Case Note & Summary
The Supreme Court dismissed the civil appeal filed by MMTC Ltd. against the judgment of the Bombay High Court which had upheld the majority arbitral award dated 27.06.2001. The dispute arose from a consignment agency agreement dated 14.12.1993 between MMTC Ltd. (appellant) and Vedanta Ltd. (respondent, formerly Sterlite Industries). Under the agreement, MMTC was to store, handle, and market copper rods produced by Vedanta, selling them to customers against 100% advance payment. The agreement was modified on 06.01.1994 via a Memorandum of Understanding allowing MMTC to supply goods against letters of credit, with MMTC bearing responsibility for ensuring payment. Further modifications on 20.01.1994 allowed MMTC to extend credit to customers on its own terms, with payment to Vedanta due upon delivery. The dispute pertained to supplies made by MMTC to Hindustan Transmission Products Ltd. (HTPL) after April 1995. HTPL failed to pay MMTC, and MMTC did not pay Vedanta. Vedanta invoked the arbitration clause, and a three-member tribunal by majority awarded Vedanta Rs. 15,73,77,296 with interest. MMTC challenged the award under Section 34 of the Arbitration and Conciliation Act, 1996, arguing that the supplies to HTPL were under a direct agreement between Vedanta and HTPL, not under the 1993 agreement, and thus the dispute was not arbitrable. The Single Judge and Division Bench of the Bombay High Court rejected this challenge. The Supreme Court examined the scope of interference with arbitral awards under Sections 34 and 37 of the 1996 Act, noting that courts do not sit in appeal and interference is limited to grounds of public policy, including patent illegality, fraud, corruption, or violation of fundamental policy of Indian law. The Court held that the arbitrator's construction of the contract, considering the conduct of parties and correspondence, was a possible view and not perverse. The majority award found that the agreement did not distinguish between customers arranged by MMTC or Vedanta, and MMTC was responsible for payment. The Supreme Court found no ground to interfere with the concurrent findings of the arbitrator and the courts below, and dismissed the appeal.
Headnote
A) Arbitration Law - Scope of Interference with Arbitral Award - Section 34, Arbitration and Conciliation Act, 1996 - Court does not sit in appeal over arbitral award; interference limited to grounds of public policy including patent illegality, fraud, corruption, violation of fundamental policy of Indian law, or conflict with basic notions of justice or morality - Award not to be set aside merely for erroneous application of law or reappreciation of evidence (Paras 10-12). B) Arbitration Law - Interpretation of Arbitration Clause - Construction of contract by arbitrator is within arbitrator's jurisdiction; courts will not reassess material on record unless findings are arbitrary, capricious, or perverse - Conduct of parties and correspondence are relevant factors for interpretation (Paras 13-14). C) Contract Law - Consignment Agency - Agreement dated 14.12.1993 as modified by Memorandum of Understanding dated 06.01.1994 and meeting minutes dated 20.01.1994 - Appellant's responsibility to ensure payment from customers; no distinction between customers arranged by appellant or respondent - Arbitrator's finding that dispute was covered by arbitration clause upheld (Paras 2-9, 15-17).
Issue of Consideration
Whether the dispute between MMTC Ltd. and Vedanta Ltd. regarding supplies made to HTPL was arbitrable under the arbitration clause in the agreement dated 14.12.1993, and whether the courts below correctly refused to set aside the majority arbitral award.
Final Decision
The Supreme Court dismissed the civil appeal, upholding the majority arbitral award and the decisions of the Bombay High Court. The Court found no ground to interfere with the concurrent findings of the arbitrator and the courts below.
Law Points
- Scope of interference with arbitral award under Section 34 of Arbitration and Conciliation Act
- 1996
- Interpretation of arbitration clause
- Construction of contract by arbitrator not to be reassessed unless perverse
- Conduct of parties and correspondence relevant for interpreting contract



