High Court of Bombay Dismisses Petition Challenging Arbitral Award in Insurance Dispute — Loss of Profit Claim Rejected Due to Flood Exclusion Clause. The court upheld the arbitrator's finding that 'inundation' was excluded under the Loss of Profit (Fire) Policy, and the claim was not maintainable.

High Court: Bombay High Court Bench: BOMBAY In Favour of Prosecution
  • 3
Judgement Image
Font size:
Print

Case Note & Summary

The petitioner, Agrocel Industries Pvt. Ltd., was engaged in the production of Marine Chemical Bromine and had availed a 'Loss of Profit (Fire) Policy' from the respondent, United India Insurance Company Ltd., for an insured amount of Rs.20 crores on its gross profit. On 6 and 7 September 2011, heavy rainfall in the Kutch region caused flooding, damaging the petitioner's factory and resulting in loss of production. The petitioner informed the respondent and a surveyor was appointed, who assessed the loss at Rs.3,59,58,346/-. However, the respondent rejected the claim on the ground that the loss was caused by 'inundation', which was excluded under the policy. The matter was referred to arbitration, and the arbitral tribunal rejected the claim. The petitioner challenged the award under Section 34 of the Arbitration and Conciliation Act, 1996, arguing that the award was contrary to the public policy of India. The court examined the policy terms and found that the Loss of Profit Policy specifically covered loss due to fire but excluded loss caused by 'inundation'. The court noted that the petitioner had also availed a Standard Fire and Special Perils Policy which covered flood damage, and under that policy, the petitioner had already received Rs.1,72,25,105.88. The court held that the arbitrator's interpretation of the policy was plausible and not perverse, and the award did not shock the conscience of the court. The petition was dismissed.

Headnote

A) Arbitration - Section 34 of Arbitration and Conciliation Act, 1996 - Public Policy - Challenge to Arbitral Award - The court examined whether the arbitral award was contrary to the public policy of India. Held that the award was not patently illegal or perverse as the arbitrator had correctly interpreted the policy exclusion for 'inundation' and the claim was not maintainable under the Loss of Profit Policy. (Paras 1-16)

B) Insurance Law - Interpretation of Insurance Policy - Exclusion Clauses - Loss of Profit (Fire) Policy - The policy covered loss of profit due to fire but excluded loss caused by 'inundation'. The court held that the heavy rainfall and flooding constituted 'inundation' and thus the claim was rightly rejected. (Paras 2-10)

C) Evidence - Surveyor's Report - Binding Nature - The surveyor's report assessed the loss at Rs.3,59,58,346/- but the arbitrator found that the loss was not covered under the policy. The court held that the surveyor's report cannot override the policy terms. (Paras 6-12)

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the arbitral award rejecting the petitioner's claim for loss of profit under the Loss of Profit (Fire) Policy is liable to be set aside under Section 34 of the Arbitration and Conciliation Act, 1996, on the ground that it is contrary to the public policy of India, particularly when the loss was caused by flood/inundation which was excluded under the policy.

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

The court dismissed the petition, upholding the arbitral award dated 24 July 2015. The court held that the award was not contrary to the public policy of India and that the arbitrator's interpretation of the policy exclusion was plausible.

Law Points

  • Arbitration Act
  • 1996
  • Section 34
  • Public Policy
  • Interpretation of Insurance Policy
  • Exclusion Clauses
  • Surveyor's Report
  • Burden of Proof
Subscribe to unlock Law Points Subscribe Now

Case Details

2020 LawText (BOM) (03) 51

Commercial Arbitration Petition No. 544 of 2017

2020-03-11

G.S. Kulkarni

Mr. A.M. Vernekar a/w. Suraj S. Ghogare for the petitioner, Mr. Aseem Naphade a/w. Nikhil Mehta i/b. KMC Legal Venture for the respondent

Agrocel Industries Pvt. Ltd.

United India Insurance Company Ltd.

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Petition under Section 34 of the Arbitration and Conciliation Act, 1996 challenging an arbitral award rejecting insurance claim for loss of profit.

Remedy Sought

The petitioner sought to set aside the arbitral award dated 24 July 2015 and to have its claim for loss of profit under the insurance policy allowed.

Filing Reason

The petitioner's claim for loss of profit due to flood damage was rejected by the arbitral tribunal on the ground that the policy excluded 'inundation'.

Previous Decisions

The arbitral tribunal rejected the claim. The petitioner had also received Rs.1,72,25,105.88 under a separate Standard Fire and Special Perils Policy for damage to fixed assets.

Issues

Whether the arbitral award is contrary to the public policy of India under Section 34 of the Arbitration and Conciliation Act, 1996. Whether the loss caused by heavy rainfall and flooding is covered under the Loss of Profit (Fire) Policy or excluded as 'inundation'.

Submissions/Arguments

The petitioner argued that the heavy rainfall was an unprecedented event and the loss should be covered under the policy; the surveyor had assessed the loss at Rs.3,59,58,346/-. The respondent argued that the policy specifically excluded loss caused by 'inundation', and the claim was not maintainable; the petitioner had already been compensated under the Standard Fire and Special Perils Policy.

Ratio Decidendi

The court held that under Section 34 of the Arbitration and Conciliation Act, 1996, an arbitral award can be set aside only if it is contrary to the public policy of India, which includes patent illegality. The arbitrator's interpretation of the insurance policy exclusion clause was plausible and not perverse, and thus the award was not liable to be interfered with.

Judgment Excerpts

This is petition filed under section 34 of the Arbitration and Conciliation Act whereby the petitioner an insured under a 'Loss of Profit (Fire) Policy' availed from the respondent-insurance company, is before the Court assailing an arbitral award dated 24 July 2015 passed by the arbitral tribunal rejecting the claims as made by the petitioner. The court held that the award was not contrary to the public policy of India and that the arbitrator's interpretation of the policy exclusion was plausible.

Procedural History

The petitioner filed a claim with the respondent insurance company after flood damage in September 2011. The respondent appointed a surveyor who assessed the loss at Rs.3,59,58,346/-. The respondent rejected the claim. The matter was referred to arbitration, and the arbitral tribunal passed an award on 24 July 2015 rejecting the claim. The petitioner then filed the present petition under Section 34 of the Arbitration and Conciliation Act, 1996 before the High Court of Bombay.

Acts & Sections

  • Arbitration and Conciliation Act, 1996: Section 34
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
High Court High Court of Bombay Dismisses Petition Challenging Arbitral Award in Insurance Dispute — Loss of Profit Claim Rejected Due to Flood Exclusion Clause. The court upheld the arbitrator's finding that 'inundation' was excluded under the Loss of Profit...
Related Judgement
High Court Bombay High Court Upholds Disqualification of Municipal Councillor for Defying Party Whip Under Maharashtra Local Authority Members Disqualification Act, 1986. The Court held that the Petitioner's act of voting against the party whip constituted defi...