Bombay High Court Quashes Stamp Duty Demand on Shifting Agreements in MHADA Redevelopment Project — Collector of Stamps Lacked Review Power and Agreements Were for Temporary Shifting, Not Permanent Alternate Accommodation Under Article 25(d) of Bombay Stamp Act, 1958.

High Court: Bombay High Court Bench: BOMBAY In Favour of Accused
  • 2
Judgement Image
Font size:
Print

Case Note & Summary

The Petitioner, Guruashish Construction Pvt. Ltd., a builder and developer, entered into a tripartite Joint Development Agreement dated 10 April 2008 with the Maharashtra Housing and Area Development Authority (MHADA) and Goregaon Siddharth Nagar Sahakari Grahanirman Sanstha Limited (the Sanstha) for development of a piece of land occupied by members of the Sanstha who were erstwhile tenants of MHADA. Under the agreement, the Petitioner was required to provide housing to individual members. The Petitioner executed 648 individual 'Shifting Agreements' with each member for shifting them from their current occupation to temporary alternate accommodation. These agreements expressly provided that a separate agreement for permanent alternate accommodation would be executed in future, which would be treated as the 'principal document' for payment of appropriate stamp duty. The Petitioner presented the Shifting Agreements for adjudication of stamp duty before the Collector of Stamps, Borivali. By order dated 16 October 2010, the Collector adjudicated the stamp duty at a certain amount. However, the Collector subsequently issued a show cause notice and, by order dated 5 March 2012, reviewed his earlier order and held that the Shifting Agreements should be treated as 'Agreements for alternate accommodation' under Article 25(d) of the Bombay Stamp Act, 1958, and fixed market value and stamp duty accordingly, directing the Petitioner to deposit the duty within 30 days. The Petitioner challenged this order by way of a writ petition. The High Court considered whether the Collector had the power to review his own order and whether the Shifting Agreements were liable to stamp duty under Article 25(d). The Court noted that the Bombay Stamp Act, 1958 does not confer any power of review on the Collector. The Court also examined the nature of the Shifting Agreements and found that they were only for temporary shifting and not for permanent alternate accommodation. The agreements themselves stated that a separate agreement for permanent accommodation would be executed later and would be the principal document for stamp duty. Therefore, the Shifting Agreements could not be treated as 'Agreements for alternate accommodation' under Article 25(d). The Court held that the impugned order was without jurisdiction and liable to be quashed. The Court allowed the petition, quashed the order dated 5 March 2012, and restored the earlier order dated 16 October 2010.

Headnote

A) Stamp Duty - Shifting Agreement - Temporary Alternate Accommodation - Bombay Stamp Act, 1958, Article 25(d) - The Petitioner, a builder, executed 'Shifting Agreements' with members of a housing society for temporary alternate accommodation during redevelopment of MHADA property. The Collector of Stamps reviewed his earlier order and held these agreements liable to stamp duty under Article 25(d) as 'Agreements for alternate accommodation'. The High Court quashed the order, holding that the Shifting Agreements were only for temporary shifting and not for permanent alternate accommodation, and the principal document for stamp duty was the future agreement for permanent accommodation. The Court also held that the Collector had no power of review under the Act. (Paras 2-10)

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the 'Shifting Agreements' executed by the Petitioner with tenement holders for temporary alternate accommodation during redevelopment of MHADA property are liable to stamp duty under Article 25(d) of the Bombay Stamp Act, 1958 as 'Agreements for alternate accommodation'.

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

The High Court allowed the writ petition, quashed the order dated 5 March 2012 passed by the Collector of Stamps, Borivali, and restored the earlier order dated 16 October 2010. Rule made absolute accordingly.

Law Points

  • Stamp duty
  • Shifting Agreement
  • Alternate accommodation
  • Bombay Stamp Act
  • 1958
  • Article 25(d)
  • Review jurisdiction
  • Collector of Stamps
  • MHADA redevelopment
Subscribe to unlock Law Points Subscribe Now

Case Details

2012 LawText (BOM) (04) 22

WRIT PETITION NO. 842 OF 2012

2012-04-17

A.A. Sayed

Mr. Raju Subramanium with Mr. A.Joshi and Mr. Atul Kshatriya i/by M/s. Markant Gandhi & Co. for the Petitioner; Mr. G.W. Mattos, AGP., for the Respondents.

Guruashish Construction Pvt. Ltd.

The Collector of Stamp & Anr.

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Writ petition challenging an order of the Collector of Stamps reviewing his earlier order and imposing stamp duty on Shifting Agreements under Article 25(d) of the Bombay Stamp Act, 1958.

Remedy Sought

The Petitioner sought quashing of the order dated 5 March 2012 passed by the Collector of Stamps, Borivali, and restoration of the earlier order dated 16 October 2010.

Filing Reason

The Collector of Stamps reviewed his earlier order and held that the 'Shifting Agreements' executed by the Petitioner with tenement holders were 'Agreements for alternate accommodation' liable to stamp duty under Article 25(d) of the Bombay Stamp Act, 1958, and directed payment of stamp duty.

Previous Decisions

The Collector of Stamps, Borivali, by order dated 16 October 2010, adjudicated the stamp duty on the Shifting Agreements. Subsequently, by order dated 5 March 2012, the Collector reviewed and set aside the earlier order, holding the agreements liable under Article 25(d).

Issues

Whether the Collector of Stamps has the power to review his own order under the Bombay Stamp Act, 1958? Whether the 'Shifting Agreements' executed by the Petitioner for temporary alternate accommodation are liable to stamp duty under Article 25(d) of the Bombay Stamp Act, 1958 as 'Agreements for alternate accommodation'?

Submissions/Arguments

The Petitioner argued that the Shifting Agreements were only for temporary shifting and not for permanent alternate accommodation, and the principal document for stamp duty was the future agreement for permanent accommodation. The Collector had no power of review under the Act. The Respondents argued that the Shifting Agreements were agreements for alternate accommodation and liable to stamp duty under Article 25(d).

Ratio Decidendi

The Bombay Stamp Act, 1958 does not confer any power of review on the Collector of Stamps. The 'Shifting Agreements' were only for temporary shifting and not for permanent alternate accommodation, and therefore could not be treated as 'Agreements for alternate accommodation' under Article 25(d) of the Act. The impugned order was without jurisdiction.

Judgment Excerpts

By the impugned order, the Respondent No. 1 – Collector of Stamps, Borivali, has reviewed his order dated 16 October 2010 and held that the 'Shifting Agreements' between the Petitioner and tenement holders be treated as 'Agreements for alternate accommodation' and has fixed the market value and the stamp duty payable under Article 25(d) of the Bombay Stamp Act, 1958. The 'Shifting Agreement' provide for a separate Agreement to be executed in future for alternate permanent accommodation. This Agreement for alternate permanent accommodation was agreed in the 'Shifting Agreement' to be treated as the 'principal document' for payment of appropriate stamp duty.

Procedural History

The Petitioner executed 648 Shifting Agreements with members of the Sanstha. The Petitioner presented the agreements for adjudication of stamp duty before the Collector of Stamps, Borivali. The Collector passed an order on 16 October 2010 adjudicating stamp duty. Subsequently, the Collector issued a show cause notice and passed the impugned order on 5 March 2012 reviewing the earlier order and imposing stamp duty under Article 25(d). The Petitioner filed the present writ petition on 17 April 2012, which was heard and disposed of on the same day.

Acts & Sections

  • Bombay Stamp Act, 1958: Article 25(d)
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
High Court Bombay High Court Quashes Stamp Duty Demand on Shifting Agreements in MHADA Redevelopment Project — Collector of Stamps Lacked Review Power and Agreements Were for Temporary Shifting, Not Permanent Alternate Accommodation Under Article 25(d) of Bom...
Related Judgement
High Court Bombay High Court Grants Interim Injunction in Copyright Infringement Case Over Hair Colour Product Trade Dress. L'Oreal's artistic work in label/trade dress held entitled to protection against alleged imitation by Henkel.