Case Note & Summary
The case involves a consumer dispute between flat purchasers and a developer, Mantri Castles Pvt. Ltd., regarding delayed possession of flats in Bangalore. The flat purchasers, represented by R V Prasannakumaar and others, filed a complaint under Section 12(1)(c) of the Consumer Protection Act, 1986, before the National Consumer Disputes Redressal Commission (NCDRC). The NCDRC, by its order dated 8 June 2018, found that the developer breached its contractual obligation to hand over possession by 31 January 2014, as the occupation certificate was obtained only on 10 February 2016. The NCDRC awarded compensation for delayed possession from 1 February 2014 to 31 July 2016 at the contractual rate of Rs. 3 per sq. ft. per month, and additionally directed interest at 6% per annum on the amounts deposited by the complainants before the due date of possession. The NCDRC also directed the developer to complete common facilities and amenities within six months, failing which a monthly compensation of Rs. 1,000 per complainant would be payable. Both parties appealed to the Supreme Court: the flat purchasers challenged the limitation of interest only up to 31 July 2016, while the developer challenged the award of interest at 6% per annum, arguing that the contractual rate should prevail. The Supreme Court, after hearing arguments, upheld the NCDRC's view that the contractual compensation rate was inadequate and that the NCDRC had jurisdiction to award just compensation. However, the Court found merit in the flat purchasers' submission that the developer had not offered possession to all purchasers even as of the date of the appeal. The developer's affidavit admitted that 43 complainants were denied possession because they had filed the consumer complaint. The Supreme Court held that moving the NCDRC is no justification to deny possession, and the developer cannot avoid liability for interest during the pendency of the complaint. The Court noted that even according to the developer, out of 55 flat purchasers, possession had been handed over to only 16, and possession to 9 more was to be offered within a week. The Court modified the NCDRC order to direct that the liability to pay interest at 6% per annum shall continue until the date each flat purchaser is offered possession. The NCDRC in execution shall verify the date of offer of possession for each purchaser. The Supreme Court allowed the appeal of the flat purchasers and dismissed the appeals of the developer.
Headnote
A) Consumer Law - Representative Complaint - Section 12(1)(c) Consumer Protection Act, 1986 - Just Compensation - The NCDRC disposed of a consumer complaint filed in a representative capacity under Section 12(1)(c) of the Consumer Protection Act, 1986, awarding compensation for delayed possession. The Supreme Court upheld the NCDRC's power to award just compensation beyond the contractual rate, but modified the order to extend interest until actual possession is offered. (Paras 1-8) B) Consumer Law - Delay in Possession - Interest - The flat purchase agreement stipulated compensation at Rs. 3 per sq. ft. per month for delay, which the NCDRC found inadequate. The Supreme Court agreed that the contractual rate was too meager and upheld the award of 6% per annum interest as just compensation. (Paras 3-4) C) Consumer Law - Possession - Denial due to Litigation - The developer admitted that 43 complainants were not given possession because they had filed a consumer complaint. The Supreme Court held that moving the NCDRC is no justification to deny possession, and the developer cannot avoid liability for interest during the pendency of the complaint. (Paras 5-7) D) Consumer Law - Interest - Duration - The NCDRC confined interest to 31 July 2016, but the Supreme Court found that possession had not been offered to all purchasers even as of the date of the appeal. The Court directed that interest at 6% per annum shall continue until the date each flat purchaser is offered possession. (Paras 5-8)
Issue of Consideration
Whether the NCDRC was justified in confining the liability to pay interest for delayed possession only up to 31 July 2016, and whether the developer's appeal against the award of interest at 6% per annum is maintainable.
Final Decision
The Supreme Court allowed the appeal of the flat purchasers (Civil Appeal No. 1232 of 2019) and dismissed the appeals of the developer (Civil Appeal Nos. 1443-1444 of 2019). The Court modified the NCDRC order to direct that the liability to pay interest at 6% per annum shall continue until the date each flat purchaser is offered possession. The NCDRC in execution shall verify the date of offer of possession for each purchaser.
Law Points
- Consumer Protection Act
- 1986
- Section 12(1)(c)
- Representative capacity
- Just compensation
- Delay in possession
- Interest rate
- One-sided agreement
- Deficiency in service



