High Court of Bombay Rejects Application for Appointment of Arbitrator Under Section 11 of Arbitration Act Due to Premature Invocation of Two-Tier Dispute Resolution Clause. The Applicant Failed to First Exhaust the Decision of the Five-Member Committee as Mandated by Clause 21 of the Agreement, Rendering the Application Not Maintainable.

High Court: Bombay High Court Bench: NAGPUR In Favour of Accused
  • 5
Judgement Image
Font size:
Print

Case Note & Summary

The Miscellaneous Civil Application (Arbitration) No. 920/2012 was filed by The Akola Pravasi Va Malvahtuk Sahakari Sanstah Maryadit, Akola, a cooperative society, under Section 11 of the Arbitration and Conciliation Act, 1996 seeking appointment of an arbitrator based on an arbitration clause in an agreement with the Municipal Corporation of City of Amravati and another cooperative society. The dispute arose from the agreement's Clause 21, which provided a two-tier mechanism: first, a five-member committee comprising the Municipal Commissioner or his representative, the Divisional Controller of MSRTC, the agent's representative, the RTO, and the Incharge Engineer (Automobile) would decide the dispute; if the agent was dissatisfied, within 30 days it could indicate its intention to refer the dispute to arbitration, after which the Municipal Commissioner would send a list of three officers for selection as sole arbitrator. The applicant, having a dispute pending since August 2011, directly approached the High Court without the committee having rendered a decision. On 28.06.2013, the Court noted that the committee was under process and that certain interim prayers were not pressed. At the final hearing on 05.07.2013, the Court found that the applicant had not exhausted the first tier of the agreed procedure. It also observed that the applicant contributed to the delay by not timely nominating its representative for the committee. Relying on the principle from Deep Trading Company v. Indian Oil Corporation, (2013) 4 SCC 35, that a party may forfeit the right to appoint an arbitrator if it fails to do so upon request, the Court distinguished the present case because the applicant had not yet crossed the pre-arbitral stage. The Court held that the application for appointment of an arbitrator was premature and rejected it while granting liberty to pursue remedies. However, directing that the committee should adjudicate the claim within six months and the applicant should cooperate, the Court disposed of the matter with no order as to costs. The decision favored the respondents, as the application was dismissed, emphasizing strict adherence to contractual dispute resolution mechanisms.

Headnote

A) Arbitration - Appointment of Arbitrator - Section 11, Arbitration and Conciliation Act, 1996 - The Court held that where an arbitration clause mandates a pre-arbitral committee decision before arbitration, a party must exhaust that step before seeking appointment of an arbitrator. The applicant's failure to wait for the committee's decision rendered the application premature. (Paras 7-8)

B) Contract - Interpretation of Arbitration Clause - Clause 21 of Agreement - The clause required constitution of a five-member committee. The applicant's delay in nominating a representative contributed to the delay in constitution, thereby disentitling the applicant to immediate appointment of an arbitrator. (Paras 6-7)

C) Civil Procedure - Interim Relief under Section 11 - Section 11, Arbitration Act - The designated court under Section 11 lacks jurisdiction to grant interim relief or stay; the applicant accordingly did not press such prayers. (Order dated 28.06.2013, Para 3)

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the application under Section 11 of the Arbitration and Conciliation Act, 1996 for appointment of an arbitrator was maintainable given the two-tier dispute resolution clause and the fact that the pre-arbitral committee had not yet rendered a decision.

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

The application under Section 11 was rejected as premature, with liberty to initiate appropriate proceedings. The Court directed that the five-member committee should adjudicate the claim within six months, subject to confirmation of its constitution, and the applicant was to cooperate. No costs were awarded.

Law Points

  • Arbitration clause must be strictly construed
  • Pre-arbitral mechanism must be exhausted before invoking Section 11
  • Delay by applicant in appointing representative under agreed procedure precludes appointment of arbitrator at that stage
  • Designated court under Section 11 has no jurisdiction to grant interim relief
Subscribe to unlock Law Points Subscribe Now

Case Details

2013 LawText (BOM) (07) 203

Miscellaneous Civil Application (Arbitration) No. 920 of 2012

2013-07-05

Anoop V. Mohta, J.

Shri A.P. Wachasunder for applicant, Shri J.B. Kasat for nonapplicant no.1, None for nonapplicant no.2

The Akola Pravasi Va Malvahtuk Sahakari Sanstah Maryadit, Akola, through Digambar Sadashiv Warhade

1. The Municipal Corporation of City of Amravati, through its Municipal Commissioner, Amravati. 2. Amba Mal Va Pravasi Wahatuk Sewa Sahakari Sanstha Maryadit, Amravati, through Mahfooz Alam Badar Siddiqui

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Application under Section 11 of the Arbitration and Conciliation Act, 1996 seeking appointment of an arbitrator based on an agreement between a cooperative society and the Municipal Corporation and another society.

Remedy Sought

The applicant sought appointment of an arbitrator and interim reliefs, but later did not press the interim prayers.

Filing Reason

A dispute arising from the agreement had been pending since August 2011, and the applicant alleged delay in resolution, invoking the arbitration clause directly.

Previous Decisions

An order dated 28.06.2013 recorded that the five-member committee was under process and set the matter for final disposal on 05.07.2013.

Issues

Whether the application under Section 11 of the Arbitration and Conciliation Act, 1996 is maintainable when the pre-arbitral committee under Clause 21 of the agreement had not yet decided the dispute.

Submissions/Arguments

The applicant contended that the dispute had been pending since August 2011 and that the respondents had delayed the resolution, warranting judicial appointment of an arbitrator. The contesting respondent (nonapplicant no.1) argued that the appointment of the five-member committee was under process and therefore the petition was premature. The Court noted that the applicant had not appointed its representative for the committee in a timely manner, contributing to the delay.

Ratio Decidendi

Where an arbitration agreement contains a pre-arbitral mechanism such as a committee decision as a condition precedent to arbitration, the party seeking arbitration must exhaust that mechanism before approaching the court under Section 11 of the Arbitration and Conciliation Act, 1996. An application is premature if the agreed pre-arbitral steps have not been completed. Further, a party cannot take advantage of its own delay in complying with the contractual procedure to seek immediate appointment of an arbitrator.

Judgment Excerpts

The applicant has not crossed the first hurdle which in the present facts and circumstances and in view of specific agreement/ arbitration clause, just cannot be overlooked. No case is made out by the applicant to appoint the arbitrator at this stage of the proceedings. If we apply the legal position exposited by this Court in Datar Switchgears to the admitted facts, it will be seen that the Corporation has forfeited its right to appoint the arbitrator... The designated Court has no jurisdiction under Section 11 to pass such order.

Procedural History

The applicant filed the miscellaneous civil application under Section 11. On 28.06.2013, the Court passed an order noting that the five-member committee was under process and that the applicant was not pressing certain interim prayers; the matter was stood over to 05.07.2013 for final disposal. On 05.07.2013, after hearing both sides, the Court rejected the application with liberty.

Acts & Sections

  • Arbitration and Conciliation Act, 1996: Section 11
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
High Court High Court of Bombay Rejects Application for Appointment of Arbitrator Under Section 11 of Arbitration Act Due to Premature Invocation of Two-Tier Dispute Resolution Clause. The Applicant Failed to First Exhaust the Decision of the Five-Member Commit...
Related Judgement
High Court High Court of Bombay at Aurangabad Considers Civil Revision on Willful Default in Rent under Hyderabad Houses (Rent, Eviction and Lease) Control Act, 1954. Tenant Challenges Concurrent Eviction Orders, Arguing Joint Family Tenancy and Non-Willful Def...