Bombay High Court Dismisses Insurance Company's Challenge to Arbitral Award on Fire Insurance Claim. Reinstatement Value Claim Allowed Despite Delay in Replacement; Acceptance Under Protest Not Full Settlement; Interest at 18% Upheld.

High Court: Bombay High Court Bench: BOMBAY
  • 2
Judgement Image
Font size:
Print

Case Note & Summary

The New India Assurance Company Limited (Petitioner) issued two fire and special perils insurance policies to M/s. Alan Scott Industries Limited (Respondent) covering raw materials, stock, and premises/machinery for their socks manufacturing plant. A fire occurred causing loss. The Respondent claimed on reinstatement value basis but replaced machinery after 12 months without seeking written extension from the insurer. The arbitral tribunal awarded compensation on reinstatement value basis. The Petitioner challenged the award under Section 34 of the Arbitration and Conciliation Act, 1996. The learned single Judge, by order dated 5th June 2008, found that the tribunal had not dealt with three contentions: non-arbitrability, acceptance of Rs.1,10,46,134/- in full and final settlement, and entitlement to interest. Instead of setting aside the award, the Judge remitted these issues to the tribunal. The tribunal then made an auxiliary award dated 5th May 2009 deciding all three issues against the Petitioner. The Petitioner filed a second petition challenging the auxiliary award. The court held that the remission was proper under Section 34(4). On the merits, the court found that the tribunal's interpretation of the reinstatement clause was plausible and not patently illegal. The acceptance of payment under protest did not constitute full and final settlement. The tribunal's award of interest at 18% per annum from the date of cause of action was within its discretion under Section 31(7)(a) and not excessive. Both petitions were dismissed.

Headnote

A) Arbitration Law - Remission of Award - Section 34 Arbitration and Conciliation Act, 1996 - Court remitted award to arbitral tribunal for decision on three specific issues instead of setting it aside - Held that remission is permissible under Section 34(4) to give an opportunity to cure defects (Paras 1-2).

B) Insurance Law - Reinstatement Value - Fire Insurance Policy - Insured claimed on reinstatement value basis but replaced machinery after 12 months without seeking extension - Arbitral tribunal allowed claim on reinstatement value - Held that the tribunal's interpretation of policy terms was plausible and not patently illegal (Paras 3-10).

C) Arbitration Law - Full and Final Settlement - Acceptance of Payment - Respondent accepted Rs.1,10,46,134/- under protest and continued to claim balance - Held that acceptance under protest does not amount to accord and satisfaction barring further claims (Paras 11-15).

D) Arbitration Law - Interest - Section 31(7)(a) Arbitration and Conciliation Act, 1996 - Arbitral tribunal awarded interest at 18% per annum from date of cause of action till payment - Held that tribunal has discretion to award interest even in absence of contract, and rate of 18% is not excessive (Paras 16-20).

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the arbitral tribunal correctly decided the three issues remitted by the court: (i) non-arbitrability of the dispute; (ii) whether the respondent had accepted a sum in full and final settlement of the award; (iii) whether the respondent is entitled to interest in the absence of a contract and at what rate.

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

Both Arbitration Petitions are dismissed. The original award and the auxiliary award are upheld.

Law Points

  • Arbitration and Conciliation Act
  • 1996
  • Section 31(7)(a)
  • Section 34
  • Section 16
  • Insurance Law
  • Reinstatement Value
  • Full and Final Settlement
  • Interest
  • Remission of Award
Subscribe to unlock Law Points Subscribe Now

Case Details

2010 LawText (BOM) (09) 45

Arbitration Petition No. 101 of 2007 and Arbitration Petition No. 1016 of 2009

2010-09-03

S.J. Vazifdar

Mr. Vishal Sheth i/b Crawford Bayley & Co. for the Petitioner; Mr. Shailesh Shah with Ms. Nina Kapadia i/b Pandya Gandhy & Co. for the Respondent

The New India Assurance Company Limited

M/s. Alan Scott Industries Limited

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Challenge to arbitral award under Section 34 of the Arbitration and Conciliation Act, 1996, and challenge to auxiliary award made upon remission.

Remedy Sought

Petitioner sought setting aside of the original award and the auxiliary award.

Filing Reason

Petitioner contended that the arbitral tribunal failed to decide three issues: non-arbitrability, acceptance of payment in full settlement, and entitlement to interest.

Previous Decisions

The learned single Judge by order dated 5th June 2008 remitted the award to the tribunal for decision on the three issues. The tribunal made an auxiliary award on 5th May 2009.

Issues

Whether the dispute was arbitrable? Whether the respondent had accepted Rs.1,10,46,134/- in full and final settlement of the award? Whether the respondent is entitled to interest in the absence of a contract and at what rate?

Submissions/Arguments

Petitioner argued that the claim on reinstatement value basis was not maintainable as replacement was not done within 12 months or with written extension. Petitioner argued that acceptance of payment amounted to full and final settlement. Petitioner argued that no interest was payable in absence of contract. Respondent argued that replacement was done within reasonable time and acceptance was under protest. Respondent argued that interest is payable under Section 31(7)(a) of the Act.

Ratio Decidendi

The court held that the arbitral tribunal's interpretation of the reinstatement clause was plausible and not patently illegal. Acceptance of payment under protest does not constitute full and final settlement. The tribunal has discretion to award interest under Section 31(7)(a) even in absence of contract, and 18% per annum is not excessive.

Judgment Excerpts

The learned Judge considered it appropriate to remit the award to the arbitral tribunal for a decision on these three issues. The arbitral tribunal, therefore, made and published what is termed as an auxillary award dated 5th May, 2009. The Petitioner had issued two fire and special perils insurance policies in favour of the Respondent for their socks manufacturing plant. Under the policies, compensation was payable either on a depreciated value basis or, if the insured was able to reinstate/replace the plant and machinery, on a reinstatement value basis provided the reinstatement/replacement was carried out within twelve months from the date of the loss or within such extended period as may have been allowed by the Petitioner in writing.

Procedural History

The arbitral tribunal made an award on 13th June 2006. The Petitioner challenged it under Section 34. On 5th June 2008, the learned single Judge remitted three issues to the tribunal. The tribunal made an auxiliary award on 5th May 2009. The Petitioner filed a second petition challenging the auxiliary award. Both petitions were heard together and disposed of by this common judgment.

Acts & Sections

  • Arbitration and Conciliation Act, 1996: Section 31(7)(a), Section 34, Section 34(4), Section 16
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
High Court Bombay High Court Dismisses Insurance Company's Challenge to Arbitral Award on Fire Insurance Claim. Reinstatement Value Claim Allowed Despite Delay in Replacement; Acceptance Under Protest Not Full Settlement; Interest at 18% Upheld.
Related Judgement
High Court Bombay High Court Upholds Industrial Court Order in Unfair Labour Practice Case — Contractual Watchmen Entitled to Permanent Status After 240 Days of Work. The court held that the employer committed unfair labour practices under Items 6, 9 and 10 o...