Bombay High Court Partly Allows State's Appeal and Dismisses Contractor's Appeal in Arbitration Dispute Over Bridge Construction — Interest Rate Reduction from 25% to 18% per annum Upheld. The court held that the District Judge's modification of future interest was within permissible limits under Section 34 of the Arbitration and Conciliation Act, 1996 and the award did not contravene public policy.

High Court: Bombay High Court Bench: NAGPUR
  • 2
Judgement Image
Font size:
Print

Case Note & Summary

The case involves two appeals under Section 37 of the Arbitration and Conciliation Act, 1996 arising from a dispute between the State of Maharashtra (through its Executive Engineer, Public Works Division) and Khare & Tarkunde Infrastructure Pvt. Ltd., a contractor. The State had invited tenders for construction of two bridges on a BOT (Build, Operate, Transfer) basis. Disputes arose and were referred to a sole arbitrator, R.H. Tadvi, who passed an award on 04/03/2004. The State filed an application under Section 34 of the Act before the Principal District Judge, Chandrapur (Misc. Civil Application No.63/2004) challenging the award. The District Judge partly allowed the application by maintaining the award on all counts except one: the rate of future interest was reduced from 25% per annum to 18% per annum from the date of the award till realization. Aggrieved, the State filed First Appeal No.240/2007 challenging the maintenance of the award, and the contractor filed First Appeal No.213/2007 challenging the reduction in interest. The High Court heard both appeals together. The court held that the District Judge's modification of interest was justified and within the scope of Section 34, as 18% per annum is reasonable and not contrary to public policy. The State's challenge to the award on merits was rejected as the award did not contravene public policy. Consequently, the State's appeal was dismissed, and the contractor's appeal was also dismissed, upholding the District Judge's judgment.

Headnote

A) Arbitration Law - Appeal under Section 37 - Scope of Interference - The appeals under Section 37 of the Arbitration and Conciliation Act, 1996 challenge the judgment of the Principal District Judge partly allowing the State's application under Section 34. The court held that the scope of interference under Section 37 is limited and the District Judge's modification of interest rate was within permissible limits. (Paras 1-2)

B) Arbitration Law - Interest Rate - Reduction by Court - The District Judge reduced future interest from 25% to 18% per annum. The court upheld this reduction, noting that 18% is reasonable and not contrary to public policy. The contractor's appeal for restoration of 25% was dismissed. (Paras 2, 4)

C) Arbitration Law - Award Challenge - Public Policy - The State's challenge to the award on merits was rejected as the award did not contravene public policy under Section 34(2)(b)(ii) of the Act. The court found no error in the arbitrator's findings. (Paras 2-3)

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the learned Principal District Judge was justified in reducing the rate of future interest from 25% per annum to 18% per annum while maintaining the rest of the arbitral award, and whether the State's challenge to the award on merits is maintainable.

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

Both appeals dismissed. The judgment of the Principal District Judge, Chandrapur dated 15/12/2006 in Misc. Civil Application No.63/2004 is upheld. No order as to costs.

Law Points

  • Section 37 of the Arbitration and Conciliation Act
  • 1996
  • Section 34 of the Arbitration and Conciliation Act
  • Interest rate reduction by court under Section 34
  • Scope of interference with arbitral award
  • Public policy under Section 34(2)(b)(ii)
Subscribe to unlock Law Points Subscribe Now

Case Details

2021 LawText (BOM) (02) 99

First Appeal No.240 of 2007 and First Appeal No.213 of 2007

2021-02-18

A. S. Chandurkar, N. B. Suryawanshi

Shri P.K. Sathianathan (Special Counsel for State), Shri J. P. Pendsey with Shri R. S. Charpe (for contractor)

State of Maharashtra (in FA 240/2007); Khare & Tarkunde Infrastructure Pvt. Ltd. (in FA 213/2007)

Khare & Tarkunde Infrastructure Pvt. Ltd. and R.H. Tadvi (in FA 240/2007); State of Maharashtra and R.H. Tadvi (in FA 213/2007)

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Appeals under Section 37 of the Arbitration and Conciliation Act, 1996 against judgment of Principal District Judge partly allowing application under Section 34 challenging arbitral award.

Remedy Sought

State sought setting aside of arbitral award; contractor sought restoration of 25% interest rate.

Filing Reason

State challenged the award on merits; contractor challenged reduction of interest from 25% to 18%.

Previous Decisions

Arbitral award dated 04/03/2004; District Judge's judgment dated 15/12/2006 partly allowing Section 34 application by reducing future interest to 18%.

Issues

Whether the District Judge was justified in reducing the rate of future interest from 25% to 18% per annum. Whether the State's challenge to the arbitral award on merits is maintainable under Section 34.

Submissions/Arguments

State argued that the award was contrary to public policy and should be set aside. Contractor argued that the reduction of interest was unwarranted and the original 25% should be restored.

Ratio Decidendi

The court held that the District Judge's modification of future interest from 25% to 18% per annum was reasonable and within the scope of Section 34 of the Arbitration and Conciliation Act, 1996. The award did not contravene public policy, and the State's challenge on merits was not sustainable.

Judgment Excerpts

These appeals filed under Section 37 of the Arbitration and Conciliation Act, 1996 take exception to the judgment of the learned Principal District Judge, Chandrapur in Misc. Civil Application (Arbitration) No.63/2004 dated 15/12/2006. By that judgment the application filed by the appellant in First Appeal No.240/2007 under Section 34 of the Act of 1996 challenging the award passed by the sole Arbitrator on 04/03/2004 came to be partly allowed by maintaining the award of the Arbitrator dated 04/03/2004 on all counts except one. The only modification directed by the learned Principal District Judge was in the rate of future interest which was reduced from 25% per annum to 18% per annum from the date of the award till realization.

Procedural History

Arbitral award passed on 04/03/2004. State filed Section 34 application (Misc. Civil Application No.63/2004) before Principal District Judge, Chandrapur. District Judge partly allowed application on 15/12/2006, reducing future interest to 18%. State filed First Appeal No.240/2007; contractor filed First Appeal No.213/2007. Both appeals heard together and dismissed on 18/02/2021.

Acts & Sections

  • Arbitration and Conciliation Act, 1996: Section 34, Section 37
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
High Court High Court of Karnataka Allows Writ Petition Seeking Linguistic Minority Status for Telugu Trust in Medical Education — State's Rejection Based on Non-Applicability of Telangana Act Quashed. The Court held that the State Government must consider th...
Related Judgement
High Court High Court of Karnataka Quashes FIR in Forgery and Cheating Case Due to Lack of Prima Facie Evidence. Petitioners Accused of Forgery and Cheating Under Sections 468, 471, 420 IPC - FIR Quashed as Allegations Did Not Disclose Any Offence.