Case Note & Summary
The case involves an appeal by the Maharashtra Industrial Development Corporation (MIDC) against a decree passed in Special Civil Suit No.99/2009, where the trial court partly decreed the suit in favor of the respondent, Govardhani Construction Company, directing MIDC to pay Rs.2,16,53,217.36 with interest at 9% per annum. The respondent, a partnership firm engaged in civil and electrical works, had submitted a bid in response to a tender notice issued by MIDC in 2002 for construction of roads at Transport Nagar, Akola. On 12.05.2003, MIDC issued a letter accepting the respondent's tender and directed deposit of security amounts. However, no formal work order was issued, and the contract was not executed. The respondent filed a suit claiming losses due to breach of contract. The trial court held that a binding contract existed and awarded damages. On appeal, the Bombay High Court examined the terms of the tender and the general conditions of contract. The court found that the tender documents clearly stipulated that a formal work order was required for the contract to be binding. The letter of acceptance was merely an intimation of acceptance and did not constitute a contract. Since no work order was issued, no contract came into existence, and there was no breach. The court also noted that the respondent had not deposited the security amounts as directed, indicating that the contract was not finalized. Consequently, the court held that the respondent was not entitled to any damages. The appeal was allowed, the decree of the trial court was set aside, and the suit was dismissed. The court also reduced the rate of interest to 6% per annum if damages were payable, but since no damages were awarded, this was not applicable.
Headnote
A) Contract Law - Formation of Contract - Tender Acceptance - Acceptance of tender without issuance of formal work order does not create a binding contract - The court held that under the terms of the tender and general conditions of contract, a formal work order is necessary for the contract to come into existence; mere letter of acceptance is insufficient (Paras 10-15). B) Damages - Breach of Contract - Entitlement to Losses - Plaintiff not entitled to damages for losses suffered due to non-execution of work order - The court held that since no binding contract was formed, the question of breach does not arise; the plaintiff cannot claim losses for anticipated profits or expenses incurred before the contract was finalized (Paras 16-20). C) Interest - Award of Interest - Discretion of Court - Interest at 9% per annum from date of suit till realization - The court held that even if damages were payable, the rate of interest awarded by the trial court was excessive and reduced it to 6% per annum (Paras 21-25).
Issue of Consideration
Whether the acceptance of a tender by MIDC without issuance of a formal work order constitutes a binding contract, and whether the plaintiff is entitled to damages for alleged breach of contract.
Final Decision
Appeal allowed; decree of trial court set aside; suit dismissed. No order as to costs.
Law Points
- Contract formation
- Tender acceptance
- Work order
- Breach of contract
- Damages
- Interest




