Case Note & Summary
The judgment concerns two cross-suits between M/s. Shanti Builders (a building contractor) and CIBA Industrial Workers' Co-op. Housing Society Ltd. (the society) arising out of a construction agreement dated 13th March 1978. The contractor filed Suit No.1574 of 1980 seeking a declaration that the agreement was valid and subsisting, specific performance of the agreement, and in the alternative, damages for construction work carried out. The society filed Suit No.1301 of 1981 seeking termination of the agreement on grounds of breach by the contractor and claiming damages of Rs.3,37,000/- for defective work and cost of completion. The parties had previously entered into agreements on 24th June 1974, 7th August 1975, and 13th March 1978, the last of which constituted a novation. The contractor claimed he completed the second slab of building A-1 but the society failed to transfer a plot of land agreed in lieu of fees. The society contended that the contractor failed to complete electrical wiring of 80 flats, cast the second slab, and complete building C-1, requiring the society to get the work done at additional cost, and that the contractor was paid in excess for defective work. The society also challenged the validity of the notice under Section 164 of the Maharashtra Co-operative Societies Act, 1960 issued by the contractor before filing suit. The court framed issues based on pleadings. After analyzing evidence, the court held that both parties committed breaches of reciprocal promises. The contractor failed to prove readiness and willingness for specific performance. The society's claim for damages was partly allowed, and the contractor's suit was dismissed. The notice under Section 164 was held valid. The court decreed the society's suit for damages and dismissed the contractor's suit.
Headnote
A) Contract Law - Novation - Reciprocal Promises - Agreement dated 13th March 1978 constituted novation of earlier agreements - Parties disputed breaches of reciprocal promises - Court examined performance and breach by both sides - Held that both parties failed to perform their respective obligations, leading to mutual breach (Paras 1-5). B) Specific Performance - Readiness and Willingness - Contractor claimed specific performance but failed to prove continuous readiness and willingness - Society also breached by not transferring plot - Court held that specific performance cannot be granted when both parties are in breach and contractor did not show readiness (Paras 6-10). C) Damages - Breach of Contract - Society claimed damages for defective work and cost of completion - Contractor claimed damages for non-transfer of plot - Court assessed evidence and awarded damages to society for cost of completing work and defective work, rejecting contractor's claim (Paras 11-15). D) Co-operative Societies - Notice under Section 164 - Validity - Contractor issued notice dated 7th January 1980 under Section 164 of Maharashtra Co-operative Societies Act, 1960 - Society challenged validity - Court held notice was valid and proper, as it complied with requirements (Paras 16-18).
Issue of Consideration
Whether the agreement dated 13th March 1978 is valid and subsisting; whether the contractor is entitled to specific performance; whether the society is entitled to damages for breach; whether the notice under Section 164 of the Maharashtra Co-operative Societies Act, 1960 is valid.
Final Decision
The court dismissed Suit No.1574 of 1980 filed by the contractor and decreed Suit No.1301 of 1981 filed by the society for damages. The society was awarded damages as claimed, with interest. The notice under Section 164 was held valid.
Law Points
- Novation of contract
- reciprocal promises
- breach of contract
- specific performance
- damages
- notice under Section 164 of Maharashtra Co-operative Societies Act
- 1960
- readiness and willingness





