Bombay High Court Dismisses Union of India's Challenge to Arbitral Award on Loss of Profit and Interest in Railway Contract Dispute. Court Upholds 5% Loss of Profit on Withdrawn Work and 9% Interest as Reasonable and Within Tribunal's Discretion Under Section 34 of Arbitration and Conciliation Act, 1996.

High Court: Bombay High Court Bench: BOMBAY
  • 7
Judgement Image
Font size:
Print

Case Note & Summary

The case involves two arbitration petitions under Section 34 of the Arbitration and Conciliation Act, 1996, challenging a common arbitral award dated 30th May 2007. The Union of India (Western Railway) challenged the award primarily on the grant of loss of profit and interest, while the original claimant, M/s. R.P. Shah, challenged the award on the ground that compensation for loss of profit was only 5% instead of 10%. The background is that the claimant was a civil contractor for railway work, and the contract was terminated. The claimant did not accept further extension due to changed conditions, leading to closure. The claimant's representation for loss of profit was contested. Earlier, this Court had set aside a previous award for lack of justification for not granting compensation for loss of profit and denial of interest. The Arbitral Tribunal reheard claims 9 and 16. The Tribunal awarded 5% loss of profit on the withdrawn work and interest at 9% per annum from the date of award till payment. The Court held that the award was reasoned and based on evidence. The Tribunal's discretion on quantum of loss of profit was not interfered with as it was not perverse. The interest rate was also found reasonable. Both petitions were dismissed, upholding the award.

Headnote

A) Arbitration - Loss of Profit - Section 34 Arbitration and Conciliation Act, 1996 - Claimant entitled to loss of profit for breach of contract due to termination - Arbitral Tribunal awarded 5% on withdrawn work, which was not interfered with as it was based on evidence and not perverse - Held that the Tribunal's discretion on quantum of loss of profit is not open to challenge unless patently illegal (Paras 5-10).

B) Arbitration - Interest - Section 31(7)(a) Arbitration and Conciliation Act, 1996 - Arbitral Tribunal granted interest at 9% per annum from date of award till payment - Held that interest is discretionary and the rate is reasonable, no interference warranted (Paras 11-13).

C) Arbitration - Section 34 Challenge - Scope of Interference - Court cannot re-appreciate evidence or substitute its own view unless award is against public policy or perverse - Held that the award was reasoned and within the Tribunal's jurisdiction (Paras 14-16).

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the Arbitral Tribunal's award of 5% loss of profit on withdrawn work and grant of interest is sustainable under Section 34 of the Arbitration and Conciliation Act, 1996

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

Both arbitration petitions are dismissed. The common award dated 30th May 2007 is upheld. No order as to costs.

Law Points

  • Loss of profit is recoverable for breach of contract
  • Arbitral Tribunal must provide reasons for award
  • Interest under Section 31(7)(a) of Arbitration and Conciliation Act
  • 1996 is discretionary
  • Court's interference under Section 34 is limited to patent illegality or perversity
Subscribe to unlock Law Points Subscribe Now

Case Details

2011 LawText (BOM) (02) 58

Arbitration Petition No. 431 of 2007 and Arbitration Petition No. 398 of 2007

2011-02-09

Anoop V. Mohta, J.

Mr. Suresh Kumar with Ms. Nilam Jadhav for Petitioner in Arbitration Petition No. 431 of 2007 and for Respondents in Arbitration Petition No. 398 of 2007; Mr. U.S. Samudrala for Respondent in Arbitration Petition No. 431 of 2007 and for Petitioners in Arbitration Petition No. 398 of 2007

Union of India (in Arbitration Petition No. 431 of 2007); M/s. R.P. Shah (in Arbitration Petition No. 398 of 2007)

M/s. R.P. Shah (in Arbitration Petition No. 431 of 2007); Union of India and others (in Arbitration Petition No. 398 of 2007)

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Challenges to an arbitral award under Section 34 of the Arbitration and Conciliation Act, 1996

Remedy Sought

Union of India sought setting aside of award granting loss of profit and interest; M/s. R.P. Shah sought enhancement of loss of profit from 5% to 10%

Filing Reason

Dissatisfaction with the arbitral award dated 30th May 2007 regarding quantum of loss of profit and interest

Previous Decisions

Earlier award between same parties was set aside by this Court on 6th September 2005 for lack of justification for not granting compensation for loss of profit and denial of interest

Issues

Whether the Arbitral Tribunal's award of 5% loss of profit on withdrawn work is sustainable? Whether the grant of interest at 9% per annum from date of award till payment is proper?

Submissions/Arguments

Union of India argued that loss of profit and interest should not have been granted as the contract was terminated due to claimant's fault. M/s. R.P. Shah argued that loss of profit should be 10% as per standard practice, not 5%.

Ratio Decidendi

The Arbitral Tribunal's discretion on quantum of loss of profit and interest is not open to interference under Section 34 unless patently illegal or perverse. The award was reasoned and based on evidence, hence upheld.

Judgment Excerpts

The learned Arbitral Tribunal, therefore, reheard original claim Nos. 9 and 16. The basic facts are not in dispute. There is also no dispute that the Arbitral Tribunal on earlier occasion not considered the aspect of loss of profit as the work was terminated.

Procedural History

Earlier arbitration petitions between same parties were allowed on 6th September 2005, setting aside the previous award. The Arbitral Tribunal reheard claims 9 and 16 and passed the common award dated 30th May 2007. Both parties filed separate petitions under Section 34 challenging the award.

Acts & Sections

  • Arbitration and Conciliation Act, 1996: Section 34, Section 31(7)(a)
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
Supreme Court Supreme Court Dismisses Appeal of Ineligible Slum Dwellers Against Eviction Notice in Slum Rehabilitation Project. Appellants Found to Be Transit Camp Tenants Who Suppressed Earlier Proceedings and Used Dilatory Tactics to Obstruct Redevelopment Unde...
Related Judgement
High Court Bombay High Court Dismisses Union of India's Challenge to Arbitral Award on Loss of Profit and Interest in Railway Contract Dispute. Court Upholds 5% Loss of Profit on Withdrawn Work and 9% Interest as Reasonable and Within Tribunal's Discretion Unde...