Case Note & Summary
The case arises from a lease deed dated 1st August 2013 between Reliable Spaces Pvt Ltd (the Petitioner/Lessor) and Evonik India Pvt Ltd (the Respondent/Lessee) for premises in Mumbai. The lease required the Lessor to obtain approvals from the Maharashtra Industrial Development Corporation (MIDC) within 12 months. Clause 11.2 of the lease contained a force majeure provision allowing either party to terminate if such approvals were delayed beyond 12 months due to reasons beyond the Lessor's control. The Lessee also had an option to terminate under Clause 11.1 if the Lessor failed to obtain approvals within 12 months. MIDC approvals were not obtained within the stipulated period. On 8th October 2014, the Lessee issued a termination letter invoking the force majeure clause (Clause 11.2) and also citing Clause 11.1. The Lessor disputed the termination and invoked arbitration. The sole arbitrator, Mr Cyrus Ardeshir, passed an award on 8th May 2019, holding that the termination was not under the force majeure clause, that there was no evidence of delayed MIDC approvals, that the time-limit for obtaining approvals was not binding, and that the Lessee was liable for NMMC property tax dues. The Lessee was directed to pay arrears of rent and property tax, and the Lessor was directed to refund the security deposit. The Lessor challenged the award under Section 34 of the Arbitration and Conciliation Act, 1996, on the ground of patent illegality, specifically perversity. The High Court found that the Arbitrator's conclusion that the termination was not under the force majeure clause was perverse because the termination letter explicitly invoked that clause. The court also found perversity in the Arbitrator's finding that there was no evidence of delayed MIDC approvals, as the record contained correspondence showing delays. However, the court upheld the Arbitrator's findings on the time-limit for approvals (though noting it was a plausible interpretation), the property tax dues, and the security deposit. The court set aside the award in part, only to the extent of the finding that the termination was not under the force majeure clause, and remitted the matter to the Arbitrator for fresh consideration on the consequences of such termination. The petition was partly allowed.
Headnote
A) Arbitration Law - Challenge to Arbitral Award - Section 34 of the Arbitration and Conciliation Act, 1996 - Patent Illegality - Perversity - The court examined whether the arbitral award was perverse, i.e., whether no reasonable person could have arrived at the conclusion based on the evidence. The court found that the Arbitrator's conclusion that the termination was not under the force majeure clause was perverse because the termination letter explicitly invoked the force majeure clause and the Arbitrator ignored this evidence. (Paras 1-2, 22-24) B) Contract Law - Force Majeure Clause - Interpretation - The lease deed contained a force majeure clause allowing termination if MIDC approvals were delayed beyond 12 months. The court held that the Arbitrator's finding that the termination was not under this clause was contrary to the plain language of the termination letter, which stated that the lessee was terminating under the force majeure clause due to delay in approvals. (Paras 22-24) C) Arbitration Law - Evidence Appreciation - Section 34 of the Arbitration and Conciliation Act, 1996 - Perversity - The court held that the Arbitrator's finding that there was no evidence of delayed MIDC approvals was perverse because the record contained correspondence showing delays. The court noted that the Arbitrator ignored material evidence. (Paras 25-27) D) Contract Law - Time-Limit for Performance - The lease deed required the lessor to obtain MIDC approvals within 12 months. The court found that the Arbitrator's interpretation that the time-limit was not binding was contrary to the express terms of the contract and was perverse. (Paras 28-29) E) Property Law - NMMC Property Tax Dues - The court upheld the Arbitrator's finding that the lessee was liable to pay property tax dues to NMMC as per the lease deed, as this finding was based on a plausible interpretation of the contract and was not perverse. (Para 30) F) Contract Law - Refund of Security Deposit - The court upheld the Arbitrator's direction for refund of the security deposit, as it was consistent with the lease terms and not perverse. (Para 31)
Issue of Consideration
Whether the arbitral award dated 8th May 2019 suffers from patent illegality, specifically perversity, under Section 34 of the Arbitration and Conciliation Act, 1996, in relation to the interpretation of the force majeure clause, the time-limit for obtaining MIDC approvals, and the findings on NMMC property tax dues and security deposit.
Final Decision
The petition is partly allowed. The arbitral award dated 8th May 2019 is set aside only to the extent of the finding that the termination was not under the force majeure clause. The matter is remitted to the sole arbitrator for fresh consideration on the consequences of the termination under the force majeure clause. All other findings of the award are upheld. No order as to costs.
Law Points
- Section 34 of the Arbitration and Conciliation Act
- 1996
- patent illegality
- perversity
- force majeure clause
- interpretation of contract
- evidence appreciation
- public policy



