Case Note & Summary
The petitioner, Indian Oil Corporation Ltd., filed a petition under Section 34 of the Arbitration and Conciliation Act, 1996 challenging an arbitral award dated 31st January, 2007. The dispute arose out of a construction contract for sand pad foundation, fabrication of new cone roof tank, and installation of fire fighting pumps at the petitioner's Bhadli depot. The respondent, M/s. Kadbrotee Engineering Industries, was awarded the work order on 26th July, 2002, and a formal contract was executed on 23rd August, 2002. The respondent commenced work on 7th October, 2002, but progress was slow, and only about 10% of the work was completed by 3rd March, 2003. The petitioner terminated the contract and invoked the arbitration clause. The arbitrator awarded Rs.9,12,157/- with interest to the respondent. The petitioner challenged the award on the grounds that the arbitrator ignored material evidence, misconstrued the contract, and that the award was contrary to public policy. The court, after hearing arguments, held that the scope of interference under Section 34 is limited and that findings of fact by the arbitrator are not open to reappraisal unless perverse. The court found that the arbitrator had considered all relevant evidence and that his interpretation of the contract was plausible. The court dismissed the petition, upholding the award.
Headnote
A) Arbitration Law - Challenge to Arbitral Award - Section 34 of the Arbitration and Conciliation Act, 1996 - Scope of Interference - The court considered whether the arbitral award was liable to be set aside on grounds that the arbitrator ignored material evidence and misconstrued the contract. The court held that the scope of interference under Section 34 is limited and that findings of fact by the arbitrator are not open to reappraisal unless perverse or contrary to public policy. The court found no such perversity and dismissed the petition. (Paras 1-10) B) Arbitration Law - Interpretation of Contract - Section 34 of the Arbitration and Conciliation Act, 1996 - Finality of Arbitrator's Interpretation - The court held that the arbitrator's interpretation of the contract terms is final and cannot be substituted by the court's own view unless the interpretation is so unreasonable that no reasonable person could have arrived at it. The court found that the arbitrator's interpretation was plausible and not perverse. (Paras 5-8)
Issue of Consideration
Whether the arbitral award dated 31st January, 2007 granting Rs.9,12,157/- with interest to the respondent is liable to be set aside under Section 34 of the Arbitration and Conciliation Act, 1996 on the grounds that the arbitrator ignored material evidence and misconstrued the contract.
Final Decision
The court dismissed the petition and upheld the arbitral award dated 31st January, 2007.
Law Points
- Arbitration and Conciliation Act
- 1996
- Section 34
- Scope of challenge
- Findings of fact
- Interpretation of contract
- Perversity
- Public policy



