Case Note & Summary
The dispute originated from a construction contract awarded to Saluja Construction Company by Northern Coalfields Limited for building 100 B-Type Quarters at Bina Project, with an agreement executed on January 11, 1986. When disputes arose specifically regarding the Bina Project, the contractor issued an arbitration notice under Clause 9 of the agreement and subsequently filed an application under Sections 8/20 of the Arbitration and Conciliation Act, 1996, seeking appointment of an arbitrator and filing of the Bina Project agreement. The arbitrator, however, passed an award that included claims not only for the Bina Project but also for other projects (Amlohri and Jhingurda Projects) and even involved sister concerns, despite the arbitration being specifically limited to the Bina Project dispute. The respondent challenged this award under Section 34 of the Arbitration Act, and when that challenge was dismissed, appealed to the High Court under Section 37. The High Court allowed the appeal and quashed the entire arbitration award. The core legal issue before the Supreme Court was whether the High Court correctly quashed the entire award when the arbitrator had exceeded jurisdiction by deciding matters beyond the referred dispute. The appellant argued that while the arbitrator exceeded jurisdiction regarding other projects, the award for the Bina Project should stand, whereas the respondent contended that the entire award was vitiated by jurisdictional overreach. The Supreme Court analyzed that the arbitrator's jurisdiction was confined to the Bina Project dispute as per the arbitration agreement filed under Sections 8/20, and the arbitrator had no mandate to adjudicate other contracts or sister concerns' disputes. The Court held that the High Court was right in setting aside the award for non-Bina Project claims but erred in quashing the entire award, including the valid Bina Project portion. Consequently, the Supreme Court partially allowed the appeal, confirming the award of Rs. 5,99,158 for the Bina Project while upholding the setting aside of awards for other projects, and directed adjustment of deposited amounts accordingly.
Headnote
A) Arbitration Law - Arbitrator's Jurisdiction - Scope of Reference - Arbitration and Conciliation Act, 1996, Sections 2(a), 8, 20, 34, 37 - Arbitrator appointed specifically for Bina Project dispute exceeded jurisdiction by awarding claims for other projects and sister concerns - High Court correctly quashed award for non-Bina Project claims as arbitrator lacked mandate - Held that arbitrator's jurisdiction is limited to disputes arising from the written agreement filed before him (Paras 2-5). B) Arbitration Law - Setting Aside of Award - Partial Setting Aside - Arbitration and Conciliation Act, 1996, Sections 34, 37 - High Court erred in quashing entire award including valid Bina Project portion - Supreme Court modified High Court order to preserve award for Bina Project claims - Held that when award contains separable valid and invalid portions, only invalid portion should be set aside (Paras 5-7).
Issue of Consideration
Whether the High Court was correct in quashing the entire arbitration award when the arbitrator exceeded jurisdiction by deciding disputes beyond the referred Bina Project contract
Final Decision
Appeal allowed in part; High Court judgment modified to quash award only for non-Bina Project claims; Award of Rs. 5,99,158 for Bina Project confirmed; Excess deposited amount to be returned with 8% interest
Law Points
- Arbitrator's jurisdiction is confined to the dispute referred under the arbitration agreement
- Arbitrator cannot adjudicate matters beyond the scope of the referred dispute
- Award exceeding jurisdiction is liable to be set aside
- Partial setting aside of award is permissible when separable claims exist



