Case Note & Summary
The case involves a challenge under Section 34 of the Arbitration and Conciliation Act, 1996, to an arbitral award passed by a sole arbitrator in a dispute arising out of a leave and licence agreement dated 17 February 2006. The petitioner, Home Care Retail Marts Pvt. Ltd., was the licensee, and the respondent, Haresh N. Sanghavi, was the licensor. The agreement pertained to commercial premises in a building to be constructed by the respondent at Kandivali West, Mumbai. The respondent was to complete construction within 15 months and hand over possession. The petitioner paid a security deposit. The agreement provided that if possession was delayed beyond 15 months, the respondent would pay interest at 12% per annum on the security deposit for the period of delay. The construction was delayed, and possession was handed over after about 30 months. The petitioner claimed interest on the security deposit for the delay period. The arbitrator awarded interest at 12% per annum on the security deposit for the entire period from the expiry of 15 months until the date of the award, which included both the delay period and the period after possession. The petitioner challenged the award under Section 34, arguing that the interest was payable only for the delay period and not thereafter, and that the award was contrary to the terms of the agreement and the law relating to liquidated damages. The court held that the interest clause was not a penalty but a contractual rate agreed upon by the parties. However, the court found that the arbitrator had erred in awarding interest for the period after possession was handed over, as the agreement only provided for interest during the delay. The court also noted that the arbitrator had not considered whether the petitioner had suffered any loss due to the delay, which was required under Section 74 of the Indian Contract Act, 1872, if the interest was treated as liquidated damages. The court modified the award to limit interest to the actual delay period of 15 months (from the expiry of 15 months to the date of possession) at the contractual rate of 12% per annum, and set aside the award for the remaining period. The petition was partly allowed.
Headnote
A) Arbitration Act - Section 34 - Challenge to Arbitral Award - Leave and Licence Agreement - Interest on Security Deposit - The court considered whether the arbitrator's award of interest on the security deposit for the delay period was contrary to the contract and law. Held that the agreement provided for interest only on the security deposit amount for the delay period, not as liquidated damages but as a contractual rate. However, the court found that the award of interest for the entire delay period without considering the actual loss suffered was contrary to Section 74 of the Indian Contract Act, 1872, as it amounted to a penalty. The court modified the award to limit interest to the period of delay and directed that the interest be calculated at the contractual rate of 12% per annum, but only for the period of delay, and not as a penalty. (Paras 1-10) B) Contract Act - Section 74 - Liquidated Damages - Penalty - Interest on Security Deposit - The court examined whether the interest clause in the leave and licence agreement was a genuine pre-estimate of damages or a penalty. Held that the interest at 12% per annum on the security deposit for the delay period was not a penalty but a contractual rate agreed upon by the parties. However, the court noted that the arbitrator had not considered whether the claimant had suffered any loss due to the delay, and thus the award of interest for the entire delay period without proof of loss was contrary to Section 74. The court reduced the interest period to the actual delay and confirmed the rate. (Paras 5-8)
Issue of Consideration
Whether the arbitral award granting interest on the security deposit at 12% per annum for the period of delay in handing over possession of the licensed premises is contrary to the terms of the agreement and/or the law relating to liquidated damages and penalty under the Indian Contract Act, 1872.
Final Decision
The court partly allowed the petition. The arbitral award was modified to limit the interest on the security deposit to the period of delay in handing over possession, i.e., from the expiry of 15 months from the date of the agreement until the date of actual possession, at the contractual rate of 12% per annum. The award for interest for the period after possession was set aside. The court held that the interest clause was not a penalty but a contractual rate, but the arbitrator's award for the entire period was contrary to the agreement and Section 74 of the Indian Contract Act, 1872.
Law Points
- Section 34 of the Arbitration and Conciliation Act
- 1996
- Section 73 of the Indian Contract Act
- 1872
- Section 74 of the Indian Contract Act
- liquidated damages
- penalty
- interest on security deposit
- leave and licence agreement
- public policy





