Supreme Court Dismisses Appeal of Contractor in Arbitration Dispute Over Interest. Contractual Clauses 50 and 51 of GCC Barred Arbitral Tribunal from Awarding Interest on Delayed Payments Under Section 31(7)(a) of Arbitration and Conciliation Act, 1996.

  • 7
Judgement Image
Font size:
Print

Case Note & Summary

The dispute arose from a contract awarded to Jaiprakash Associates Ltd. (JAL) by Tehri Hydro Development Corporation India Ltd. (THDC) for execution of certain works, signed on 18th December 1998. Disputes led to arbitration under the Arbitration and Conciliation Act, 1996. The majority arbitral award dated 10th October 2010 allowed two claims and granted interest at 10% per annum from the date of invocation of arbitration (9th October 2007) until 60 days after the award, and future interest at 18% per annum until payment. THDC objected, arguing that Clauses 50 and 51 of the General Conditions of Contract (GCC) barred any interest. The Delhi High Court Single Judge quashed the interest portion, and the Division Bench upheld that decision. The core legal issue was whether the arbitral tribunal could award interest despite the express contractual prohibition. JAL argued that the clauses did not prohibit interest and that the earlier three-judge bench decision in State of Uttar Pradesh v. Harish Chandra and Company (1999) 1 SCC 63 should prevail over the later decision in Tehri Hydro Development Corporation Ltd. v. Jai Prakash Associates Ltd. (2012) 12 SCC 10, which interpreted identical clauses. Alternatively, JAL sought reference to a larger bench. THDC contended that the clauses were different from those in Harish Chandra, and that under Section 31(7)(a) of the 1996 Act, an arbitrator cannot award interest when the contract expressly prohibits it. The Supreme Court held that the clauses in the present case were identical to those in THDC v. Jai Prakash Associates Ltd., which had already decided that no interest was payable. The Court distinguished Harish Chandra as arising under the 1940 Act and involving different clause wording. The Court dismissed the appeal, affirming that the arbitral tribunal had no jurisdiction to award interest in light of the express contractual bar.

Headnote

A) Arbitration Law - Power to Award Interest - Contractual Prohibition - Section 31(7)(a) Arbitration and Conciliation Act, 1996 - Where the contract between the parties expressly prohibits payment of interest, the arbitral tribunal has no jurisdiction to award pendente lite interest. The High Court correctly set aside the award of interest by the arbitrators as Clauses 50 and 51 of the GCC barred such interest. (Paras 2-5, 12-13)

B) Arbitration Law - Precedent - Conflict of Decisions - Tehri Hydro Development Corporation Ltd. v. Jai Prakash Associates Ltd., (2012) 12 SCC 10 - The identical clauses were interpreted in this case between the same parties, holding that no interest was payable. This judgment governs the present case, and there is no conflict with State of Uttar Pradesh v. Harish Chandra and Company, (1999) 1 SCC 63 as the clauses were different and the latter arose under the Arbitration Act, 1940. (Paras 5, 10, 13)

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the arbitral tribunal could award interest in view of Clauses 50 and 51 of the General Conditions of Contract which prohibited payment of interest on amounts due to the contractor.

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

The Supreme Court dismissed the appeal, upholding the High Court's decision that no interest is payable as Clauses 50 and 51 of GCC bar the arbitrators from granting interest.

Law Points

  • Arbitration
  • Interest
  • Contractual prohibition
  • Pendente lite interest
  • Section 31(7)(a) Arbitration and Conciliation Act
  • 1996
Subscribe to unlock Law Points Subscribe Now

Case Details

2019 LawText (SC) (2) 35

Civil Appeal No(s). 1539 of 2019 (Arising out of SLP (C) No. 13551 of 2013)

2019-02-07

A.K. Sikri

Jaiprakash Associates Ltd. (JAL) Through Its Director

Tehri Hydro Development Corporation India Ltd. (THDC) Through Its Director

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Civil appeal against High Court order setting aside arbitral award of interest.

Remedy Sought

Appellant sought to restore the interest awarded by the arbitral tribunal.

Filing Reason

Appellant challenged the High Court's decision that Clauses 50 and 51 of GCC barred interest.

Previous Decisions

Arbitral tribunal awarded interest; Single Judge of Delhi High Court quashed interest; Division Bench upheld Single Judge.

Issues

Whether Clauses 50 and 51 of GCC prohibit the arbitral tribunal from awarding interest. Whether the judgment in Tehri Hydro Development Corporation Ltd. v. Jai Prakash Associates Ltd. governs the present case. Whether there is a conflict between Harish Chandra and THDC cases requiring reference to a larger bench.

Submissions/Arguments

Appellant argued that Clauses 50 and 51 did not prohibit interest and that Harish Chandra case should prevail. Appellant alternatively sought reference to a larger bench. Respondent argued that clauses were identical to those in THDC case, which held interest barred, and that under 1996 Act, arbitrator cannot override express contractual bar.

Ratio Decidendi

Where the contract expressly prohibits payment of interest, the arbitral tribunal has no jurisdiction to award pendente lite interest under Section 31(7)(a) of the Arbitration and Conciliation Act, 1996.

Judgment Excerpts

Clause 50.0 Interest on money due to the contractor No omission on the part of the Engineer in charge to pay the amount due upon measurement or otherwise shall vitiate or make void the contract, nor shall the contractor be entitled to interest upon any guarantee or payments in arrears nor upon any balance which may on the final settlement of his account, be due to him. Clause 51.0 No claim for delayed payment due to dispute etc. No claim for interest or damage will be entertained or be payable by the corporation in respect of any amount or balance which may be lying with the corporation owing to nay dispute, different or misunderstanding between the parties or in respect of any delay or omission on the part of he Engineer in charge in making intermediate or final payments on in any other respect whatsoever.

Procedural History

Contract signed on 18th December 1998. Disputes referred to arbitration. Majority award on 10th October 2010 granted interest. THDC filed objections in Delhi High Court. Single Judge on 15th November 2011 quashed interest. JAL appealed to Division Bench, which dismissed appeal in September 2012. JAL then filed SLP in Supreme Court, which was converted into Civil Appeal No. 1539 of 2019.

Acts & Sections

  • Arbitration and Conciliation Act, 1996: Section 31(7)(a)
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
Supreme Court Supreme Court Dismisses Appeal of Contractor in Arbitration Dispute Over Interest. Contractual Clauses 50 and 51 of GCC Barred Arbitral Tribunal from Awarding Interest on Delayed Payments Under Section 31(7)(a) of Arbitration and Conciliation Act, 19...
Related Judgement
Supreme Court Supreme Court Dismisses Appeals in Insolvency Case Due to Limitation and Mis-statements. NCLAT's Refusal to Condon Delay Upheld as Appellant Failed to Apply for Certified Copies and Made Contradictory Assertions Under Section 61 of Insolvency and Ban...