Case Note & Summary
The Petitioner, Guruashish Construction Pvt. Ltd., a builder and developer, entered into a tripartite Joint Development Agreement dated 10 April 2008 with the Maharashtra Housing and Area Development Authority (MHADA) and Goregaon Siddharth Nagar Sahakari Grahanirman Sanstha Limited (the Sanstha) for development of a piece of land occupied by members of the Sanstha who were erstwhile tenants of MHADA. Under the agreement, the Petitioner was required to provide housing to individual members. The Petitioner executed 648 individual 'Shifting Agreements' with each member for shifting them from their current occupation to temporary alternate accommodation. These agreements expressly provided that a separate agreement for permanent alternate accommodation would be executed in future, which would be treated as the 'principal document' for payment of appropriate stamp duty. The Petitioner presented the Shifting Agreements for adjudication of stamp duty before the Collector of Stamps, Borivali. By order dated 16 October 2010, the Collector adjudicated the stamp duty at a certain amount. However, the Collector subsequently issued a show cause notice and, by order dated 5 March 2012, reviewed his earlier order and held that the Shifting Agreements should be treated as 'Agreements for alternate accommodation' under Article 25(d) of the Bombay Stamp Act, 1958, and fixed market value and stamp duty accordingly, directing the Petitioner to deposit the duty within 30 days. The Petitioner challenged this order by way of a writ petition. The High Court considered whether the Collector had the power to review his own order and whether the Shifting Agreements were liable to stamp duty under Article 25(d). The Court noted that the Bombay Stamp Act, 1958 does not confer any power of review on the Collector. The Court also examined the nature of the Shifting Agreements and found that they were only for temporary shifting and not for permanent alternate accommodation. The agreements themselves stated that a separate agreement for permanent accommodation would be executed later and would be the principal document for stamp duty. Therefore, the Shifting Agreements could not be treated as 'Agreements for alternate accommodation' under Article 25(d). The Court held that the impugned order was without jurisdiction and liable to be quashed. The Court allowed the petition, quashed the order dated 5 March 2012, and restored the earlier order dated 16 October 2010.
Headnote
A) Stamp Duty - Shifting Agreement - Temporary Alternate Accommodation - Bombay Stamp Act, 1958, Article 25(d) - The Petitioner, a builder, executed 'Shifting Agreements' with members of a housing society for temporary alternate accommodation during redevelopment of MHADA property. The Collector of Stamps reviewed his earlier order and held these agreements liable to stamp duty under Article 25(d) as 'Agreements for alternate accommodation'. The High Court quashed the order, holding that the Shifting Agreements were only for temporary shifting and not for permanent alternate accommodation, and the principal document for stamp duty was the future agreement for permanent accommodation. The Court also held that the Collector had no power of review under the Act. (Paras 2-10)
Issue of Consideration
Whether the 'Shifting Agreements' executed by the Petitioner with tenement holders for temporary alternate accommodation during redevelopment of MHADA property are liable to stamp duty under Article 25(d) of the Bombay Stamp Act, 1958 as 'Agreements for alternate accommodation'.
Final Decision
The High Court allowed the writ petition, quashed the order dated 5 March 2012 passed by the Collector of Stamps, Borivali, and restored the earlier order dated 16 October 2010. Rule made absolute accordingly.
Law Points
- Stamp duty
- Shifting Agreement
- Alternate accommodation
- Bombay Stamp Act
- 1958
- Article 25(d)
- Review jurisdiction
- Collector of Stamps
- MHADA redevelopment





