Bombay High Court Dismisses Appeal by Municipal Corporation in Arbitration Dispute — 1996 Act Applies to Proceedings Commenced After Its Enforcement. Failure to Appoint Arbitrator Within 30 Days Under Section 10 of Arbitration and Conciliation Act, 1996 Results in Default Appointment of Sole Arbitrator.

High Court: Bombay High Court In Favour of Prosecution
  • 79
Judgement Image
Font size:
Print

Case Note & Summary

The case involves an appeal by the Municipal Corporation of the City of Pune against a judgment of the 3rd Extra Joint District Judge, Pune, in Misc. Application No.586 of 1998. The dispute arose from a contract between the Corporation and Bombay Cable Car Co. Pvt. Ltd., which contained an arbitration clause. On 1st October 1996, the respondent issued a notice under Section 9 of the Arbitration Act, 1940, invoking the arbitration clause and appointing Hon'ble Mr. Justice M.L. Pendse (retd.) as sole arbitrator, giving the appellant 15 days to appoint its own arbitrator, failing which the appointed arbitrator would act as sole arbitrator. Subsequently, on 8th November 1996, the respondent issued another notice stating that since the Arbitration and Conciliation Act, 1996 had come into force, the earlier notice should be treated as a notice under Section 10 of the new Act, and the appellant had 30 days to communicate the name of its arbitrator. The notice claimed that the 30-day period ended on 5th October 1996, and in the absence of communication, the respondent's arbitrator would act as sole arbitrator. The arbitrator proceeded with the matter and passed an award. The appellant challenged the award before the District Court, which dismissed the application. The High Court considered the applicability of the 1996 Act to the arbitration proceedings. The court noted that the 1996 Act came into force on 22nd August 1996, and the arbitration proceedings commenced after that date. The court held that the 1996 Act applies to arbitrations commenced after its enforcement, even if the agreement was entered into prior, as per Section 85(2)(a) of the 1996 Act, which saves only those proceedings that had already commenced under the 1940 Act. The court further held that the notice under Section 9 of the 1940 Act could be treated as a notice under Section 10 of the 1996 Act, as the respondent's subsequent notice clarified the change. The appellant's failure to appoint an arbitrator within 30 days from the notice resulted in the respondent's arbitrator becoming the sole arbitrator. The court dismissed the appeal, upholding the judgment of the District Court.

Headnote

A) Arbitration Law - Applicability of Arbitration Act, 1996 - Repeal and Savings - Section 85 of Arbitration and Conciliation Act, 1996 - The court considered whether the 1996 Act applies to arbitration proceedings where the agreement was entered into before the new Act but proceedings commenced after its enforcement. The court held that the 1996 Act applies to arbitrations commenced after its enforcement, even if the agreement was prior, as per Section 85(2)(a) which saves only those proceedings that had already commenced under the 1940 Act. (Paras 1-10)

B) Arbitration Law - Appointment of Arbitrator - Notice under Section 9 of 1940 Act treated as notice under Section 10 of 1996 Act - The court examined the validity of treating a notice issued under Section 9 of the 1940 Act as a notice under Section 10 of the 1996 Act. The court held that such treatment is permissible as the 1996 Act had come into force before the expiry of the notice period, and the respondent's subsequent notice clarified the change. (Paras 2-5)

C) Arbitration Law - Appointment of Arbitrator - Failure to Appoint - Default Appointment - The court considered whether the appellant's failure to appoint an arbitrator within the stipulated time under the 1996 Act entitled the respondent to have its appointed arbitrator act as sole arbitrator. The court held that the appellant's failure to communicate the name of its arbitrator within 30 days from the notice resulted in the respondent's arbitrator becoming the sole arbitrator. (Paras 3-6)

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the Arbitration and Conciliation Act, 1996 applies to arbitration proceedings commenced after its enforcement, where the arbitration agreement was entered into prior to the new Act, and whether the notice under Section 9 of the 1940 Act can be treated as a notice under Section 10 of the 1996 Act.

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

The High Court dismissed the appeal, upholding the judgment of the 3rd Extra Joint District Judge, Pune, and confirming the validity of the arbitral award.

Law Points

  • Arbitration Act
  • 1940
  • 1996
  • Section 9
  • Section 10
  • Section 21
  • Section 85
  • Repeal and Savings
  • Applicability of New Act
  • Appointment of Arbitrator
  • Notice under Section 9 of 1940 Act treated as notice under Section 10 of 1996 Act
Subscribe to unlock Law Points Subscribe Now

Case Details

2005 LawText (BOM) (03) 251

Arbitration Appeal No.1 of 2003

2005-03-03

D.K. Deshmukh, J.

2005:BHC-AS:4223

Rohit Kapadia, Sr. Counsel with V.G. Mujumdar for Appellant; V.R. Manohar, Sr. Counsel with Usha Purohit i/b Shah, Desai, Doijode & Phatarphekar for Respondent

Municipal Corporation of the City of Pune

Bombay Cable Car Co. Pvt. Ltd.

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Appeal against judgment of District Court dismissing application challenging arbitral award

Remedy Sought

Appellant sought to set aside the judgment of the 3rd Extra Joint District Judge, Pune, which dismissed its application challenging the arbitral award

Filing Reason

Appellant challenged the arbitral award on the ground that the arbitration proceedings were not validly constituted under the Arbitration and Conciliation Act, 1996

Previous Decisions

The 3rd Extra Joint District Judge, Pune, dismissed Misc. Application No.586 of 1998 filed by the appellant challenging the arbitral award

Issues

Whether the Arbitration and Conciliation Act, 1996 applies to arbitration proceedings commenced after its enforcement, where the arbitration agreement was entered into prior to the new Act Whether the notice under Section 9 of the Arbitration Act, 1940 can be treated as a notice under Section 10 of the Arbitration and Conciliation Act, 1996 Whether the appellant's failure to appoint an arbitrator within the stipulated time under the 1996 Act entitled the respondent to have its appointed arbitrator act as sole arbitrator

Submissions/Arguments

Appellant argued that the arbitration proceedings were governed by the Arbitration Act, 1940, as the agreement was entered into prior to the 1996 Act, and the notice under Section 9 of the 1940 Act could not be treated as a notice under Section 10 of the 1996 Act Respondent argued that the 1996 Act applies to arbitrations commenced after its enforcement, and the notice under Section 9 of the 1940 Act was validly treated as a notice under Section 10 of the 1996 Act, and the appellant's failure to appoint an arbitrator within 30 days resulted in the respondent's arbitrator becoming the sole arbitrator

Ratio Decidendi

The Arbitration and Conciliation Act, 1996 applies to arbitrations commenced after its enforcement, even if the arbitration agreement was entered into prior to the new Act, as per Section 85(2)(a) of the 1996 Act. A notice under Section 9 of the 1940 Act can be treated as a notice under Section 10 of the 1996 Act if the new Act has come into force before the expiry of the notice period and the party clarifies the change. Failure to appoint an arbitrator within the stipulated time under the 1996 Act results in the other party's appointed arbitrator becoming the sole arbitrator.

Judgment Excerpts

By this Appeal, the Appellant challenges the judgment dated 5th August, 2000 passed by the 3rd Extra Joint District Judge, Pune in Misc.Application No.586 of 1998. The facts that are material and relevant for deciding this petition are that the Petitioner/Pune Municipal Corporation had entered into a contract with the Respondent. On 1st October, 1996 the Respondent issued a notice styling it as notice under Section 9 of the Arbitration Act, 1940. Another notice was issued on 8-11-1996 by the Respondent stating therein that as the Arbitration Act, 1996 had already come into force, the notice dated 1st October, 1996 should be taken to be a notice under Section 10 of the new Act and therefore the Petitioner had 30 days to communicate the name of its arbitrator.

Procedural History

The respondent issued a notice under Section 9 of the Arbitration Act, 1940 on 1st October 1996, followed by a notice on 8th November 1996 treating it as a notice under Section 10 of the Arbitration and Conciliation Act, 1996. The arbitrator appointed by the respondent proceeded and passed an award. The appellant filed Misc. Application No.586 of 1998 before the 3rd Extra Joint District Judge, Pune, challenging the award. The District Court dismissed the application on 5th August 2000. The appellant then filed Arbitration Appeal No.1 of 2003 before the Bombay High Court, which dismissed the appeal on 3rd March 2005.

Acts & Sections

  • Arbitration Act, 1940: Section 9
  • Arbitration and Conciliation Act, 1996: Section 10, Section 21, Section 85
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
High Court High Court of Karnataka Dismisses Appeal for Correction of Date of Birth in School Records at Fag End of Service — Delay and Lack of Credible Evidence Lead to Dismissal. The appellant failed to prove his date of birth as 29-9-1959 and the suit was ...
Related Judgement
High Court Bombay High Court Dismisses Appeal by Municipal Corporation in Arbitration Dispute — 1996 Act Applies to Proceedings Commenced After Its Enforcement. Failure to Appoint Arbitrator Within 30 Days Under Section 10 of Arbitration and Conciliation Act,...