High Court of Bombay at Goa Dismisses Appeal in Contract for Supply of Rails — Upholds Decree for Recovery of Amount for Short Supply. Appellant liable to pay Rs.2,71,873/- with interest at 10% per annum from 15-12-1987 for short supply of 16.263 metric tonnes of rails.

High Court: Bombay High Court Bench: GOA In Favour of Prosecution
  • 5
Judgement Image
Font size:
Print

Case Note & Summary

The respondent, State of Goa through the Executive Engineer, filed a suit for recovery of Rs.2,71,873/- against the appellant, M/s. H. L. Nathurmal, for short supply of rails. The appellant had placed an order for 100 metric tonnes of rails at Rs.16,707/- per metric tonne and paid Rs.16,70,700/-. However, only 83.737 metric tonnes were supplied, leaving a shortfall of 16.263 metric tonnes. The appellant admitted short supply but disputed the measurement method. The trial court decreed the suit with interest at 10% per annum from 15-12-1987. The appellant appealed, arguing that the delivery challans conclusively showed the quantity and that no interest was demanded before suit. The High Court, after considering the evidence, found that the appellant failed to prove that the measurement was not as per the agreement. The court noted that the appellant did not lead any evidence to show that the weight was to be calculated differently. The court also held that interest was justified as the amount was due. The appeal was dismissed with no order as to costs.

Headnote

A) Contract Law - Supply of Goods - Short Supply - Recovery of Amount - The respondent filed a suit for recovery of Rs.2,71,873/- for short supply of 16.263 metric tonnes of rails out of 100 metric tonnes ordered. The appellant disputed the manner of measurement but admitted short supply. The trial court decreed the suit. On appeal, the High Court held that the appellant failed to prove that the measurement was not as per agreement and upheld the decree. (Paras 2-5)

B) Interest - Pre-suit Interest - No Demand - The appellant contended that no interest was demanded before suit. However, the court held that interest at 10% per annum from the date of payment (15-12-1987) was justified as the amount was due and payable. (Para 5)

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the appellant is liable to pay the amount claimed by the respondent for short supply of rails and whether the interest awarded is justified.

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

Appeal dismissed. Decree of trial court upheld. No order as to costs.

Law Points

  • Contract for supply of goods
  • short supply
  • recovery of amount
  • interest
  • burden of proof
  • measurement of goods
Subscribe to unlock Law Points Subscribe Now

Case Details

2011 LawText (BOM) (07) 23

First Appeal No. 85 of 2006

2011-07-21

F. M. Reis

Shri V. Menezes for Appellant, Shri S. Vahidulla for Respondent

M/s. H. L. Nathurmal

State of Goa, through the Executive Engineer, Stores and Workshops, Div. II, Electricity Department, Government of Goa, Panaji

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Civil appeal against decree for recovery of amount for short supply of rails.

Remedy Sought

Appellant sought setting aside of decree directing payment of Rs.2,71,873/- with interest.

Filing Reason

Appellant aggrieved by decree of trial court holding them liable for short supply.

Previous Decisions

Trial court decreed suit in favor of respondent on 21-4-2005.

Issues

Whether the appellant is liable to pay the amount claimed for short supply of rails? Whether the interest awarded at 10% per annum from 15-12-1987 is justified?

Submissions/Arguments

Appellant argued that delivery challans conclusively disclosed quantity and measurement was not as per agreement. Appellant argued no demand for interest before suit, so interest should not be granted from 15-12-1987.

Ratio Decidendi

The appellant admitted short supply but failed to prove that measurement was not as per agreement. The burden was on the appellant to show that the weight was to be calculated differently, which they did not discharge. Interest was justified as the amount was due.

Judgment Excerpts

The Appellants were liable to supply 100 metric tonnes of the rails but, however, only 83.737 metric tonnes were supplied by the Respondents to the Appellants. The learned Judge by Judgment and Decree dated 21-4-2005 decreed the suit filed by the Respondents and directed the Appellants to pay the said amount of Rs.2,71,873/- together with interest thereon at the rate of 10% per annum from 15-12-1987 upto the date of actual payment.

Procedural History

Respondent filed Civil Suit No.164 of 2004 in the Court of Additional District Judge at Panaji for recovery of Rs.2,71,873/-. Trial court decreed suit on 21-4-2005. Appellant filed First Appeal No.85 of 2006 in the High Court of Bombay at Goa. High Court dismissed appeal on 21-7-2011.

Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
High Court Bombay High Court Dismisses Petition of Railway Driver Challenging Revision of Penalty from Reversion to Removal. Revision under Rule 25(1) of Railway Service (Discipline and Appeal) Rules, 1968 Upheld as Valid and Procedurally Fair.
Related Judgement
High Court High Court of Bombay at Goa Dismisses Appeal in Contract for Supply of Rails — Upholds Decree for Recovery of Amount for Short Supply. Appellant liable to pay Rs.2,71,873/- with interest at 10% per annum from 15-12-1987 for short supply of 16.263 m...