Bombay High Court Dismisses Employer's Challenge to Arbitral Award on Royalty Reimbursement. Award's Interpretation of 'Any Further Increase' Clause as Covering Royalty Charges Upheld as Reasonable Under Section 34 of Arbitration and Conciliation Act, 1996.

High Court: Bombay High Court Bench: BOMBAY In Favour of Accused
  • 18
Judgement Image
Font size:
Print

Case Note & Summary

The Maharashtra State Road Development Corporation Ltd. (MSRDC), a Government of Maharashtra undertaking, had awarded a contract for four-laning of a section of National Highway-4 (Satara-Kolhapur up to Maharashtra State Border) to a joint venture comprising Valecha Engineering Ltd. and M/s. M. Venkata Rao. The work was awarded in 2001-2002 and was to be completed by August 2004, but was actually completed on 1 June 2005. During the execution of the work, the Government of Maharashtra increased the royalty charges on minor minerals from Rs.28 to Rs.50 per brass with effect from January 2003. Initially, MSRDC reimbursed the increased royalty to the contractor for the first 49 running account bills. However, from the 50th running bill, MSRDC deducted the entire previously reimbursed amount, interpreting Clause 14 of the Special Conditions of Contract as not covering increased royalty charges. Clause 14, as amended, stated that contractor’s rates were deemed inclusive of sales tax and other taxes, including royalty charges, and also provided for reimbursement of any further increase in Central or State sales tax or other taxes on complete items of work. The contractor contended that the increase in royalty was covered by the reimbursement provision, while MSRDC argued that the second sentence did not specifically mention royalty. The dispute was referred to the Dispute Resolution Committee, which rejected the contractor’s claim, leading to arbitration. The sole arbitrator Shri Sharad P. Upasani, former Chief Secretary of Maharashtra, passed an award on 29 February 2008 in favour of the contractor, holding that the words 'any further increase' covered royalty charges, and awarded Rs.1,16,71,879 principal plus interest at 15% per annum aggregating Rs.1,49,62,774 with further interest. MSRDC challenged the award under Section 34 of the Arbitration and Conciliation Act, 1996, contending that the arbitrator’s interpretation was perverse. The Bombay High Court, after examining the clause, found the arbitrator’s interpretation reasonable and plausible, emphasising that the court’s power under Section 34 is limited and does not permit substitution of its own view merely because another interpretation is possible. The court noted that the two sentences of Clause 14 had to be read together and that the expression 'any further increase' in the second sentence, in light of the first sentence which explicitly included royalty, meant that increased royalty charges were reimbursable. The court held that the award did not suffer from patent illegality or perversity, and accordingly dismissed the arbitration petition and upheld the award, with costs to the respondents.

Headnote

A) Arbitration - Challenge to Award - Limited Judicial Review - Arbitration and Conciliation Act, 1996, Section 34 - Interpretation of Contract Clause - The High Court reiterated that an arbitral award cannot be interfered with lightly; the court does not sit in appeal over the award; if the arbitrator's view is plausible and not patently illegal, it must be upheld. Here, the arbitrator interpreted Clause 14 of the Special Conditions of Contract, which provided for reimbursement of increase in taxes and included 'any further increase' as covering royalty charges despite the absence of express mention in the second sentence; the court found this interpretation reasonable and not perverse, thus dismissing the challenge (Paras 13-16).

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the arbitral award allowing reimbursement of increased royalty charges under Clause 14 of the Special Conditions of Contract was liable to be set aside under Section 34 of the Arbitration and Conciliation Act, 1996

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

The arbitration petition was dismissed. The arbitral award was upheld, and the petitioner was directed to pay the awarded amount along with interest as per the award. Costs were awarded to the respondents.

Law Points

  • limited judicial review under Section 34 of Arbitration and Conciliation Act 1996
  • interpretation of contract clauses
  • reimbursement of increased royalty charges
  • construction of 'any further increase' in taxes including royalty
  • plausible view of arbitrator cannot be substituted
Subscribe to unlock Law Points Subscribe Now

Case Details

2012 LawText (BOM) (08) 59

Arbitration Petition No. 269 of 2008

2012-08-17

Anoop V. Mohta, J.

2012:BHC-OS:10328

Mr. D.D. Madon, Senior Counsel with Mr. P.P. Chavan and Mr. Nooruddin Dhilla i/by Amarchand Mangaldas and S.A. Shroff & Co. for the Petitioners; Mr. K.M. Javle for the Respondents

Maharashtra State Road Development Corporation Ltd. (MSRDC)

Valecha Engineering Ltd., M/s. M. Venkata Rao, Valecha Engineering Ltd. & M/s. M. Venkata Rao J/V

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Challenge under Section 34 of the Arbitration and Conciliation Act, 1996 to an arbitral award granting reimbursement of increased royalty charges under a construction contract.

Remedy Sought

The petitioner MSRDC sought to set aside the arbitral award dated 29 February 2008.

Filing Reason

The petitioner contended that the arbitrator's interpretation of Clause 14, which allowed reimbursement of increased royalty charges, was perverse and contrary to the contract terms.

Previous Decisions

The Sole Arbitrator, Shri Sharad P. Upasani, passed an award on 29 February 2008 in favour of the respondents, awarding Rs.1,49,62,774 with further interest. The Dispute Resolution Committee had earlier rejected the respondents' claims.

Issues

Whether the arbitral award allowing reimbursement of increased royalty charges under Clause 14 of the Special Conditions of Contract was liable to be set aside under Section 34 of the Arbitration and Conciliation Act, 1996.

Submissions/Arguments

Petitioner argued that the second sentence of Clause 14 only mentioned 'other taxes' and did not specifically include 'royalty charges' for increase, thus increased royalty was not reimbursable; the arbitrator's interpretation was perverse. Respondents contended that the clause, read as a whole, intended to cover any increase in all taxes including royalty; the arbitrator's view was plausible and in line with commercial sense.

Ratio Decidendi

Under Section 34 of the Arbitration and Conciliation Act, 1996, the court does not sit in appeal over an arbitral award. An award can be set aside only if it is patently illegal or perverse. If the arbitrator's interpretation of a contract term is plausible and reasonable, the court cannot substitute its own view merely because another interpretation is possible. In this case, the arbitrator's reading of Clause 14, that 'any further increase' in taxes included increased royalty charges, was a plausible interpretation and not perverse, hence the award was upheld.

Judgment Excerpts

The words “any further increase" need to be read in the context of the first basic sentence, in my view, cannot be dissected to state that the words "royalty charges" are missing in the next sentence. It is wrong reading of the whole clause itself. All the materials, as referred in the first sentence, in my view includes "all items of work". Therefore, any increase or revision should follow for all the purposes.

Procedural History

December 2001: Tender invited for four-laning work. February 2002: Letter of acceptance issued. 3 May 2002: Notice to proceed with work issued; completion due by 2 August 2004. January 2003: Government of Maharashtra increased royalty on minor minerals from Rs.28 to Rs.50 per brass. 1 June 2005: Work completed. Prior to April 2006: MSRDC reimbursed increased royalty up to RA Bill No.49, then deducted entire previously reimbursed amount from RA Bill No.50 onwards. 6 April 2006: Respondents gave notice under Clause 67.2 for Steering Committee. After rejection, reference to arbitration. 7 November 2006: Shri Sharad P. Upasani appointed Sole Arbitrator. 29 February 2008: Arbitral Award passed. Thereafter, MSRDC filed Arbitration Petition No. 269 of 2008. 17 August 2012: High Court pronounced judgment dismissing the petition.

Acts & Sections

  • Arbitration and Conciliation Act, 1996: 34
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
Supreme Court Supreme Court Upholds Full Ownership for Widow under Hindu Succession Act, 1956. Widow's Pre-1956 Acquisition via Partition Award Confers Absolute Rights under Section 14(1), Not Restricted Estate under Section 14(2).
Related Judgement
High Court Bombay High Court Dismisses Employer's Challenge to Arbitral Award on Royalty Reimbursement. Award's Interpretation of 'Any Further Increase' Clause as Covering Royalty Charges Upheld as Reasonable Under Section 34 of Arbitration and Conciliation Act...