Bombay High Court Dismisses Builder's Suit for Specific Performance and Damages in Construction Contract Dispute. Termination of Agreement Upheld as Another Contractor Completed the Buildings, Making Specific Performance Impossible.

High Court: Bombay High Court Bench: BOMBAY
  • 5
Judgement Image
Font size:
Print

Case Note & Summary

The plaintiff, M/s. Gurudev Developers, a partnership firm, filed a suit against the defendant, Kurla Konkan Niwas CHS Ltd., seeking specific performance of an agreement dated 18th January, 1985, under which the plaintiff was appointed as builder/contractor to construct buildings for the defendant society. The plaintiff also sought a declaration that the termination of the agreement by the defendant's advocate's letter dated 21st January, 1992 was illegal, and in the alternative, claimed damages of Rs.1,83,07,410/-. The plaintiff had only completed some plinth work and erected 27 pillars before the defendant terminated the contract and awarded it to another contractor, who completed the buildings. The defendant admitted the agreement and the limited construction but denied any further work by the plaintiff. The court framed issues, including whether the plaintiff proved the illegality of termination, entitlement to specific performance, and entitlement to damages. The court found that since the buildings were already constructed by another contractor, specific performance was impossible. The plaintiff failed to prove damages beyond Rs.4 lacs, which was admitted by the defendant. The court dismissed the suit for specific performance and damages except for Rs.4 lacs, which was awarded to the plaintiff. The judgment was pronounced on 20th February, 2013 by Justice Roshan Dalvi.

Headnote

A) Contract Law - Specific Performance - Impossibility of Performance - Specific Relief Act, 1963, Section 10 - The plaintiff builder sought specific performance of a construction agreement after the defendant society terminated the contract and another contractor completed the buildings. The court held that since the buildings were already constructed by another contractor, specific performance was impossible and the plaintiff was not entitled to it. (Paras 1-2)

B) Contract Law - Damages - Burden of Proof - Indian Contract Act, 1872, Section 73 - The plaintiff claimed damages of Rs.1,83,07,410/- in the alternative. The court found that the plaintiff failed to prove the extent of damages suffered, except for Rs.4 lacs which was admitted by the defendant. The court held that the burden of proving damages lies on the plaintiff. (Paras 2, 5)

C) Contract Law - Termination of Contract - Validity - The defendant society terminated the agreement dated 18th January, 1985 by letter dated 21st January, 1992. The court held that the termination was not illegal as the plaintiff had not completed the construction and the defendant had the right to terminate. (Paras 1-3)

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the plaintiff is entitled to specific performance of the agreement dated 18th January, 1985 and whether the termination of the agreement by the defendant was illegal.

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

The suit is dismissed except for the award of Rs.4 lacs to the plaintiff. The plaintiff is not entitled to specific performance or the claimed damages.

Law Points

  • Specific performance
  • Damages
  • Termination of contract
  • Impossibility of performance
  • Burden of proof
Subscribe to unlock Law Points Subscribe Now

Case Details

2013 LawText (BOM) (02) 27

Suit No.819 of 1992

2013-02-20

Mrs. Roshan Dalvi, J.

Mr. S.H. Mishra for the Plaintiffs, Mr. V.L. Desai for the Defendants

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Civil suit for specific performance of a construction agreement and damages in the alternative.

Remedy Sought

Plaintiff sought specific performance of agreement dated 18th January, 1985, declaration that termination was illegal, and damages of Rs.1,83,07,410/-.

Filing Reason

Defendant society terminated the construction agreement and awarded the project to another contractor.

Previous Decisions

Issues were framed by Justice Ganoo on 13th August, 2008.

Issues

Whether the plaintiff proved that the termination of the suit agreement by the defendant was illegal? Whether the plaintiff is entitled to specific performance of the agreement dated 18th January, 1985? Whether the plaintiff is entitled to recover damages of Rs.1,83,07,410/- from the defendant?

Submissions/Arguments

Plaintiff argued that the termination was illegal and that they were entitled to specific performance or damages. Defendant argued that specific performance was impossible as another contractor had completed the buildings, and that the plaintiff failed to prove damages.

Ratio Decidendi

Specific performance cannot be granted when the subject matter of the contract has been performed by another party, making it impossible. The burden of proving damages lies on the plaintiff, and failure to prove the extent of damages results in denial of the claim except for admitted amounts.

Judgment Excerpts

The Plaintiff has sued for specific performance of the agreement between the Plaintiff and the defendant society dated 18th January, 1985 and for declaration that the termination of the agreement dated 21st January, 1992 is illegal. The case of specific performance is resisted under the ground that another contractor has constructed the buildings of the society.

Procedural History

The suit was filed in 1992. Issues were framed by Justice Ganoo on 13th August, 2008. Judgment was reserved on 7th February, 2013 and pronounced on 20th February, 2013.

Acts & Sections

  • Indian Partnership Act, 1932:
  • Specific Relief Act, 1963: Section 10
  • Indian Contract Act, 1872: Section 73
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
High Court Bombay High Court Dismisses Builder's Suit for Specific Performance and Damages in Construction Contract Dispute. Termination of Agreement Upheld as Another Contractor Completed the Buildings, Making Specific Performance Impossible.
Related Judgement
High Court Bombay High Court Quashes School Tribunal's Contempt Proceedings for Lack of Jurisdiction. Presiding Officer Not Empowered as Judicial Magistrate First Class Under Section 13 of M.E.P.S. Act, 1977.