Case Note & Summary
The case involves a challenge under Section 34 of the Arbitration and Conciliation Act, 1996, against an arbitral award dated 6th September 2019. The Petitioners, Mann Housing Development and others (collectively 'the Developers'), were the respondents in the arbitration, while the Respondent, Paarijat Co-operative Housing Society Ltd. ('the Society'), was the claimant. The dispute arose from a Development Agreement (DA) between the parties, under which the Developers were to develop the Society's property and pay rent. The Developers failed to complete the project and defaulted on rent payments. The arbitral tribunal directed the Developers to hand over quiet, vacant, and peaceful possession of the property to the Society and to pay outstanding rent: Rs. 2,12,29,571 for the period up to 31st October 2018 with 9% interest, and rent from 1st November 2018 till handover with a 15% yearly increase as per Section 12(f) of the DA. The Developers challenged the award on grounds of patent illegality and public policy, arguing that the tribunal misconstrued the agreement and that the rent computation was erroneous. The court, after examining the award and submissions, held that the tribunal's findings were based on evidence and were not perverse. The court noted that the scope of interference under Section 34 is limited and does not permit re-appreciation of evidence. The court found no patent illegality or error apparent on the face of the award. Consequently, the petition was dismissed, and the award was upheld. The court also disposed of the interim application.
Headnote
A) Arbitration - Section 34 Challenge - Scope of Interference - Section 34 of the Arbitration and Conciliation Act, 1996 - The court considered whether the arbitral award directing possession and payment of rent was patently illegal or against public policy. The court held that the tribunal's findings on breach of development agreement and computation of rent were based on evidence and not perverse, and thus no interference was warranted under Section 34. (Paras 1-16) B) Arbitration - Development Agreement - Breach and Possession - Section 34 of the Arbitration and Conciliation Act, 1996 - The dispute arose from a Development Agreement where the Developers failed to complete construction and pay rent. The tribunal directed handover of property and payment of outstanding rent with 15% yearly increase. The court upheld the award, finding no error in the tribunal's interpretation of the agreement or computation of rent. (Paras 2-16)
Issue of Consideration
Whether the arbitral award dated 6th September 2019 directing the Developers to hand over possession and pay outstanding rent suffers from patent illegality or is against the public policy of India warranting interference under Section 34 of the Arbitration and Conciliation Act, 1996.
Final Decision
The court dismissed the petition and upheld the arbitral award dated 6th September 2019. The interim application was also disposed of.
Law Points
- Section 34 of the Arbitration and Conciliation Act
- 1996
- scope of interference
- patent illegality
- public policy
- findings of fact not re-appreciable
- no error apparent on face of award



