Case Note & Summary
The dispute originated from a construction contract awarded in 1971 for building a road link, with completion delayed until 1977. The contractor, after receiving partial payments, raised claims in 1989 and initiated legal proceedings under the Arbitration Act, 1940, which led to a decree in 1990 for arbitration reference. However, the contractor failed to file the required agreement, and after the Arbitration and Conciliation Act, 1996 came into force, sought arbitrator appointment through the High Court in 2001. The arbitrator in 2004 awarded a principal sum of Rs. 9,20,650 and interest at 18% per annum from 1976, totaling Rs. 46,90,000 in interest. The appellants challenged this award under Section 34 of the 1996 Act, arguing that the interest award was unreasonable due to the contractor's prolonged inaction and the exorbitant rate. The District Judge and High Court upheld the award, leading to this Supreme Court appeal. The core legal issues involved the arbitrator's discretion under Section 31(7)(a) of the 1996 Act to award interest, the reasonableness of the 18% rate, and the entitlement to interest for periods of delay. The appellants contended that the contractor's silence for 12 years post-completion and 10 years post-decree should disentitle him to interest, and the interest amount being five times the principal was unjust. The respondents relied on Section 31(7)(a) and precedent to support the award. The Court analyzed Section 31(7)(a), emphasizing that while arbitrators have discretion to award interest, they must provide reasons for deeming the rate reasonable and consider the facts, including claimant conduct. It noted the contractor's delays from 1977 to 1989 and 1990 to 2001, holding that interest for these periods was unwarranted due to lapses. Citing precedents like Rajendra Construction Co., the Court found the 18% rate exorbitant and modified it to 9% per annum from 2001 to the award date and 6% thereafter, disallowing interest for the earlier delay periods. The appeal was partly allowed, modifying the interest award accordingly.
Headnote
A) Arbitration Law - Arbitral Award - Interest Award - Arbitration and Conciliation Act, 1996, Section 31(7)(a) - Dispute arose from construction contract where contractor claimed interest on delayed payments - Arbitrator awarded interest at 18% per annum from 1976 to award date without reasons - Court held that arbitrator must give reasons for deeming interest rate reasonable and consider claimant's delays - Interest disallowed for periods of claimant's inaction (Paras 10-14). B) Arbitration Law - Arbitral Award - Interest Rate Reasonableness - Arbitration and Conciliation Act, 1996, Section 31(7)(a) - Arbitrator awarded 18% interest, making interest amount five times principal award - Court found rate exorbitant and unreasonable based on precedents - Modified interest rate to 9% per annum from 2001 to award date and 6% thereafter (Paras 15-16). C) Arbitration Law - Arbitral Award - Delay and Laches - Arbitration and Conciliation Act, 1996 - Claimant remained silent for 12 years after work completion and 10 years after court decree - Court held claimant cannot benefit from own lapses - Interest disallowed for periods of delay (Paras 12-14).
Issue of Consideration
Whether the arbitrator's award of interest at 18% per annum for the entire period from 1976 to 2002 and beyond was justified under Section 31(7)(a) of the Arbitration and Conciliation Act, 1996, considering the claimant's delays
Final Decision
Appeal partly allowed, interest award modified: interest disallowed for periods from 1977 to 1989 and 1990 to 2001, interest rate reduced to 9% per annum from 2001 to award date and 6% per annum thereafter till payment
Law Points
- Arbitrator's discretion to award interest under Section 31(7)(a) of the Arbitration and Conciliation Act
- 1996 must be exercised reasonably with reasons
- interest cannot be awarded for periods of delay attributable to claimant's inaction
- interest rate must be reasonable and not exorbitant



