Bombay High Court Allows Appointment of Arbitrator in Arbitration Petition Under Section 11 of the Arbitration and Conciliation Act, 1996 — Dispute Arising from Work Contract for Construction of Canal. Clause 30.1 of General Conditions Constitutes an Arbitration Agreement and Disputes Are Not Excepted Matters.

High Court: Bombay High Court Bench: BOMBAY In Favour of Prosecution
  • 9
Judgement Image
Font size:
Print

Case Note & Summary

The petitioner, M/s F.A. Enterprise, a registered partnership firm, filed an arbitration petition under Section 11 of the Arbitration and Conciliation Act, 1996, seeking appointment of an arbitrator to resolve disputes arising from a work contract dated 17 August 2009 with the Vidarbha Irrigation Development Corporation (respondent). The contract was for construction of a canal and had a tender cost of Rs. 699,76,22,994. The petitioner relied on Clauses 30.1, 30.2, and 30.3 of the General Conditions of the Contract, which provided for the decision of the Superintending Engineer to be final and binding on all questions relating to the contract. The respondents opposed the petition, arguing that Clause 30.1 did not constitute an arbitration agreement and that the disputes were excepted matters under the contract. The court examined the language of Clause 30.1 and held that it amounted to an arbitration agreement as it provided for a binding decision by a third party on disputes arising out of the contract. The court also rejected the respondents' contention that the disputes were excepted matters, noting that the termination of the contract and claims for payment were not specifically excluded from arbitration. Consequently, the court allowed the petition and appointed a sole arbitrator to adjudicate the disputes, directing the parties to bear the arbitrator's fees equally.

Headnote

A) Arbitration Law - Existence of Arbitration Agreement - Section 11 of the Arbitration and Conciliation Act, 1996 - Clause 30.1 of General Conditions - The court examined whether Clause 30.1, which makes the decision of the Superintending Engineer final and binding, constitutes an arbitration agreement. The court held that the clause provides for a dispute resolution mechanism by a named authority and thus amounts to an arbitration agreement, relying on the principle that a clause need not use the word 'arbitration' if it contemplates a binding decision by a third party. (Paras 1-10)

B) Arbitration Law - Excepted Matters - Section 11 of the Arbitration and Conciliation Act, 1996 - The respondents argued that certain disputes were excepted from arbitration under the contract. The court held that the dispute raised by the petitioner regarding termination of the contract and claims for payment were not excepted matters and were arbitrable. (Paras 11-15)

C) Arbitration Law - Appointment of Arbitrator - Section 11 of the Arbitration and Conciliation Act, 1996 - The court allowed the petition and appointed a sole arbitrator to adjudicate the disputes between the parties, noting that the arbitration clause was valid and the disputes fell within its scope. (Paras 16-20)

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether Clause 30.1 of the General Conditions of the Contract constitutes an arbitration agreement and whether the disputes fall within the excepted matters under the contract.

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

The court allowed the arbitration petition and appointed a sole arbitrator to adjudicate the disputes between the parties.

Law Points

  • Arbitration agreement
  • existence of
  • Section 11 of the Arbitration and Conciliation Act
  • 1996
  • excepted matters
  • finality clause
  • appointment of arbitrator
Subscribe to unlock Law Points Subscribe Now

Case Details

2021 LawText (BOM) (08) 42

Arbitration Petition No.62 of 2017

2021-08-13

S.J. Kathawalla

Ms. Shilpa Kapil for Petitioner, Mr. P.M. Palshikar for Respondent Nos.1 and 2

M/s. F.A.Enterprise

Vidarbha Irrigation Development Corporation & Anr.

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Arbitration petition under Section 11 of the Arbitration and Conciliation Act, 1996 for appointment of an arbitrator.

Remedy Sought

Petitioner seeks appointment of an arbitrator to decide disputes arising out of a work contract.

Filing Reason

Disputes arose between the parties regarding the work contract dated 17 August 2009, and the petitioner invoked the arbitration clause.

Issues

Whether Clause 30.1 of the General Conditions constitutes an arbitration agreement? Whether the disputes are excepted matters under the contract?

Submissions/Arguments

Petitioner argued that Clauses 30.1, 30.2, and 30.3 contain an arbitration agreement. Respondents argued that Clause 30.1 does not constitute an arbitration agreement and that the disputes are excepted matters.

Ratio Decidendi

Clause 30.1 of the General Conditions of the Contract, which makes the decision of the Superintending Engineer final and binding on all questions relating to the contract, constitutes an arbitration agreement under Section 7 of the Arbitration and Conciliation Act, 1996. The disputes raised by the petitioner are not excepted matters and are arbitrable.

Judgment Excerpts

Clause 30.1 - Except where otherwise specified in the contract and subjected to the powers delegated to him by Corporation under the code, rules then in force, the decision of Superintending Engineer of the Circle for the time being shall be final, conclusive and binding on all parties to the contract upon all questions relating to the meaning of the specifications, design, drawing and instructions herein before mentioned and as to the quality of workmanship or material used on the work or as to any other questions claims, right matter or thing whatsoever if any way arising out of or relating to the contract designs, drawings, specifications, estimates, instructions, orders or these conditions or otherwise concerning the works, or the execution or failure to execute same, whether arising during the progress of work or after the completion or abandonment thereof.

Procedural History

The petitioner filed Arbitration Petition No.62 of 2017 under Section 11 of the Arbitration and Conciliation Act, 1996 before the High Court of Judicature at Bombay seeking appointment of an arbitrator. The respondents filed their reply opposing the petition. The court heard the parties and delivered judgment on 13 August 2021.

Acts & Sections

  • Arbitration and Conciliation Act, 1996: Section 11
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
High Court Bombay High Court Quashes Externment Order in Maharashtra Police Act Case — Lack of Material to Show Threat to Public Order. Externment under Section 56(1)(a)(b) of Maharashtra Police Act, 1951 set aside as crimes relied upon were pending trial and...
Related Judgement
High Court Bombay High Court Allows Appointment of Arbitrator in Arbitration Petition Under Section 11 of the Arbitration and Conciliation Act, 1996 — Dispute Arising from Work Contract for Construction of Canal. Clause 30.1 of General Conditions Constitutes ...