Case Note & Summary
The case involves an appeal under Section 37 of the Arbitration and Conciliation Act, 1996, against a judgment of a Learned Single Judge dated 11 November 2011, which partly set aside an arbitral award. The dispute arose from a construction contract between Edifice Developers and Project Engineers Ltd. (Appellant) and M/s. Essar Projects (India) Ltd. (Respondent) for the construction of Plant 'C' building. A letter of intent was issued on 28 February 1998 for a contract price of Rs.1.63 Crores. Disputes were referred to arbitration, and the Arbitral Tribunal awarded Rs.1.93 Crores to the Appellant, including retention money, overhead losses, loss of profit, and underutilized plant and equipment, with interest. The Learned Single Judge affirmed the award for retention money but set aside the other claims. The Appellant appealed. The High Court upheld the Single Judge's decision, holding that the Arbitrator's award for overhead losses based on Hudson's Formula was without proof of actual loss, as the Appellant did not produce accounts or oral evidence. The award for loss of profit and underutilized plant was also set aside for lack of reasoning. The court emphasized that an award based on no evidence is patently illegal and contrary to public policy under Section 34 of the Act.
Headnote
A) Arbitration - Section 34 Arbitration and Conciliation Act, 1996 - Setting Aside Award - Public Policy - The court examined whether an arbitral award granting overhead losses and loss of profit based on Hudson's Formula without proof of actual loss is contrary to public policy. The court held that the award was based on no evidence and thus patently illegal, warranting interference under Section 34. (Paras 4-6) B) Arbitration - Hudson's Formula - Overhead Loss - Proof of Actual Loss - The Arbitral Tribunal allowed a claim for overhead losses using Hudson's Formula despite the claimant not producing any basis of account or oral evidence. The court held that in the absence of proof of actual loss, the award is unsustainable and set aside. (Paras 4-5) C) Arbitration - Loss of Profit - Underutilized Plant and Equipment - The court set aside the award for loss of profit and underutilized plant and equipment as the Arbitrator failed to provide any reasoning or basis for the quantification, rendering the award arbitrary and liable to be set aside. (Para 6)
Issue of Consideration
Whether the Arbitral Tribunal could award overhead losses and loss of profit based on Hudson's Formula without the claimant producing evidence of actual loss, and whether such award is contrary to the public policy of India under Section 34 of the Arbitration and Conciliation Act, 1996.
Final Decision
The appeal was dismissed. The High Court upheld the judgment of the Learned Single Judge, confirming that the arbitral award for overhead losses, loss of profit, and underutilized plant and equipment was rightly set aside. The award for retention money was affirmed.
Law Points
- Arbitration
- Hudson's Formula
- Overhead Loss
- Loss of Profit
- Section 34 Arbitration and Conciliation Act 1996
- Public Policy
- Proof of Actual Loss




