Case Note & Summary
The petitioner, Spectrum Estates Private Ltd., filed a petition under Section 9 of the Arbitration and Conciliation Act, 1996, seeking interim relief against the respondent, Charkop Gagan Vihar CHS Limited. The dispute arose from a Memorandum of Understanding (MoU) dated 1st March 2008, for the development of land allotted by MHADA to the proposed society. The petitioner had paid a substantial amount towards the land cost and had performed its obligations under the MoU. The respondent, after registration, attempted to cancel the MoU and deal with a third party. The court examined whether an arbitration agreement existed, whether the petitioner had a prima facie case, and whether the balance of convenience favored granting interim relief. The court held that the MoU contained an arbitration clause and that the respondent was bound by it. The petitioner had a strong prima facie case as it had performed its obligations. The balance of convenience was in favor of granting interim relief to maintain status quo and prevent irreparable loss to the petitioner. The court directed the respondent to maintain status quo in respect of the land and not to create any third-party rights.
Headnote
A) Arbitration - Interim Relief - Section 9 of the Arbitration and Conciliation Act, 1996 - Existence of Arbitration Agreement - The court considered whether an arbitration agreement existed between the parties. The MoU contained an arbitration clause. The court held that the existence of an arbitration agreement is a prerequisite for relief under Section 9. The court found that the MoU was signed by the Chief Promoter on behalf of the proposed society and that the society, after registration, ratified the MoU. Therefore, the arbitration agreement was binding on the respondent. (Paras 1-10) B) Arbitration - Interim Relief - Section 9 of the Arbitration and Conciliation Act, 1996 - Prima Facie Case - The court examined whether the petitioner had a prima facie case. The petitioner had paid a substantial amount towards the land cost and had performed its obligations under the MoU. The respondent's attempt to cancel the MoU and deal with a third party was prima facie in breach of the agreement. The court held that the petitioner had a strong prima facie case. (Paras 11-15) C) Arbitration - Interim Relief - Section 9 of the Arbitration and Conciliation Act, 1996 - Balance of Convenience and Irreparable Loss - The court assessed the balance of convenience. The petitioner had invested significant funds and the land was the subject matter of the agreement. If the respondent was allowed to deal with the land, the petitioner would suffer irreparable loss. The court held that the balance of convenience was in favor of granting interim relief to maintain status quo. (Paras 16-20)
Issue of Consideration
Whether the petitioner is entitled to interim relief under Section 9 of the Arbitration and Conciliation Act, 1996, pending arbitration, in respect of a Memorandum of Understanding (MoU) for development of land.
Final Decision
The court directed the respondent to maintain status quo in respect of the land and not to create any third-party rights, pending arbitration.
Law Points
- Section 9 of the Arbitration and Conciliation Act
- 1996
- interim relief
- existence of arbitration agreement
- prima facie case
- balance of convenience
- irreparable loss



