreement was extended due to force majeure (delay in forest and environmental clearances), but the price escalation clause did not correspondingly extend the first operating year, the arbitrator's interpretation that the zero year for escalation remained the originally stipulated date (25.06.2011) was plausible and equitable. The High Court erred in interfering with such interpretation. (Paras 5.3.2-5.3.3) C) Contract Interpretation - Fixed Costs - Buyer's Default - Under clause 8.2(iii) of the Coal Mining and Delivery Agreement, if the buyer fails to take delivery of coal, causing the seller to operate at suboptimal levels and incur fixed costs, the seller is entitled to compensation. The arbitrator's award of Rs.78 crores for fixed costs was based on a plausible reading of the contract and could not be set aside under Section 37. (Paras 5.4-5.4.2) D) Contract Interpretation - Escrow Account - Contingent Undertaking - Where the seller's undertaking regarding the escrow account was limited to a contingency (failure of mine closure activity leading to forfeiture), and no such contingency occurred, the arbitrator's direction to refund the amount deducted from running bills was correct. The High Court's interference was unwarranted. (Para 2.4)
Issue of Consideration
Whether the High Court, in an appeal under Section 37 of the Arbitration and Conciliation Act, 1996, was justified in setting aside the arbitral award by substituting its own interpretation of the contract, when the arbitrator's interpretation was plausible.
Final Decision
The Supreme Court allowed the appeal, set aside the impugned judgment of the High Court dated 28.02.2018, and restored the arbitral award dated 27.05.2015 as confirmed by the Commercial Court. The Court held that the High Court exceeded its jurisdiction under Section 37 of the Arbitration and Conciliation Act, 1996 by substituting its own interpretation of the contract when the arbitrator's interpretation was plausible.
Law Points
- Scope of Section 37 of the Arbitration and Conciliation Act
- 1996
- Plausible interpretation of contract by arbitrator not to be interfered with
- Force majeure and price escalation in commercial contracts
- Fixed costs claim for suboptimal plant operation due to buyer's default
- Escrow account refund when contingency not triggered



