Bombay High Court Allows Employer's Challenge to Compensation Order in Workmen's Compensation Case — Employer Not Liable for Interest on Delayed Payment as Delay Was Due to Court Proceedings. Commissioner's Order for Interest Under Section 4A(3) of Workmen's Compensation Act, 1923 Set Aside as Employer Had Deposited Amount Within Time.

High Court: Bombay High Court Bench: AURANGABAD In Favour of Accused
  • 58
Judgement Image
Font size:
Print

Case Note & Summary

The petitioner, Shrikrishna Saw Mill, through its proprietor Rasiklal Walji Patel, filed a writ petition challenging an order dated 09-02-2010 passed by the Commissioner for Workmen's Compensation, Labour Court, Jalgaon in Misc. W.C.A. No. 7 of 2005. The impugned order rejected the petitioner's applications (Exhibits U-16 and U-20) seeking to set aside the award of interest under Section 4A(3) of the Workmen's Compensation Act, 1923. The respondent No.2, Sadashiv Shankar Suryawanshi, an employee, had suffered an injury during employment and claimed compensation. The Commissioner had earlier awarded compensation of Rs.1,04,400/- with interest at 12% per annum from the date of accident till deposit. The petitioner deposited the principal amount within one month of the accident, but the interest component was disputed. The petitioner argued that the delay in payment of compensation was not attributable to them but to the court proceedings, and that they had deposited the amount within the prescribed period under Section 4A(1) of the Act. The respondent No.2 contended that the employer was liable to pay interest as per Section 4A(3) for delayed payment. The court analyzed Section 4A of the Act, which requires the employer to pay compensation within one month of the accident falling due, and if delayed, the Commissioner may direct payment of interest and penalty after giving the employer an opportunity of being heard. The court found that the employer had deposited the principal amount within one month of the accident, and the delay in payment of the interest component was due to the pendency of the proceedings before the Commissioner. The court held that the Commissioner had not given any opportunity to the employer to show cause before imposing interest, and the delay was not attributable to the employer. Therefore, the order imposing interest was set aside, and the petition was allowed. The rule was made absolute with no order as to costs.

Headnote

A) Workmen's Compensation - Interest under Section 4A(3) - Employer's Liability - The Commissioner awarded interest on compensation amount from the date of accident till deposit, but the employer had deposited the amount within one month of the accident and the delay in payment was due to court proceedings - Held that interest cannot be imposed when the employer was not at fault and the delay was attributable to the judicial process (Paras 2-5).

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the Commissioner for Workmen's Compensation was justified in awarding interest under Section 4A(3) of the Workmen's Compensation Act, 1923 on the compensation amount when the employer had deposited the amount within the prescribed period and the delay was occasioned due to court proceedings?

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

The writ petition is allowed. The impugned order dated 09-02-2010 passed by the Commissioner for Workmen's Compensation, Labour Court, Jalgaon below Exhibits U-16 and U-20 in Misc. W.C.A. No. 7 of 2005 is set aside. The award of interest under Section 4A(3) of the Workmen's Compensation Act, 1923 is quashed. Rule made absolute with no order as to costs.

Law Points

  • Interest under Section 4A(3) of Workmen's Compensation Act
  • 1923 is not automatic
  • employer must be given opportunity to show cause before imposing penalty or interest
  • delay due to court proceedings is not attributable to employer
Subscribe to unlock Law Points Subscribe Now

Case Details

2011 LawText (BOM) (12) 12

Writ Petition No. 2845 of 2011

2011-12-12

S.S. SHINDE, J.

Mr. Vijay B. Patil for petitioner; Mr. N.R. Shaikh, AGP for respondent No.1; Mr. A.S. Bayas for respondent No.2

Shrikrishna Saw Mill, Dharangaon, through its proprietor, Shri. Rasiklal Walji Patel

1. The State of Maharashtra, Through Tahsildar, Dharangaon, Dist. Jalgaon; 2. Sadashiv Shankar Suryawanshi

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Writ petition challenging order of Commissioner for Workmen's Compensation rejecting applications to set aside award of interest under Section 4A(3) of Workmen's Compensation Act, 1923.

Remedy Sought

Petitioner sought to set aside the order dated 09-02-2010 rejecting Exhibits U-16 and U-20 and to quash the award of interest.

Filing Reason

The Commissioner awarded interest on compensation amount from date of accident till deposit, but petitioner had deposited principal amount within one month of accident and delay was due to court proceedings.

Previous Decisions

Commissioner for Workmen's Compensation, Labour Court, Jalgaon passed order dated 09-02-2010 rejecting petitioner's applications (Exhibits U-16 and U-20) seeking to set aside the award of interest.

Issues

Whether the Commissioner was justified in awarding interest under Section 4A(3) of the Workmen's Compensation Act, 1923 when the employer had deposited the compensation amount within the prescribed period and the delay was due to court proceedings? Whether the employer is liable to pay interest for the period during which the matter was pending before the Commissioner?

Submissions/Arguments

Petitioner argued that the principal amount was deposited within one month of the accident and the delay in payment of interest was due to court proceedings, not attributable to the employer. Respondent No.2 argued that the employer is liable to pay interest under Section 4A(3) for delayed payment of compensation.

Ratio Decidendi

Interest under Section 4A(3) of the Workmen's Compensation Act, 1923 cannot be imposed automatically; the employer must be given an opportunity of being heard before imposing interest or penalty. If the employer deposits the compensation amount within the prescribed period and the delay in payment is attributable to court proceedings, the employer is not liable for interest.

Judgment Excerpts

It is not in dispute that the petitioner deposited the amount of compensation within one month from the date of accident. The Commissioner has not given any opportunity to the petitioner to show cause before imposing interest. The delay in payment of compensation was not attributable to the petitioner but to the court proceedings.

Procedural History

The employee (respondent No.2) filed a claim for compensation under the Workmen's Compensation Act, 1923. The Commissioner awarded compensation of Rs.1,04,400/- with interest at 12% per annum from the date of accident till deposit. The employer deposited the principal amount within one month of the accident. The employer filed applications (Exhibits U-16 and U-20) seeking to set aside the award of interest, which were rejected by the Commissioner on 09-02-2010. The employer then filed the present writ petition before the High Court.

Acts & Sections

  • Workmen's Compensation Act, 1923: Section 4A, Section 4A(1), Section 4A(3)
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
High Court Bombay High Court Allows Employer's Challenge to Compensation Order in Workmen's Compensation Case — Employer Not Liable for Interest on Delayed Payment as Delay Was Due to Court Proceedings. Commissioner's Order for Interest Under Section 4A(3) of...
Related Judgement
High Court High Court of Karnataka Dismisses Petition Seeking to Exclude MLAs/MPs from Voting in Mayor Election. Writ of mandamus refused as petitioners failed to show any legal bar preventing legislators from voting in municipal corporation mayoral elections.