Supreme Court Upholds Project Proponent's Environmental Clearance in Construction Dispute Under Amended EIA Regime. Environmental Clearance Granted by Local Authority Valid as Per Notification Dated 9.12.2016, Protecting Existing Constructions but Requiring Fresh Clearance for Future Expansion.

  • 7
Judgement Image
Font size:
Print

Case Note & Summary

The dispute centered on the validity of an Environmental Clearance (EC) obtained by a project proponent for a construction project in Maharashtra. The appellant, M/s Sai Baba Sales Pvt. Ltd., initially constructed a project below the 20,000 sq. meter threshold under the 2006 EIA notification, not requiring an EC. Upon expansion to 49,012 sq. meters, the proponent applied for an EC, but the regime changed with the MoEFCC notification dated 9.12.2016, designating local authorities like the Pimpri Chinchwad Municipal Corporation (PCMC) as competent to grant ECs for projects between 20,000 and 50,000 sq. meters. Accordingly, the proponent obtained an EC from PCMC on 28.11.2017. However, the National Green Tribunal (NGT) later invalidated certain clauses of the 2016 notification in a batch matter on 8.12.2017. An original applicant filed OA No. 83/2019 in 2019, alleging unauthorized construction without a valid EC, leading the NGT to find the EC invalid and direct coercive action for post-8.12.2017 construction, but protected existing constructions based on the ratio in Goan Real Estate and Construction Ltd. Vs. Union of India. The Supreme Court considered appeals under Section 22 of the NGT Act against the NGT's judgment dated 18.1.2021. The core legal issue was whether the EC was valid under the amended regime and the effect of the NGT's invalidation. The appellant argued compliance with the applicable procedure and that the NGT's order did not nullify existing ECs, while the original applicant contended the EC was illegitimate post-invalidation. The Court analyzed the chronological facts, noting the proponent acted within the legal framework, obtaining necessary sanctions and applying to the competent authority as per the 2016 notification. It emphasized that the NGT's Committee report indicated the PCMC was the competent authority at the time, and the NGT's invalidation did not provide guidance on existing ECs. The Court held the EC was validly granted, protecting the existing constructions, but upheld the NGT's direction for future construction to require a fresh EC from the competent authority under the current regime, thus partially allowing the appeals by affirming the EC's validity while maintaining conditions for further development.

Headnote

A) Environmental Law - Environmental Clearance - Validity Under Amended Regime - Environmental Impact Assessment Notification, 2006 and Ministry of Environment, Forest and Climate Change Notification dated 9.12.2016 - Project Proponent initially constructed below threshold limit without EC, then expanded project and obtained EC from PCMC under 2016 notification after regime change - Court held EC valid as it was granted by competent authority at relevant time, complying with applicable procedure, and NGT's invalidation did not nullify existing ECs - Construction already raised protected (Paras 3-15).

B) Environmental Law - Judicial Review of Environmental Clearance - Retrospective Effect of NGT Orders - National Green Tribunal Act, 2010, Section 22 - NGT invalidated certain clauses of 2016 notification but did not nullify ECs granted under it - Court held NGT's order did not have retrospective effect to invalidate EC obtained prior to judgment, and no guidance was provided on implications for existing ECs - Existing constructions allowed to stand (Paras 12-16).

C) Environmental Law - Limitation for Environmental Challenges - Cause of Action Accrual - National Green Tribunal Act, 2010 - Original Applicant filed OA in 2019 alleging construction without EC - NGT rejected limitation challenge, finding cause of action arose in 2017 when threshold limit exceeded - Court did not overturn this finding, implying challenge was timely (Para 14).

D) Environmental Law - Future Construction Requirements - Fresh Environmental Clearance - Environmental Impact Assessment Notification, 2006 - NGT directed further construction only after securing EC from competent authority under current regime - Court upheld this direction, requiring Project Proponent to obtain fresh EC for any future expansion (Para 14).

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the Project Proponent possesses a validly granted Environmental Clearance (EC) under the Environmental Impact Assessment (EIA) notification dated 14.9.2006, and the implications of the NGT's invalidation of certain clauses of the MoEFCC notification dated 9.12.2016 on the EC granted by the local authority.

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

Supreme Court held the Environmental Clearance obtained from PCMC on 28.11.2017 is valid as it was granted by the competent authority under the amended regime at the relevant time. The existing constructions are protected, but further construction requires a fresh Environmental Clearance from the competent authority under the current regime. The appeals are disposed of accordingly.

Law Points

  • Environmental Impact Assessment (EIA) notification compliance
  • validity of Environmental Clearance (EC) under amended regime
  • protection of existing constructions
  • retrospective application of judicial orders
  • limitation period for environmental challenges
Subscribe to unlock Law Points Subscribe Now

Case Details

2021 LawText (SC) (11) 13

Civil Appeal No. 595 of 2021 with Civil Appeal No. 5768 of 2021

2021-11-26

Hrishikesh Roy, J.

Mr. Huzefa Ahmadi, Mr. Lonkar Nitin, Ms. Aishwarya Bhati, Mr. Rahul Chitnis, Mr. Mukesh Verma

M/s. Sai Baba Sales Pvt. Ltd.

Union of India & Ors.

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Appeal under Section 22 of the National Green Tribunal Act, 2010 against NGT judgment regarding validity of Environmental Clearance for construction project

Remedy Sought

Appellant seeks to uphold EC validity and protect constructions; Original Applicant seeks to invalidate EC and penalize unauthorized construction

Filing Reason

Challenging NGT judgment dated 18.1.2021 in OA No. 83/2019 which found EC invalid but protected existing constructions

Previous Decisions

NGT order dated 17.11.2020 found constructions irregular and directed remedial measures; Supreme Court set aside this order on 11.12.2020 in CA No. 3893/2020 and remitted matter to NGT; NGT then passed impugned judgment dated 18.1.2021

Issues

Whether the Project Proponent possesses a validly granted Environmental Clearance under the EIA notification dated 14.9.2006 Implications of NGT's invalidation of certain clauses of MoEFCC notification dated 9.12.2016 on EC granted by local authority

Submissions/Arguments

Project Proponent complied with applicable procedure and obtained EC from competent authority under amended regime; NGT's invalidation did not nullify existing ECs Original Applicant contended EC granted by Municipal Corporation is illegitimate after NGT struck down provisions of 2016 notification; construction should be prevented and penalized

Ratio Decidendi

Environmental Clearance granted by a local authority under an amended regulatory regime is valid if obtained in compliance with the applicable procedure at the time, and judicial invalidation of certain clauses of the notification does not retrospectively nullify such clearances, thereby protecting existing constructions while requiring fresh clearance for future expansion.

Judgment Excerpts

The main issue that arises for consideration in these matters is whether the Project Proponent herein possesses a validly granted Environmental Clearance (EC) under the Environmental Impact Assessment (EIA) notification dated 14.9.2006. The NGT then observed that because of the invalidation of certain clauses in the 2016 notification, the EC obtained from the PCMC is unacceptable and accordingly rendered a finding that the Project Proponent had failed to obtain the valid EC. It is apposite to note that the Committee appointed by the NGT, in its report dated 11.8.2020 had clearly indicated that when the Project Proponent had received the EC on 28.11.2017, the competent authority to issue the EC was the Environmental Cell of the PCMC.

Procedural History

Project Proponent initially constructed with sanction below threshold; expanded project and obtained EC from PCMC under 2016 notification; NGT invalidated certain clauses of 2016 notification on 8.12.2017; Original Applicant filed OA No. 83/2019 in 2019; NGT constituted Committee which reported in 2020; NGT passed order on 17.11.2020 finding constructions irregular; Supreme Court set aside this order on 11.12.2020 and remitted matter; NGT passed impugned judgment on 18.1.2021 protecting existing constructions but requiring fresh EC for future construction; appeals filed to Supreme Court under Section 22 of NGT Act.

Acts & Sections

  • National Green Tribunal Act, 2010: Section 22
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
Supreme Court Supreme Court Upholds Project Proponent's Environmental Clearance in Construction Dispute Under Amended EIA Regime. Environmental Clearance Granted by Local Authority Valid as Per Notification Dated 9.12.2016, Protecting Existing Constructions but Re...
Related Judgement
Supreme Court Supreme Court Dismisses Landowners' Special Leave Petition in Land Acquisition Compensation Case Due to Unexplained Delay and Lack of Merit. Compensation at Rs. 28.12 per Square Yard Upheld as Landowners Accepted Award and Court Found Consistent Dete...