Bombay High Court Dismisses Arbitration Application for Non-Compliance with Agreed ICC Procedure. Party Must First Exhaust Agreed Institutional Arbitration Procedure Before Seeking Court Appointment Under Section 11(6) of Arbitration and Conciliation Act, 1996.

High Court: Bombay High Court Bench: BOMBAY
  • 72
Judgement Image
Font size:
Print

Case Note & Summary

The applicant, Manish Gunwani, filed an application under Section 11(6) of the Arbitration and Conciliation Act, 1996 seeking appointment of an arbitrator. The arbitration agreement was contained in an employment contract dated 14 August 2007 between the applicant and the respondent, Lehman Brother Securities Pvt. Ltd. The arbitration clause provided that disputes would be resolved by binding arbitration in Mumbai pursuant to the Rules of Arbitration of the International Chamber of Commerce (ICC). The applicant invoked arbitration by a letter dated 3 November 2011. However, the respondent's reply revealed that the applicant had earlier invoked arbitration by a letter dated 16 February 2010, to which the respondent replied on 19 March 2010 stating that it would respond as per ICC Rules. The applicant suppressed these earlier communications. The court noted that under Section 11(6), recourse to the court is available only if a party fails to act as required under the agreed procedure, or if the parties or arbitrators fail to reach an agreement, or if an institution fails to perform its function. Since the parties had agreed to ICC Rules, the applicant should have first approached the ICC. There was no allegation that the ICC failed to act. Relying on The Iron and Steel Company Limited v. M/s. Tiwari Road Lines (AIR 2007 SC 2064), the court held that the application was premature and not maintainable. The court dismissed the application with no order as to costs.

Headnote

A) Arbitration Law - Appointment of Arbitrator - Section 11(6) Arbitration and Conciliation Act, 1996 - Agreed Procedure - Where parties have agreed to arbitration under ICC Rules, the applicant must first invoke that procedure and demonstrate failure of the institution to act before approaching the court under Section 11(6). The court held that since the applicant suppressed earlier correspondence and did not show that the ICC failed to act, the application was not maintainable. (Paras 1-3)

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether an application under Section 11(6) of the Arbitration and Conciliation Act, 1996 is maintainable when the parties have agreed to an institutional arbitration procedure under the ICC Rules and the applicant has not first taken recourse to that procedure.

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

The court dismissed the arbitration application with no order as to costs, holding that the applicant must first take recourse to the agreed procedure under the ICC Rules before approaching the court under Section 11(6).

Law Points

  • Arbitration agreement
  • Section 11(6) Arbitration and Conciliation Act
  • 1996
  • ICC Rules
  • Agreed procedure
  • Failure to act
  • Exhaustion of remedy
Subscribe to unlock Law Points Subscribe Now

Case Details

2012 LawText (BOM) (06) 47

Arbitration Application No.251 of 2011

2012-06-29

Dr. D.Y. Chandrachud, J.

Mr. G.S. Rao i/by Lex Consultus for applicant; Mr. Rohan Rajadhyaksha with Mr. Ankur Kashyap i/by AZB and Partners for respondent

Manish Gunwani

Lehman Brother Securities Pvt. Ltd.

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Application under Section 11(6) of the Arbitration and Conciliation Act, 1996 for appointment of an arbitrator.

Remedy Sought

The applicant sought appointment of an arbitrator by the court.

Filing Reason

The applicant invoked arbitration but the respondent did not agree to the appointment, leading to the application.

Previous Decisions

The applicant had earlier invoked arbitration by letter dated 16 February 2010, to which the respondent replied on 19 March 2010 stating it would respond as per ICC Rules. These communications were suppressed in the application.

Issues

Whether the application under Section 11(6) is maintainable when the parties have agreed to an institutional arbitration procedure under ICC Rules and the applicant has not first taken recourse to that procedure.

Submissions/Arguments

Applicant: Invoked arbitration and filed application under Section 11(6) for appointment of arbitrator. Respondent: The arbitration agreement provides for ICC Rules; the applicant must first approach the ICC; the application is premature.

Ratio Decidendi

Where parties have agreed to a procedure for appointment of an arbitrator, an application under Section 11(6) is maintainable only if a party fails to act as required under that procedure, or if the parties or arbitrators fail to reach an agreement, or if an institution fails to perform its function. The applicant must first exhaust the agreed procedure before seeking court intervention.

Judgment Excerpts

Where a procedure has been agreed upon between the parties to an arbitration agreement, recourse can be taken to the provisions of Section 11(6) only where : (a) a party fails to act as required under that procedure; or (b) the parties or the two appointed arbitrators fail to reach an agreement expected of them under that procedure; or (c) a person, including an institution, fails to perform any function entrusted to him or it under that procedure.

Procedural History

The applicant filed an arbitration application under Section 11(6) on 3 November 2011. The respondent filed an affidavit-in-reply revealing earlier correspondence. The court heard the matter and dismissed the application on 29 June 2012.

Acts & Sections

  • Arbitration and Conciliation Act, 1996: Section 11(6)
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
High Court Bombay High Court Allows Revision Application in Suit for Declaration and Injunction — Plaint Ordered to be Returned for Presentation to Proper Court Due to Lack of Territorial Jurisdiction. The court held that the City Civil Court at Dindoshi lack...
Related Judgement
High Court Bombay High Court Dismisses Arbitration Application for Non-Compliance with Agreed ICC Procedure. Party Must First Exhaust Agreed Institutional Arbitration Procedure Before Seeking Court Appointment Under Section 11(6) of Arbitration and Conciliation...