Bombay High Court Allows Builder's Appeals Against Interim Injunction in Specific Performance Suits — Agreements to Sell Not Concluded as Essential Terms Remained Unsettled. The court held that without a concluded contract, no prima facie case exists for interim injunction under Specific Relief Act, 1963.

High Court: Bombay High Court Bench: BOMBAY In Favour of Accused
  • 127
Judgement Image
Font size:
Print

Case Note & Summary

The appellant, M/s Rupji Constructions, a partnership firm engaged in construction business, entered into several agreements to sell with various flat purchasers (respondents) for flats in a building to be constructed. The respondents paid certain amounts as earnest money. However, the agreements did not specify the exact area of the flat, the total consideration, or the date of possession. Subsequently, disputes arose, and the respondents filed suits for specific performance of the agreements, seeking interim injunction restraining the builder from creating third party rights over the property. The trial court granted ad-interim injunction in favor of the respondents. The builder appealed against these orders. The High Court, after examining the agreements, held that they were not concluded contracts as essential terms were missing. The court found that the respondents had not made out a prima facie case for injunction, and the balance of convenience was in favor of the builder. The court also noted that the respondents could be compensated in damages. Accordingly, the appeals were allowed, and the interim injunctions were vacated.

Headnote

A) Specific Performance - Concluded Contract - Prima Facie Case - The court examined whether the agreements to sell between the builder and flat purchasers constituted concluded contracts. The court held that since essential terms such as the exact area of the flat, total consideration, and date of possession were not finalized, there was no concluded contract. Consequently, the plaintiffs failed to make out a prima facie case for grant of interim injunction. (Paras 6-10)

B) Interim Injunction - Balance of Convenience - Irreparable Loss - The court held that the balance of convenience was in favor of the builder as the plaintiffs had not paid the full consideration and the builder had already constructed the building. The court found that no irreparable loss would be caused to the plaintiffs if injunction was not granted, as they could be compensated in damages. (Paras 11-13)

C) Civil Procedure - Appeal from Order - Interference with Discretionary Order - The court reiterated that an appellate court should not interfere with a discretionary order of injunction unless it is perverse or based on wrong principles. However, in this case, the trial court's order was found to be based on a misreading of the evidence and thus liable to be set aside. (Paras 14-16)

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the trial court was justified in granting ad-interim injunction restraining the appellant-builder from creating third party rights over the suit property pending disposal of the suits for specific performance of agreement to sell.

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

The appeals are allowed. The impugned orders granting ad-interim injunction are set aside. The interim applications filed by the respondents for injunction stand dismissed. No order as to costs.

Law Points

  • Specific performance
  • Agreement to sell
  • Concluded contract
  • Interim injunction
  • Prima facie case
  • Balance of convenience
  • Irreparable loss
  • Section 16(c) Specific Relief Act
  • 1963
Subscribe to unlock Law Points Subscribe Now

Case Details

2013 LawText (BOM) (10) 71

Appeal from Order No. 826 of 2013 with connected appeals

0000-00-00

M/s Rupji Constructions

Bharati Santosh Labde & Anr. and others

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Civil appeals against orders granting ad-interim injunction in suits for specific performance of agreement to sell.

Remedy Sought

The appellant-builder sought to set aside the interim injunction granted by the trial court restraining it from creating third party rights over the suit property.

Filing Reason

The trial court granted ad-interim injunction in favor of the flat purchasers, which the builder challenged as being based on non-concluded agreements.

Previous Decisions

The trial court granted ad-interim injunction in favor of the respondents/plaintiffs.

Issues

Whether the agreements to sell between the builder and flat purchasers were concluded contracts? Whether the trial court was justified in granting ad-interim injunction?

Submissions/Arguments

The appellant argued that the agreements were not concluded as essential terms like area, total consideration, and possession date were not finalized. The respondents argued that they had paid earnest money and were entitled to specific performance and interim protection.

Ratio Decidendi

For an agreement to sell to be specifically enforceable, it must be a concluded contract with all essential terms finalized. In the absence of such terms, no prima facie case for interim injunction exists, and the balance of convenience favors the builder.

Judgment Excerpts

The agreements do not specify the exact area of the flat, the total consideration, or the date of possession. Hence, they are not concluded contracts. The plaintiffs have not made out a prima facie case for grant of injunction. The balance of convenience is in favor of the builder.

Procedural History

The respondents filed suits for specific performance in the trial court, which granted ad-interim injunction. The appellant filed appeals from order before the High Court.

Acts & Sections

  • Specific Relief Act, 1963: Section 16(c)
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
High Court Bombay High Court Allows Builder's Appeals Against Interim Injunction in Specific Performance Suits — Agreements to Sell Not Concluded as Essential Terms Remained Unsettled. The court held that without a concluded contract, no prima facie case exis...
Related Judgement
High Court Bombay High Court Upholds Industrial Court Order Directing Reinstatement with Full Backwages for Employee Absolved of Misconduct Charges. Employer's Action of Granting Fresh Employment Instead of Reinstatement Held Unfair Labour Practice Under MRTU &...