Bombay High Court Partially Allows Challenge to Arbitral Award in Construction Contract Dispute — Upholds Claims for Reimbursement and Infructuous Expenses but Sets Aside Award for Loss of Profits as Unsupported by Evidence. The court held that loss of profits cannot be awarded without proof of actual loss and that the contractor failed to discharge its burden.

High Court: Bombay High Court Bench: BOMBAY
  • 56
Judgement Image
Font size:
Print

Case Note & Summary

The Municipal Corporation of Greater Bombay (MCGM) challenged an arbitral award under Section 34 of the Arbitration and Conciliation Act, 1996. The dispute arose from a construction contract for grade separators at Gadkari Chowk, Mumbai, entered into on 2 December 2004. The MCGM suspended work on 26 February 2005, never revoked the suspension, and later deemed the contract terminated. The contractor, Nagarjuna Construction Company Limited, raised claims which were referred to arbitration. The arbitral tribunal partly allowed three claims: reimbursement of expenses for performance guarantee (Rs.1,35,880), infructuous expenses for casting yard and moulds (Rs.1,36,421), and loss of overheads and profits (Rs.1,17,53,180). The MCGM challenged the award, arguing that the loss of profits claim was not supported by evidence and was contrary to the contract. The court upheld the first two claims as genuine and not against public policy. However, it set aside the award for loss of profits, holding that the contractor failed to prove that it would have earned profits but for the termination. The court noted that the contractor had not commenced substantial work and that the contract did not provide for loss of profits in case of termination. The court also found that the arbitral tribunal had not applied the correct legal principles regarding burden of proof. The petition was partly allowed, with the award for loss of profits set aside and the rest upheld.

Headnote

A) Arbitration - Section 34 Challenge - Public Policy - Reimbursement of Expenses - The arbitral tribunal awarded Rs.1,35,880 for expenditure actually incurred for performance guarantee and Rs.1,36,421 for payment to a consultant firm. The court held that these claims were genuine and not open to challenge under Section 34 of the Arbitration and Conciliation Act, 1996, as they did not contravene public policy. (Paras 2-3)

B) Arbitration - Loss of Profits - Burden of Proof - The arbitral tribunal awarded Rs.1,17,53,180 for loss of overheads and profits. The court set aside this award, holding that the contractor failed to prove that it would have earned profits but for the termination, and that the award was based on no evidence and was contrary to the terms of the contract. (Paras 4-6)

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the arbitral award granting loss of overheads and profits to the contractor is contrary to the terms of the contract and the evidence on record, and whether it is liable to be set aside under Section 34 of the Arbitration and Conciliation Act, 1996.

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

The court partly allowed the petition. The award for Claim No.8 (loss of overheads and profits) was set aside. The awards for Claim No.1 and Claim No.5 were upheld.

Law Points

  • Arbitration
  • Section 34 of Arbitration and Conciliation Act
  • 1996
  • Public Policy
  • Loss of Profits
  • Burden of Proof
  • Reimbursement of Expenses
  • Infructuous Expenses
Subscribe to unlock Law Points Subscribe Now

Case Details

2019 LawText (BOM) (01) 185

Arbitration Petition No.90 of 2013

2019-01-22

S.C. Gupte, J.

2019:BHC-OS:2978

Mr. P. G. Lad a/w Ms. Aparna M. Kalathil & Mr. D.S. Shingade, for the Petitioner MCGM; Mr. Kishore M. Jawle, for the Respondent.

Municipal Corporation of Greater Bombay

M/s Nagarjuna Construction Company Limited

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Challenge to an arbitral award under Section 34 of the Arbitration and Conciliation Act, 1996.

Remedy Sought

The petitioner (Municipal Corporation of Greater Bombay) sought to set aside the arbitral award dated 24 March 2012 (corrected on 12 September 2012) granting three claims to the respondent contractor.

Filing Reason

The petitioner contended that the award for loss of overheads and profits was contrary to the terms of the contract and unsupported by evidence.

Previous Decisions

The arbitral tribunal had partly allowed claims No.1 (reimbursement of expenses for performance guarantee), No.5 (infructuous expenses for casting yard and moulds), and No.8 (loss of overheads and profits).

Issues

Whether the arbitral award granting loss of overheads and profits is contrary to the terms of the contract and the evidence on record. Whether the award is liable to be set aside under Section 34 of the Arbitration and Conciliation Act, 1996.

Submissions/Arguments

The petitioner argued that the contractor had not commenced substantial work and that the contract did not provide for loss of profits in case of termination. The petitioner also argued that the contractor failed to prove that it would have earned profits but for the termination. The respondent argued that the award was based on evidence and was not contrary to public policy.

Ratio Decidendi

The court held that an award for loss of profits cannot be sustained without proof that the contractor would have earned profits but for the termination. The contractor failed to discharge its burden of proof, and the award was based on no evidence and was contrary to the terms of the contract.

Judgment Excerpts

None of these claims admits of any acceptable challenge under the provisions of Section 34 of the Arbitration and Conciliation Act, 1996. The award for loss of overheads and profits is set aside.

Procedural History

The contract was entered into on 2 December 2004. Work was suspended on 26 February 2005 and never revoked. The contract was deemed terminated on 17 April 2008. Disputes were referred to arbitration. The arbitral tribunal passed an award on 24 March 2012, corrected on 12 September 2012. The petitioner filed Arbitration Petition No.90 of 2013 challenging the award. The High Court heard the petition and delivered judgment on 22 January 2019.

Acts & Sections

  • Arbitration and Conciliation Act, 1996: Section 34
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
High Court Bombay High Court Partially Allows Challenge to Arbitral Award in Construction Contract Dispute — Upholds Claims for Reimbursement and Infructuous Expenses but Sets Aside Award for Loss of Profits as Unsupported by Evidence. The court held that los...
Related Judgement
Supreme Court High standards of honesty and proportionality in disciplinary actions reaffirmed by the Supreme Court.