Bombay High Court Partially Sets Aside Arbitral Award in Leave and Licence Dispute — Interest on Security Deposit for Delay Period Not Payable as Liquidated Damages Without Proof of Loss. The court modified the award to limit interest to the actual delay period at the contractual rate, holding that the arbitrator's award of interest for the entire period including post-possession was contrary to the agreement and Section 74 of the Indian Contract Act, 1872.

High Court: Bombay High Court Bench: BOMBAY
  • 19
Judgement Image
Font size:
Print

Case Note & Summary

The case involves a challenge under Section 34 of the Arbitration and Conciliation Act, 1996, to an arbitral award passed by a sole arbitrator in a dispute arising out of a leave and licence agreement dated 17 February 2006. The petitioner, Home Care Retail Marts Pvt. Ltd., was the licensee, and the respondent, Haresh N. Sanghavi, was the licensor. The agreement pertained to commercial premises in a building to be constructed by the respondent at Kandivali West, Mumbai. The respondent was to complete construction within 15 months and hand over possession. The petitioner paid a security deposit. The agreement provided that if possession was delayed beyond 15 months, the respondent would pay interest at 12% per annum on the security deposit for the period of delay. The construction was delayed, and possession was handed over after about 30 months. The petitioner claimed interest on the security deposit for the delay period. The arbitrator awarded interest at 12% per annum on the security deposit for the entire period from the expiry of 15 months until the date of the award, which included both the delay period and the period after possession. The petitioner challenged the award under Section 34, arguing that the interest was payable only for the delay period and not thereafter, and that the award was contrary to the terms of the agreement and the law relating to liquidated damages. The court held that the interest clause was not a penalty but a contractual rate agreed upon by the parties. However, the court found that the arbitrator had erred in awarding interest for the period after possession was handed over, as the agreement only provided for interest during the delay. The court also noted that the arbitrator had not considered whether the petitioner had suffered any loss due to the delay, which was required under Section 74 of the Indian Contract Act, 1872, if the interest was treated as liquidated damages. The court modified the award to limit interest to the actual delay period of 15 months (from the expiry of 15 months to the date of possession) at the contractual rate of 12% per annum, and set aside the award for the remaining period. The petition was partly allowed.

Headnote

A) Arbitration Act - Section 34 - Challenge to Arbitral Award - Leave and Licence Agreement - Interest on Security Deposit - The court considered whether the arbitrator's award of interest on the security deposit for the delay period was contrary to the contract and law. Held that the agreement provided for interest only on the security deposit amount for the delay period, not as liquidated damages but as a contractual rate. However, the court found that the award of interest for the entire delay period without considering the actual loss suffered was contrary to Section 74 of the Indian Contract Act, 1872, as it amounted to a penalty. The court modified the award to limit interest to the period of delay and directed that the interest be calculated at the contractual rate of 12% per annum, but only for the period of delay, and not as a penalty. (Paras 1-10)

B) Contract Act - Section 74 - Liquidated Damages - Penalty - Interest on Security Deposit - The court examined whether the interest clause in the leave and licence agreement was a genuine pre-estimate of damages or a penalty. Held that the interest at 12% per annum on the security deposit for the delay period was not a penalty but a contractual rate agreed upon by the parties. However, the court noted that the arbitrator had not considered whether the claimant had suffered any loss due to the delay, and thus the award of interest for the entire delay period without proof of loss was contrary to Section 74. The court reduced the interest period to the actual delay and confirmed the rate. (Paras 5-8)

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the arbitral award granting interest on the security deposit at 12% per annum for the period of delay in handing over possession of the licensed premises is contrary to the terms of the agreement and/or the law relating to liquidated damages and penalty under the Indian Contract Act, 1872.

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

The court partly allowed the petition. The arbitral award was modified to limit the interest on the security deposit to the period of delay in handing over possession, i.e., from the expiry of 15 months from the date of the agreement until the date of actual possession, at the contractual rate of 12% per annum. The award for interest for the period after possession was set aside. The court held that the interest clause was not a penalty but a contractual rate, but the arbitrator's award for the entire period was contrary to the agreement and Section 74 of the Indian Contract Act, 1872.

Law Points

  • Section 34 of the Arbitration and Conciliation Act
  • 1996
  • Section 73 of the Indian Contract Act
  • 1872
  • Section 74 of the Indian Contract Act
  • liquidated damages
  • penalty
  • interest on security deposit
  • leave and licence agreement
  • public policy
Subscribe to unlock Law Points Subscribe Now

Case Details

2019 LawText (BOM) (02) 45

Arbitration Petition No.715 of 2014

2019-02-11

S.C. Gupte, J.

Mr. Rajiv Kumar, Senior Advocate, a/w. Mr. K.G. Munshi, Ms. Ferzana Behramkamdin, Ms. Shivani Khanna and Ms. Rabab Ghugharia, i/b. FZB & Associates, for the Petitioner. Mr. Joaquim Reis, Senior Advocate, a/w. Mr. Yadunath Chaudhari, Mr. Omkar Kulkarni and Mr. Susmit Phatale, i/b. Ms. Kejal Kamdar, for the Respondent.

Home Care Retail Marts Pvt. Ltd.

Haresh N. Sanghavi

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Challenge to an arbitral award under Section 34 of the Arbitration and Conciliation Act, 1996.

Remedy Sought

The petitioner sought to set aside the arbitral award or modify it to limit interest on the security deposit to the period of delay only.

Filing Reason

The petitioner challenged the arbitral award on the ground that the arbitrator awarded interest on the security deposit for a period beyond the delay period, contrary to the terms of the leave and licence agreement and the law relating to liquidated damages.

Previous Decisions

The sole arbitrator passed an award granting interest at 12% per annum on the security deposit from the expiry of 15 months until the date of the award.

Issues

Whether the arbitral award granting interest on the security deposit for the entire period from the expiry of 15 months until the date of the award is contrary to the terms of the leave and licence agreement? Whether the interest clause in the agreement constitutes liquidated damages or a penalty under Section 74 of the Indian Contract Act, 1872? Whether the award is liable to be set aside or modified under Section 34 of the Arbitration and Conciliation Act, 1996?

Submissions/Arguments

The petitioner argued that the agreement provided for interest only for the period of delay in handing over possession, i.e., from the expiry of 15 months until the date of actual possession, and not thereafter. The arbitrator erred in awarding interest for the entire period until the award. The petitioner further argued that the interest clause was in the nature of liquidated damages and the arbitrator should have considered whether the petitioner suffered any loss due to the delay. Without proof of loss, the award of interest was contrary to Section 74 of the Indian Contract Act, 1872. The respondent contended that the interest clause was a contractual rate agreed upon by the parties and not a penalty. The arbitrator's award was within the terms of the agreement and should not be interfered with.

Ratio Decidendi

The court held that under Section 74 of the Indian Contract Act, 1872, when a contract provides for payment of interest on a sum for delay, such interest is not a penalty if it is a genuine pre-estimate of damages. However, the award of interest must be limited to the period of delay as per the contract. The arbitrator's award of interest for the entire period until the award, including the period after possession, was contrary to the terms of the agreement and the law. The court modified the award to restrict interest to the actual delay period.

Judgment Excerpts

The agreement provided for interest at the rate of 12% per annum on the amount of the security deposit paid by the Petitioner to the Respondent for the period of delay in handing over possession of the licensed premises beyond the aforesaid period of 15 months. The arbitrator has awarded interest on the security deposit at the rate of 12% per annum from the expiry of 15 months from the date of the agreement until the date of the award. The interest clause in the agreement is not a penalty but a contractual rate agreed upon by the parties. However, the award of interest for the entire period until the award, including the period after possession, is contrary to the terms of the agreement. Under Section 74 of the Indian Contract Act, 1872, the court must consider whether the claimant has suffered any loss due to the delay. The arbitrator has not done so. The award is modified to limit interest to the actual delay period.

Procedural History

The petitioner filed Arbitration Petition No.715 of 2014 under Section 34 of the Arbitration and Conciliation Act, 1996, challenging an arbitral award passed by a sole arbitrator. The award was passed in a reference arising out of a leave and licence agreement dated 17 February 2006. The petition was heard by the High Court of Judicature at Bombay and disposed of on 11 February 2019.

Acts & Sections

  • Arbitration and Conciliation Act, 1996: Section 34
  • Indian Contract Act, 1872: Section 73, Section 74
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
High Court Bombay High Court Partly Allows Appeal in Workmen's Compensation Case — Enhances Compensation for Driver's Permanent Disability. Employer and Insurer Held Jointly Liable Under Workmen's Compensation Act, 1923 for 100% Loss of Earning Capacity Due t...
Related Judgement
High Court Bombay High Court Partially Sets Aside Arbitral Award in Leave and Licence Dispute — Interest on Security Deposit for Delay Period Not Payable as Liquidated Damages Without Proof of Loss. The court modified the award to limit interest to the actual...