Bombay High Court Sets Aside Arbitral Award for Claim of Idling Establishment Due to Prohibition Clause in Contract. Clause 17.3 of General Conditions of Contract Bars Compensation for Delay, Only Extension of Time Permissible.

High Court: Bombay High Court Bench: BOMBAY In Favour of Prosecution
  • 61
Judgement Image
Font size:
Print

Case Note & Summary

The Union of India, through the General Manager, Western Railway, filed a petition under Section 34 of the Arbitration and Conciliation Act, 1996, challenging an arbitral award dated 21 April 2011. The dispute arose from a contract awarded to R.S. Jiwani, Engineers and Contractors on 23 November 1992 for Rs.16,23,524 with a five-month completion period. The contractor could not complete the work on time and was granted extensions. Disputes arose, and the contractor invoked arbitration on 6 October 1997. The arbitrator allowed several claims, including Claim No. 1 for Rs.25,330/- for idling of establishment due to prolongation of the contract. The petitioner argued that Clause 17.3 of the General Conditions of Contract expressly prohibited any claim for damages or compensation for delay, regardless of the cause, and that the arbitrator ignored this clause. The respondent contended that the arbitrator found the petitioner responsible for the delay, making the prohibition inapplicable. The court examined Clause 17.3 and held that it clearly barred any claim for damages or compensation for delay, irrespective of the cause. The arbitrator had not considered this clause despite it being raised. The court concluded that the arbitrator exceeded its jurisdiction by allowing the claim in the face of the express prohibition. Consequently, the court set aside the award to the extent of Claim No. 1 and dismissed the petition in respect of other claims.

Headnote

A) Arbitration - Challenge to Arbitral Award - Section 34 Arbitration & Conciliation Act, 1996 - Prohibition Clause - Claim for idling of establishment due to prolongation of contract - Clause 17.3 of General Conditions of Contract expressly prohibits any claim for damages or compensation for delay, irrespective of cause - Arbitrator allowed claim despite specific objection - Held that arbitrator exceeded jurisdiction by awarding claim in teeth of prohibition clause - Award set aside to that extent (Paras 1-6).

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the arbitral tribunal could award compensation for idling of establishment due to prolongation of contract in the face of Clause 17.3 of the General Conditions of Contract which prohibits any claim for damages or compensation for delay.

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

The court set aside the arbitral award to the extent of Claim No. 1 (Rs.25,330/-) and dismissed the petition in respect of other claims.

Law Points

  • Arbitral tribunal cannot award damages or compensation for delay when contract expressly prohibits such claims
  • Clause 17.3 of General Conditions of Contract bars compensation for delay irrespective of cause
  • Arbitrator exceeds jurisdiction by ignoring express contractual prohibition
Subscribe to unlock Law Points Subscribe Now

Case Details

2013 LawText (BOM) (02) 46

Arbitration Petition No. 887 of 2012

2013-02-06

R.D. Dhanuka

Mr. Suresh Kumar along with Mr. Jagdish Koyande for the petitioner, Mr. M.S. Bhandari i/by Ms. Pranjali Bhandari for respondent

Union of India, through General Manager, Western Railway, Churchgate, Mumbai 400 020 and Divisional Railway Manager (Works), Western Railway, Mumbai Central

R.S. Jiwani, Engineers and Contractors, Narayan Niwas, 2nd Floor, 2, Kherwadi Lane, Mumbai 400 004

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Petition under Section 34 of the Arbitration and Conciliation Act, 1996 challenging an arbitral award.

Remedy Sought

Petitioner (Union of India) sought to set aside the arbitral award dated 21 April 2011.

Filing Reason

The arbitrator allowed Claim No. 1 for idling of establishment due to prolongation of contract despite Clause 17.3 prohibiting such compensation.

Previous Decisions

Arbitral award dated 21 April 2011 allowed some claims of the respondent and rejected the counter claim of the petitioner.

Issues

Whether the arbitral tribunal could award compensation for idling of establishment due to prolongation of contract in the face of Clause 17.3 of the General Conditions of Contract which prohibits any claim for damages or compensation for delay.

Submissions/Arguments

Petitioner: Clause 17.3 prohibits any claim for damages or compensation for delay irrespective of cause; arbitrator ignored this clause and exceeded jurisdiction. Respondent: Arbitrator found petitioner responsible for delay, so prohibition not applicable.

Ratio Decidendi

Clause 17.3 of the General Conditions of Contract expressly prohibits any claim for damages or compensation for delay, irrespective of the cause of delay. The arbitrator exceeded its jurisdiction by allowing such a claim in the teeth of the prohibition clause.

Judgment Excerpts

Perusal of clause 17.3 makes it clear that irrespective of the causes of delay of whatsoever nature, the contractor's entitlement was only to extension of completion date and not damages or compensation. In my view, in view of the such prohibition clause, the learned arbitrator could not have awarded this claim.

Procedural History

Contract awarded on 23 November 1992. Disputes arose, arbitration invoked on 6 October 1997. Arbitral award dated 21 April 2011. Petition under Section 34 filed on 2012.

Acts & Sections

  • Arbitration and Conciliation Act, 1996: Section 34
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
High Court Bombay High Court Sets Aside Arbitral Award for Claim of Idling Establishment Due to Prohibition Clause in Contract. Clause 17.3 of General Conditions of Contract Bars Compensation for Delay, Only Extension of Time Permissible.
Related Judgement
High Court Bombay High Court Dismisses Municipal Council's Challenge to Industrial Court's Order Granting Permanency to Daily Wage Workers. Regularization of daily wagers upheld as Industrial Court had jurisdiction to grant permanency under MRTU & PULP Act, 197...