Bombay High Court Dismisses Writ Petition Challenging Arbitrator's Interim Order in Coal Transport Contract Dispute. Arbitrator's findings on committee report and weighment system held to be interim and not subject to writ jurisdiction under Articles 226 and 227 of Constitution of India.

High Court: Bombay High Court Bench: GOA
  • 10
Judgement Image
Font size:
Print

Case Note & Summary

The petitioner, M/s. Sanwal Coal Carriers, a proprietary concern, entered into a contract with Western Coalfields Limited (respondents) for driving payloaders and tippers to load and transport coal. Disputes arose leading to termination of the contract. By consent, the matter was referred to a sole arbitrator, Mr. B.R. Harne, on 20/7/2009 under the Arbitration and Conciliation Act, 1996. During arbitration, the petitioner sought production of a committee report constituted by the respondents regarding penalty and termination, which the petitioner claimed was favourable. The respondents refused to produce the complete report. The petitioner also raised issues regarding the weighment of transported coal. On 25/3/2010, the arbitrator passed an order styled as 'interim report' and 'interim order', holding that the committee report had no legal standing and was not relevant, and that the weighment system was accepted by the contractor and without fault. The petitioner challenged this order under Articles 226 and 227 of the Constitution of India before the Bombay High Court, Nagpur Bench. The High Court examined whether the impugned order was an interim award under Section 31(6) of the Act or an interim order, and whether writ jurisdiction was maintainable. The Court noted that the order was not final and did not decide the rights of parties conclusively; it was merely an interim direction on procedural aspects. The Court held that such interim orders of an arbitrator are not amenable to writ jurisdiction under Articles 226 and 227 unless there is a patent illegality or lack of jurisdiction, which was not present. The Court also found that the arbitrator's findings on the committee report and weighment system were based on material on record and were not perverse. Accordingly, the High Court dismissed the writ petition, leaving it open to the petitioner to challenge the interim order after the final award under Section 37 of the Act.

Headnote

A) Arbitration Law - Interim Order vs. Interim Award - Jurisdiction of High Court - The impugned order dated 25/3/2010 passed by the sole arbitrator, though styled as 'interim report' and 'interim order', is not an interim award under Section 31(6) of the Arbitration and Conciliation Act, 1996, but an interim order on procedural issues. The High Court declined to interfere under Articles 226 and 227 as the order is not final and can be challenged under Section 37 of the Act after final award. Held that writ jurisdiction is not available against interim orders of arbitrator unless there is patent illegality or lack of jurisdiction (Paras 1-10).

B) Arbitration Law - Relevance of Internal Committee Report - The arbitrator held that the committee report regarding penalty and termination has no legal standing and is not a relevant document. The High Court found no error in this finding as the report was internal and not binding on the arbitrator. Held that the arbitrator's appreciation of evidentiary value cannot be interfered with in writ jurisdiction (Paras 3-8).

C) Arbitration Law - Weighment System - The arbitrator found that the system of delivery, weighment, and billing was accepted by the contractor throughout the contract and was without fault. The High Court upheld this interim finding as it was based on material on record and not perverse. Held that interim findings on factual issues are not subject to writ review (Paras 3-8).

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the High Court under Articles 226 and 227 of the Constitution of India can interfere with an interim order passed by an arbitrator under the Arbitration and Conciliation Act, 1996, and whether the impugned order dated 25/3/2010 is an interim award or an interim order.

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

The High Court dismissed the writ petition, holding that the impugned order is an interim order and not an interim award, and that writ jurisdiction under Articles 226 and 227 is not available against such interim orders of an arbitrator. The Court found no patent illegality or lack of jurisdiction in the arbitrator's order. The petitioner is at liberty to challenge the interim order after the final award under Section 37 of the Arbitration and Conciliation Act, 1996.

Law Points

  • Arbitration and Conciliation Act
  • 1996
  • Section 16
  • Section 37
  • Writ jurisdiction under Articles 226 and 227
  • Interim orders of arbitrator
  • Finality of interim awards
  • Relevance of internal committee reports
  • Weighment system in coal transport contracts
Subscribe to unlock Law Points Subscribe Now

Case Details

2010 LawText (BOM) (08) 138

WRIT PETITION No. 2888 OF 2010

2010-08-26

B.P. Dharmadhikari

Mr. G.C. Singh for Petitioner, Mr. S.C. Mehadia for Respondents

M/s. Sanwal Coal Carriers, through its Proprietor, Shri Rajveersingh Sanwal

Western Coalfields Limited, through its Chairman cum Managing Director, Nagpur; Western Coalfields Limited, through its General Manager (CMC), Nagpur; Western Coalfields Limited, through its Chief General Manager, Wani North Area, Wani, District Chandrapur

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Writ Petition under Articles 226 and 227 of Constitution of India challenging an interim order passed by a sole arbitrator in a commercial contract dispute.

Remedy Sought

Petitioner sought quashing of the arbitrator's interim order dated 25/3/2010 and direction to respondents to produce the complete committee report.

Filing Reason

Petitioner challenged the arbitrator's order holding that the committee report had no legal standing and that the weighment system was without fault, alleging suppression of favourable evidence.

Previous Decisions

The sole arbitrator passed an interim order on 25/3/2010 on two issues: (1) committee report not relevant, (2) weighment system accepted by contractor.

Issues

Whether the impugned order dated 25/3/2010 is an interim award under Section 31(6) of the Arbitration and Conciliation Act, 1996 or an interim order? Whether the High Court under Articles 226 and 227 can interfere with an interim order of an arbitrator? Whether the arbitrator's findings on the committee report and weighment system are perverse or suffer from patent illegality?

Submissions/Arguments

Petitioner argued that the committee report was relevant and its suppression was illegal; the arbitrator erred in holding it not relevant. Respondents argued that the committee report was internal and not binding; the weighment system was accepted by the petitioner throughout the contract.

Ratio Decidendi

Interim orders passed by an arbitrator under the Arbitration and Conciliation Act, 1996, which are not final and do not decide the rights of parties conclusively, are not amenable to writ jurisdiction under Articles 226 and 227 of the Constitution of India. Such orders can be challenged only after the final award under Section 37 of the Act, unless there is patent illegality or lack of jurisdiction.

Judgment Excerpts

The challenge in this Writ Petition under Articles 226 and 227 of Constitution of India is to order styled as interim award dated 25/3/2010 by arbitrator in dispute between petition and respondent. On issue no. 1 before him regarding filing of committee's report, arbitrator found that that report has no legal standing and it cannot be treated as relevant document. On issue no. 2 about weighment of transported coal, he found that system of delivery, weighment and preparation of bill was without any fault and was accepted by contractor all through the contract.

Procedural History

The dispute arose out of a contract for driving payloaders and tippers for loading coal into trucks/tippers from ground stock and its transportation. By consent, the matter was referred to sole arbitrator Mr. B.R. Harne on 20/7/2009 under the Arbitration and Conciliation Act, 1996. During arbitration, the petitioner filed an application on 5/12/2009 seeking production of a committee report. On 16/1/2010, the petitioner sought hearing on that application. On 3/2/2010, the petitioner placed a note on relevance of the report and weighment. On 20/2/2010, the respondent placed its brief note. The arbitrator passed the impugned order on 25/3/2010. The petitioner filed the present writ petition on an unspecified date, and the High Court pronounced judgment on 26/8/2010.

Acts & Sections

  • Arbitration and Conciliation Act, 1996: Section 31(6), Section 37
  • Constitution of India: Article 226, Article 227
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
High Court Bombay High Court Dismisses Writ Petition Challenging Arbitrator's Interim Order in Coal Transport Contract Dispute. Arbitrator's findings on committee report and weighment system held to be interim and not subject to writ jurisdiction under Articles...
Related Judgement
High Court Bombay High Court Quashes Adjudication Proceedings in FERA Case Due to Inordinate Delay of 27 Years. Revival of show cause notices after 27 years held arbitrary and violative of Article 14 of the Constitution of India.