Bombay High Court Partially Modifies Arbitral Award in Contract Dispute — Interest Rate Reduced and Service Tax Liability Clarified. The court held that the arbitrator's grant of 9% interest was excessive and reduced it to 6% per annum, while upholding the denial of service tax under Clause 10(F)(1) of the contract.

High Court: Bombay High Court Bench: BOMBAY
  • 6
Judgement Image
Font size:
Print

Case Note & Summary

The petitioner, G.D. Anklesaria & Co., a sole proprietorship, was awarded a contract by the respondent, Airports Authority of India, for replacement of existing 2 Nos. 166 KVA DG Sets at Airport Mumbai. Disputes arose, and the arbitration clause was invoked on 26/07/2007. The statement of claim was submitted on 31/01/2008, and written submissions were filed on 20/09/2008. The sole arbitrator passed an award on 27/11/2008, partly allowing the claim but not granting interest at 18% per annum as claimed from 21/06/2005, and not awarding service tax and levies. The petitioner challenged the award under Section 34 of the Arbitration and Conciliation Act, 1996, primarily on the grounds of interest and service tax. The court, relying on its earlier view in M/s. Anupam Engineers v. Indian Oil Corporation and Supreme Court judgments, held that an award can be challenged partly. The court considered the arbitrator's power to grant interest under Section 31(7) of the Act and the Interest Act, 1978, and noted that the arbitrator had granted interest at 9% per annum from 18/04/2006 to 12/01/2009. The court modified the interest rate to 6% per annum for the pre-award period and 6% per annum for the post-award period, finding the arbitrator's rate excessive. Regarding service tax, the court upheld the arbitrator's decision, noting that Clause 10(F)(1) of the contract stated that tendered rates were inclusive of all taxes and levies, and thus the claimant was not entitled to separate reimbursement. The petition was partly allowed, modifying the award only on the interest rate.

Headnote

A) Arbitration Law - Challenge to Award - Section 34 of the Arbitration and Conciliation Act, 1996 - Partial Challenge - The court held that an award can be challenged partly, relying on Supreme Court judgments including Tata Hydro-Electric Power Supply Co. Ltd. v. Union of India and McDermott International Inc. v. Burn Standard Co. Ltd. (Paras 2-3).

B) Arbitration Law - Interest - Section 31(7) of the Arbitration and Conciliation Act, 1996 - Arbitrator's Power - The arbitrator has power to grant interest from the date of cause of action to the date of award, and from the date of award to the date of payment, unless the contract prohibits it. The court modified the interest rate from 9% to 6% per annum for the pre-award period and from 9% to 6% per annum for the post-award period, considering the prevailing economic conditions and the nature of the dispute (Paras 5-8).

C) Contract Law - Service Tax - Liability - The court held that under Clause 10(F)(1) of the contract, the tendered rates were inclusive of all taxes and levies, and therefore the claimant was not entitled to separate reimbursement of service tax. The arbitrator's denial of service tax was upheld (Paras 7-9).

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the arbitral award can be challenged partially under Section 34 of the Arbitration and Conciliation Act, 1996, and whether the arbitrator erred in not granting interest at 18% per annum and in not awarding service tax and levies.

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

The petition is partly allowed. The award is modified to the extent that the interest rate is reduced from 9% per annum to 6% per annum for the period from 18/04/2006 to 12/01/2009. The rest of the award, including the denial of service tax, is upheld.

Law Points

  • Section 34 of the Arbitration and Conciliation Act
  • 1996
  • Section 31(7) of the Arbitration and Conciliation Act
  • Interest Act
  • 1978
  • Arbitrator's power to grant interest
  • Modification of award
  • Service tax liability under contract
Subscribe to unlock Law Points Subscribe Now

Case Details

2010 LawText (BOM) (02) 47

Arbitration Petition No. 186 of 2009

2010-02-17

Anoop V. Mohta, J.

Mr. C.P. Deogirikar for the Petitioner, Ms. Malan Manoharan i/by Ms. Rekha Rajgopal for the Respondent

G.D. Anklesaria & Co. through its Sole Proprietor, T.S. Anklesaria

Airports Authority of India

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Petition under Section 34 of the Arbitration and Conciliation Act, 1996 challenging an arbitral award partially on grounds of interest and service tax.

Remedy Sought

The petitioner sought modification of the award to grant interest at 18% per annum from 21/06/2005 and to award service tax and levies.

Filing Reason

The arbitrator did not grant interest at the claimed rate of 18% per annum and did not award service tax and levies.

Previous Decisions

The sole arbitrator passed an award on 27/11/2008 partly allowing the claim but denying interest at 18% and service tax.

Issues

Whether the arbitral award can be challenged partially under Section 34 of the Arbitration and Conciliation Act, 1996. Whether the arbitrator erred in not granting interest at 18% per annum from the date of cause of action. Whether the arbitrator erred in not awarding service tax and levies.

Submissions/Arguments

The petitioner argued that the arbitrator has power to grant interest under Section 31(7) of the Arbitration Act and the Interest Act, 1978, and relied on Executive Engineer v. N.C. Budharaj. The respondent opposed the modification, arguing that the award was reasonable and the contract excluded separate reimbursement of service tax.

Ratio Decidendi

An award can be challenged partly under Section 34 of the Arbitration and Conciliation Act, 1996. The arbitrator has discretion to grant interest under Section 31(7), but the court can modify the rate if it is excessive. Under a contract where rates are inclusive of all taxes, the claimant is not entitled to separate reimbursement of service tax.

Judgment Excerpts

The original claimant the Petitioner, has invoked Section 34 of the Arbitration and Conciliation Act, 1996 and thereby, challenged the award partially, mainly on the ground of interest and claiming interest @ 18% p.a. from the date of payment that i.e. from 18/04/2006 till 12/01/2009, and also service tax and levies liabilities. I have already taken a view in Arbitration Petition No.31 of 2009, M/s. Anupam Engineers Vs. Indian Oil Corporation, dated 10/12/2009 by referring to the following Supreme Court Judgments of Section 34 of the Arbitration Act, that the award can be modified or the award can be challenged partly. Clause 10(F) (1), as relevant is as under 'Tendered rates are inclusive of all taxes and levies payable under the contract.'

Procedural History

The petitioner invoked the arbitration clause on 26/07/2007. Statement of claim was submitted on 31/01/2008. Written submissions were filed on 20/09/2008. The sole arbitrator passed the award on 27/11/2008. The petitioner filed Arbitration Petition No. 186 of 2009 under Section 34 of the Arbitration and Conciliation Act, 1996, challenging the award partially. The court heard the parties and delivered judgment on 17/02/2010.

Acts & Sections

  • Arbitration and Conciliation Act, 1996: Section 34, Section 31(7)
  • Interest Act, 1978:
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
High Court Bombay High Court Partially Modifies Arbitral Award in Contract Dispute — Interest Rate Reduced and Service Tax Liability Clarified. The court held that the arbitrator's grant of 9% interest was excessive and reduced it to 6% per annum, while uphol...
Related Judgement
Supreme Court Supreme Court Upholds Constitutionality of Section 6A of the Citizenship Act, 1955 for Migrants to Assam Assam Accord-related citizenship provision sustained, balancing Article 14, Article 29, and legislative competence under Article 11.