Case Note & Summary
The dispute originated from a construction contract dated 06.02.1988 between M/s Laxmi Continental Construction Co. and the State of U.P., involving earthwork and lining of V.U.G.C. from KM 10 to KM 11. Arbitration clause 52 of the agreement mandated resolution of disputes through a sole arbitrator appointed by the Chief Engineer from a list of officers of Superintending Engineer rank or higher, not connected with the work. The Chief Engineer appointed Shri S.S. Manocha as the sole arbitrator on 31.10.1992. During proceedings, the arbitrator superannuated on 30.11.1995, but continued with the arbitration after the civil court extended the time for making the award via order dated 11.12.1997, overruling the respondents' objections. The arbitrator declared an award on 08.01.1998, ordering payment to the appellant. The respondents challenged the award under Sections 30/33 of the Arbitration Act, 1940, but the civil court made it a rule of the court on 20.04.2001. The High Court, however, set aside the award, holding that the arbitrator misconducted himself by proceeding post-retirement. The core legal issues were whether the arbitrator's mandate terminates upon retirement under clause 52, and whether his continuation constituted misconduct. The appellant argued that clause 52 did not provide for termination on retirement, and the respondents had participated in proceedings and not challenged the civil court's extension order. The respondents contended that retirement terminated the mandate, requiring a fresh appointment, and the arbitrator misconducted by continuing. The Supreme Court analyzed clause 52, noting it specified qualifications for appointment but was silent on termination due to retirement. Relying on precedents, the court held that in the absence of such a provision, the arbitrator's mandate continues, and retirement does not automatically terminate it. The court also found that the respondents' participation and failure to challenge the civil court's order amounted to acquiescence, precluding later allegations of misconduct. The court quashed the High Court's judgment, restoring the arbitrator's award and the civil court's order making it a rule of the court, thereby favoring the appellant.
Headnote
A) Arbitration Law - Arbitrator's Mandate - Termination on Retirement - Indian Arbitration Act, 1940, Section 28 - Dispute arose from construction contract with arbitration clause 52 - Clause did not specify termination of arbitrator's mandate upon retirement - Court held that arbitrator's mandate continues unless clause provides otherwise, and retirement does not automatically terminate mandate - Held that arbitrator did not misconduct by continuing proceedings post-retirement as clause silent on termination (Paras 5, 8). B) Arbitration Law - Arbitrator Misconduct - Participation and Waiver - Indian Arbitration Act, 1940, Sections 30, 33 - Respondents participated in arbitration proceedings even after arbitrator's retirement and sought adjournments - Court found respondents' objection to arbitrator's continuation after retirement was overruled by civil court order which attained finality - Held that respondents cannot later allege misconduct as they acquiesced and order unchallenged (Paras 2.3, 2.4, 5). C) Arbitration Law - Extension of Time for Award - Civil Court's Power - Indian Arbitration Act, 1940, Section 28 - Civil court extended time for arbitration by 30 days via order dated 11.12.1997 after overruling respondents' objections - Order remained unchallenged and attained finality - Court upheld extension as valid exercise of power under Section 28, supporting arbitrator's continued proceedings (Paras 2.4, 5).
Issue of Consideration
Whether the arbitrator's mandate terminates upon his retirement, and whether the arbitrator misconducted himself by continuing proceedings post-retirement.
Final Decision
Supreme Court allowed the appeal, quashed and set aside the impugned judgment and order of the High Court, and restored the award dated 08.01.1998 and the order dated 20.04.2001 passed by the civil court making the award rule of the court.
Law Points
- Arbitration clause interpretation
- arbitrator's mandate termination
- misconduct of arbitrator
- participation in proceedings
- extension of time for award



