Supreme Court Partially Allows Contractor's Appeal in Arbitration Dispute Under Arbitration Act, 1940 — Clause 59 of Agreement Does Not Bar Claims for Extra Lead, Non-Supply of Food Grains, Short Supply of Cement, and Stock Materials. Court Restores Arbitrator's Award on Certain Claims, Modifies Interest Rate.

  • 4
Judgement Image
Font size:
Print

Case Note & Summary

The case arises from arbitration proceedings under the Arbitration Act, 1940, concerning three agreements for irrigation works between the appellant contractor and the respondent State. The appellant had quoted rates 10-12% below standard and entered into agreements in 1979. Disputes arose, leading to arbitration. The arbitrator passed three awards on 19.8.1988, allowing various claims including extra lead (Claim 1), non-supply of food grains (Claim 3), short supply of cement (Claim 4), stock materials (Claim 7), and interest (Claim 9). The respondent filed applications under Sections 30 and 33 to set aside the awards, while the appellant sought decrees under Section 17. The sub-Court modified the award on Claim 1, set aside Claim 3, and upheld others. Both parties appealed to the High Court, which set aside the entire award, holding it contrary to Clause 59 of the agreement. The Supreme Court heard the appeal on the limited claims pressed by the appellant. The Court examined Clause 59, which barred claims for compensation due to departmental delays or hindrances, but held that it did not bar claims based on express contract terms or Section 70 of the Contract Act. On Claim 1 (extra lead), the Court found that the sub-Court erred in modifying the rate as there was no error apparent; the arbitrator's finding was based on evidence. On Claim 3 (food grains), the Court held that the arbitrator's finding that food grains were available but not supplied was a finding of fact, and the High Court erred in reappreciating evidence. On Claim 4 (cement), the Court upheld the arbitrator's reliance on Section 70 and adverse inference against the department. On Claim 7 (stock materials), the Court found the award justified. On Claim 9 (interest), the Court modified the rate to 9% per annum from the date of award till payment, while upholding the pre-award interest. The Supreme Court allowed the appeals in part, restoring the arbitrator's award on Claims 1, 3, 4, and 7, and modifying the interest rate.

Headnote

A) Arbitration Law - Jurisdiction of Arbitrator - Clause 59 of Agreement - Bar on Claims - The arbitrator's award was challenged on the ground that it violated Clause 59 of the contract, which prohibited claims for compensation due to departmental delays or hindrances. The Supreme Court held that Clause 59 did not bar claims based on express or implied terms of the contract or under Section 70 of the Contract Act, 1872, and that the arbitrator had jurisdiction to decide such claims. (Paras 1-6)

B) Arbitration Law - Error Apparent on Face of Record - Modification of Award - The sub-Court modified the arbitrator's award on Claim No.1 (extra lead) by reducing the rate from Rs.15 per cubic meter to a rate calculated as per procedure, finding an error apparent. The Supreme Court held that the sub-Court exceeded its jurisdiction under Sections 30 and 33 of the Arbitration Act, 1940, as the arbitrator's finding on quantum was based on evidence and not perverse. (Paras 12-13)

C) Contract Law - Section 70 of Contract Act, 1872 - Quantum Meruit - Claims for Extra Lead, Non-Supply of Food Grains, Short Supply of Cement, and Stock Materials - The arbitrator allowed these claims under Section 70, finding that the appellant had supplied materials and performed work not covered by the contract, and the respondent had accepted the benefit. The Supreme Court upheld the arbitrator's findings, holding that the claims were not barred by Clause 59 and that the arbitrator's decision was final on facts. (Paras 7-10)

D) Arbitration Law - Interest on Arbitral Awards - Interest Act - The arbitrator awarded interest at 12% per annum from the date of claim petition. The Supreme Court modified the interest rate to 9% per annum from the date of the award till payment, in line with the prevailing rate, and held that interest for the pre-award period was within the arbitrator's discretion. (Para 11)

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the High Court was justified in setting aside the arbitrator's award on the ground that it was contrary to Clause 59 of the Agreement, and whether the claims for extra lead, non-supply of food grains, short supply of cement, stock materials, and interest were sustainable under the contract and the Arbitration Act, 1940.

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

Appeals allowed in part. The Supreme Court set aside the High Court judgment and restored the arbitrator's award on Claims 1, 3, 4, and 7. On Claim 9 (interest), the Court modified the rate to 9% per annum from the date of the award till payment, instead of 12% per annum from the date of claim petition. The sub-Court's modification on Claim 1 was set aside. The matter was remanded for computation of amounts accordingly.

Law Points

  • Arbitration Act
  • 1940
  • Sections 30
  • 33
  • 17
  • Contract Act
  • 1872
  • Section 70
  • Clause 59 of Agreement
  • Interest Act
  • Arbitrator's jurisdiction
  • Error apparent on face of record
  • Misconduct
  • Modification of award
  • Interest on arbitral claims.
Subscribe to unlock Law Points Subscribe Now

Case Details

2019 LawText (SC) (3) 67

Civil Appeal Nos.159-170 of 2010

2019-03-27

K.M. Joseph, J.

Sri K. Marappan (Dead) Through Sole LR. Balasubramanian

The Superintending Engineer T.B.P.H.L.C. Circle Anantapur

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Appeals against High Court judgment setting aside arbitration awards under the Arbitration Act, 1940.

Remedy Sought

Appellant sought restoration of arbitrator's award and decree in terms of the award.

Filing Reason

High Court set aside the arbitrator's awards holding them contrary to Clause 59 of the agreement.

Previous Decisions

Sub-Court modified award on Claim 1, set aside Claim 3, and upheld others; High Court set aside entire award.

Issues

Whether Clause 59 of the agreement bars the claims awarded by the arbitrator. Whether the High Court erred in setting aside the award on Claim 1 (extra lead) and Claim 3 (food grains). Whether the sub-Court could modify the arbitrator's award on quantum under Sections 30 and 33. Whether the arbitrator's award on Claims 4, 7, and 9 was sustainable.

Submissions/Arguments

Appellant: Arbitrator's award is final on facts; Clause 59 does not bar claims under Section 70 of Contract Act; High Court exceeded jurisdiction by reappreciating evidence. Respondent: Clause 59 bars all claims; arbitrator misconducted himself; award is contrary to contract terms.

Ratio Decidendi

Clause 59 of the agreement does not bar claims based on express or implied terms of the contract or under Section 70 of the Contract Act, 1872. The arbitrator's findings on facts are final and cannot be interfered with under Sections 30 and 33 of the Arbitration Act, 1940, unless there is an error apparent on the face of the record or misconduct. The court cannot modify an award on quantum unless the error is apparent.

Judgment Excerpts

The awards came to be challenged by the appellant and the awards were set aside. The arbitrator rejected claim Nos.6 and 8 whereas he awarded various sums in regard to the other claims. The High court found that the arbitration awards were totally unsustainable in view of Clause 59 of the Agreement. The arbitrator relied on Section 70 of the Contract Act. The sub-Court held inter alia as follows: As far as Claim No.I is concerned, namely, extra lead, the sub-Court proceeded to agree with the arbitrator that the appellant is entitled to extra lead.

Procedural History

Tender invited on 18.9.1978; agreements entered on 10.3.1979 and 28.6.1979; work completed; appellant filed claims on 28.11.1983 before panel of three arbitrators; awards set aside; new arbitrator appointed on 26.4.1988; awards passed on 19.8.1988; respondent filed applications under Sections 30 and 33; appellant filed suits under Section 17; sub-Court modified award on Claim 1, set aside Claim 3, upheld others; both parties appealed to High Court; High Court set aside entire award; appellant appealed to Supreme Court.

Acts & Sections

  • Arbitration Act, 1940: Sections 30, 33, 17
  • Indian Contract Act, 1872: Section 70
  • Interest Act:
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
Supreme Court Supreme Court Partially Allows Contractor's Appeal in Arbitration Dispute Under Arbitration Act, 1940 — Clause 59 of Agreement Does Not Bar Claims for Extra Lead, Non-Supply of Food Grains, Short Supply of Cement, and Stock Materials. Court Restore...
Related Judgement
Supreme Court Supreme Court Restores Murder Conviction in Single Axe Blow Case — High Court Erred in Reducing to Culpable Homicide Not Amounting to Murder. Use of deadly weapon on vital part establishes intention to cause death under Section 302 IPC, despite sin...