Bombay High Court Quashes MIDC Circular Requiring 100% Completion of Work for Payment in Construction Contracts — Circular Held Unreasonable and Arbitrary Under Article 14 of Constitution of India. The court held that a circular requiring 100% completion of work before any payment is made is arbitrary and violative of Article 14, as it does not provide for payment for work done.

High Court: Bombay High Court Bench: AURANGABAD In Favour of Accused
  • 18
Judgement Image
Font size:
Print

Case Note & Summary

The petitioner, M/s Mascot Construction Co., a partnership firm, challenged a Circular dated 27.08.2020 issued by the Maharashtra Industrial Development Corporation (MIDC). The Circular mandated that for all construction contracts, payment would be made only after 100% completion of the work, with no provision for interim or part payments. The petitioner had ongoing contracts with MIDC and argued that the Circular was arbitrary, unreasonable, and violative of Article 14 of the Constitution of India. The court considered the submissions of both parties. The petitioner's counsel argued that the Circular was unreasonable as it did not provide for any payment for work done, even if partially completed, and that it unilaterally altered the payment terms of existing contracts. The respondents' counsel defended the Circular, stating it was issued to ensure timely completion of projects and to avoid delays. The court analyzed the Circular and found that it was indeed arbitrary and unreasonable. The court noted that the Circular did not provide for any payment for work done, even if the contractor had completed a substantial portion of the work. The court held that such a condition was not based on any intelligible differentia and was therefore violative of Article 14. The court also observed that the Circular unilaterally altered the payment terms of existing contracts without any contractual basis. The court quashed the Circular and directed the respondents to consider the representation of the petitioner in accordance with law. The court also made the rule absolute and disposed of the petition.

Headnote

A) Constitutional Law - Article 14 - Arbitrariness - Circular requiring 100% completion of work before payment - The court held that the Circular is arbitrary and unreasonable as it does not provide for any payment for work done, even if partially completed, and is not based on any intelligible differentia. (Paras 1-10)

B) Contract Law - Payment Terms - Unilateral modification - MIDC Circular - The court held that the Circular unilaterally alters the payment terms of existing contracts without any contractual basis, and is therefore unsustainable. (Paras 5-10)

C) Administrative Law - Circulars - Reasonableness - The court held that a circular which is arbitrary and unreasonable cannot be sustained, and the respondents are directed to consider the representation of the petitioner in accordance with law. (Paras 8-10)

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the Circular dated 27.08.2020 issued by MIDC requiring 100% completion of work before any payment is made is arbitrary, unreasonable, and violative of Article 14 of the Constitution of India.

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

The court quashed the Circular dated 27.08.2020 and directed the respondents to consider the representation of the petitioner in accordance with law. Rule made absolute. Petition disposed of.

Law Points

  • Article 14 of Constitution of India
  • 1950
  • Arbitrariness
  • Unreasonableness
  • Contractual obligations
  • Payment terms
  • Circulars
  • MIDC
  • Construction contracts
  • Writ jurisdiction
  • Public law remedy
Subscribe to unlock Law Points Subscribe Now

Case Details

2020 LawText (BOM) (10) 14

Writ Petition No. 6096 of 2020

2020-10-23

S. V. Gangapurwala, Shrikant D. Kulkarni

Amit A. Yadkikar, S. S. Dande

M/s Mascot Construction Co.

Maharashtra Industrial Development Corporation & Anr.

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Writ petition challenging a circular issued by MIDC requiring 100% completion of work before payment.

Remedy Sought

Quashing of Circular dated 27.08.2020 and direction to consider representation.

Filing Reason

The petitioner, a construction firm, had ongoing contracts with MIDC and was aggrieved by the Circular which mandated payment only after 100% completion of work, with no provision for part payments.

Issues

Whether the Circular dated 27.08.2020 is arbitrary and violative of Article 14 of the Constitution of India. Whether the Circular unilaterally alters the payment terms of existing contracts.

Submissions/Arguments

Petitioner argued that the Circular is arbitrary and unreasonable as it does not provide for any payment for work done, even if partially completed, and that it unilaterally alters the payment terms of existing contracts. Respondents argued that the Circular was issued to ensure timely completion of projects and to avoid delays.

Ratio Decidendi

A circular that requires 100% completion of work before any payment is made is arbitrary and unreasonable, as it does not provide for payment for work done and is not based on any intelligible differentia, thus violative of Article 14 of the Constitution of India.

Judgment Excerpts

The petitioner is assailing the Circular / order dated 27.08.2020. The Circular is arbitrary and unreasonable. The Circular does not provide for any payment for work done, even if partially completed. The Circular is not based on any intelligible differentia. The Circular unilaterally alters the payment terms of existing contracts without any contractual basis.

Procedural History

The petitioner filed a writ petition before the High Court of Judicature at Bombay, Bench at Aurangabad, challenging the Circular dated 27.08.2020 issued by MIDC. The court heard the matter and pronounced judgment on 23.10.2020.

Acts & Sections

  • Constitution of India, 1950: Article 14
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
High Court Bombay High Court Quashes MIDC Circular Requiring 100% Completion of Work for Payment in Construction Contracts — Circular Held Unreasonable and Arbitrary Under Article 14 of Constitution of India. The court held that a circular requiring 100% comp...
Related Judgement
High Court Bombay High Court Allows Arbitration Application Despite Allegations of Fraud — Holds That Serious Allegations of Fraud Do Not Bar Appointment of Arbitrator Under Section 11 of the Arbitration and Conciliation Act, 1996 When the Dispute Falls Withi...