Case Note & Summary
The case involves an appeal under Section 37 of the Arbitration and Conciliation Act, 1996, against an order of the Principal District Judge, Nagpur, setting aside an Arbitral Award dated 30.9.2004. The appellant, Shri Damodhar Rokde, was the successful bidder in a tender issued by the Defence Estates Officer (respondent) for removal of sand from Kanhan River Bed. The appellant deposited Rs. 92 lacs as bid amount and Rs. 9.20 lacs as security deposit. The tender notice specified that the contractor shall not be provided route from Gora Bazar and shall not be allowed to enter the river bed from Gora Bazar or any other new route not approved by local army authority. The contractor claimed that the routes specified (Ajni Ghat and Ghat Across the Railway Line) were not available due to army restrictions, and sought refund of security deposit. The arbitrator allowed the claim, holding that the contractor was not in breach. The respondent challenged the award under Section 34, and the PDJ set it aside, holding that the arbitrator ignored contractual terms and the award was contrary to substantive law. The High Court allowed the appeal, restoring the arbitral award. The court held that the arbitrator's interpretation of the contract was plausible and not perverse, and the award did not violate public policy. The court emphasized that under Section 37, the scope of interference is limited, and the PDJ exceeded his jurisdiction by reappreciating evidence.
Headnote
A) Arbitration Law - Appeal under Section 37 - Setting Aside of Arbitral Award - Section 37, Arbitration and Conciliation Act, 1996 - The court considered whether the Principal District Judge erred in setting aside the Arbitral Award dated 30.9.2004 on the premise that the arbitrator ignored contractual terms and that the award fell foul of substantive law. (Paras 2-3) B) Contract Law - Interpretation of Contractual Terms - Forfeiture of Security Deposit - The dispute pertained to a tender for removal of sand from river bed, where the contractor was prohibited from using certain routes. The arbitrator held that the contractor was not in breach as the routes were not available. The court held that the arbitrator's interpretation was plausible and not perverse. (Paras 7-10) C) Arbitration Law - Public Policy - Section 34, Arbitration and Conciliation Act, 1996 - The court held that an arbitral award can be set aside on the ground of public policy only if it is contrary to the fundamental policy of Indian law or is patently illegal. The award in question did not fall foul of public policy. (Paras 11-12)
Issue of Consideration
Whether the Principal District Judge erred in setting aside the Arbitral Award on the ground that the arbitrator ignored contractual terms and conditions and that the award was contrary to the substantive law of the land.
Final Decision
The appeal is allowed. The order of the Principal District Judge dated 30.11.2015 is set aside. The Arbitral Award dated 30.9.2004 is restored.
Law Points
- Arbitration
- Contractual Interpretation
- Section 37 Arbitration and Conciliation Act
- 1996
- Arbitral Award
- Public Policy
- Section 34 Arbitration and Conciliation Act



