Bombay High Court Allows Appeal Under Section 37 of Arbitration Act Against Rejection of Section 9 Petition — Interim Relief Granted to Foreign Investor in Shareholder Dispute. Court holds that the arbitral tribunal's jurisdiction to decide on interim measures does not preclude the court from granting interim relief under Section 9 of the Arbitration and Conciliation Act, 1996, especially when the tribunal is not yet constituted.

High Court: Bombay High Court Bench: BOMBAY
  • 3
Judgement Image
Font size:
Print

Case Note & Summary

The Appellant, Aniket SA Investments LLC, a foreign investor and shareholder in Respondent No. 1 (Janapriya Engineers Syndicate Private Limited), filed a Section 9 petition under the Arbitration and Conciliation Act, 1996, seeking urgent interim relief to prevent the Respondents from diluting its shareholding and removing its nominee director from the board. The dispute arose out of a Securities Subscription and Shareholders Agreement. The Learned Single Judge rejected the petition on the ground that the arbitral tribunal, once constituted, would have the power to grant interim relief under Section 17 of the Act. The Appellant appealed under Section 37. The Division Bench of the Bombay High Court allowed the appeal, holding that the court's jurisdiction under Section 9 is not ousted by the existence of Section 17. The court found that the Appellant had made out a strong prima facie case, balance of convenience was in its favor, and irreparable injury would be caused if relief was not granted. The court directed the Respondents to maintain status quo regarding the Appellant's shareholding and board composition, and restrained them from taking any steps to dilute the Appellant's shareholding or remove its nominee director, pending the constitution of the arbitral tribunal. The court also directed that the arbitral tribunal be constituted within a specified period.

Headnote

A) Arbitration Law - Interim Relief under Section 9 - Jurisdiction of Court - Section 9, Arbitration and Conciliation Act, 1996 - The court has the power to grant interim relief under Section 9 even if the arbitral tribunal may later be constituted and have power under Section 17. The existence of Section 17 does not oust the court's jurisdiction under Section 9. The court must consider the urgency and the fact that the tribunal is not yet constituted. (Paras 10-15)

B) Arbitration Law - Prima Facie Case - Balance of Convenience - Irreparable Injury - Section 9, Arbitration and Conciliation Act, 1996 - The Appellant, a foreign investor, made out a strong prima facie case that the Respondents were attempting to dilute its shareholding and remove its nominee director. The balance of convenience was in favor of granting interim relief to protect the Appellant's investment and rights under the Shareholders Agreement. Irreparable injury would be caused if the relief was not granted. (Paras 16-25)

C) Arbitration Law - Interim Relief - Status Quo - Section 9, Arbitration and Conciliation Act, 1996 - The court directed the Respondents to maintain status quo with respect to the shareholding of the Appellant and the composition of the board of directors, and restrained the Respondents from taking any steps to dilute the Appellant's shareholding or remove its nominee director, pending the constitution of the arbitral tribunal. (Paras 26-30)

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the Learned Single Judge erred in rejecting the Appellant's Section 9 petition on the ground that the arbitral tribunal, once constituted, would have the power to grant interim relief under Section 17 of the Arbitration and Conciliation Act, 1996, and whether the Appellant is entitled to interim relief pending the constitution of the arbitral tribunal.

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

The appeal is allowed. The Impugned Order dated 22nd October 2019 is set aside. The Respondents are directed to maintain status quo with respect to the shareholding of the Appellant and the composition of the board of directors of Respondent No. 1. The Respondents are restrained from taking any steps to dilute the Appellant's shareholding or remove its nominee director, pending the constitution of the arbitral tribunal. The arbitral tribunal shall be constituted within a period of four weeks from the date of this order.

Law Points

  • Section 9 of the Arbitration and Conciliation Act
  • 1996
  • Section 17 of the Arbitration and Conciliation Act
  • Section 37 of the Arbitration and Conciliation Act
  • Prima facie case
  • Balance of convenience
  • Irreparable injury
  • Interim relief pending arbitration
  • Jurisdiction of court under Section 9 not ousted by Section 17
Subscribe to unlock Law Points Subscribe Now

Case Details

2021 LawText (BOM) (01) 51

Commercial Appeal No. 504 of 2019 in Commercial Arbitration Petition (L) No. 1244 of 2019

2021-01-29

S.J. Kathawalla, R.I. Chagla

Mr. Sharan Jagtiani, Senior Advocate alongwith Ms. Surabhi Agarwal, Mr. Vyapak Desai, Mr. Alipak Banerjee, Ms. Bhavana Sunder instructed by Nishith Desai Associates for the Appellant/Original Petitioner. Mr. Mustafa Doctor, Senior Advocate alongwith Mr. Karthik Somasundaram instructed by Bharucha & Partners for Respondent Nos.1 and 2. Mr. Pavan Kumar, Mrs. Shraddha Gupta instructed by Bharucha & Partners for Respondent Nos.3 and 6.

Aniket SA Investments LLC

Janapriya Engineers Syndicate Private Limited, Janapriya Townships Private Limited, K. Ravinder Reddy, K. Priyamvada Reddy, Kranti Kiran Reddy, K. Ravi Kiran Reddy

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Commercial appeal under Section 37 of the Arbitration and Conciliation Act, 1996 against an order of the Learned Single Judge rejecting a Section 9 petition for interim relief.

Remedy Sought

The Appellant sought interim relief to prevent the Respondents from diluting its shareholding and removing its nominee director from the board of Respondent No. 1, pending the constitution of the arbitral tribunal.

Filing Reason

The Appellant alleged that the Respondents were attempting to dilute its shareholding and remove its nominee director in violation of the Securities Subscription and Shareholders Agreement.

Previous Decisions

The Learned Single Judge rejected the Section 9 petition on 22nd October 2019, holding that the arbitral tribunal, once constituted, would have the power to grant interim relief under Section 17 of the Act.

Issues

Whether the Learned Single Judge erred in rejecting the Section 9 petition on the ground that the arbitral tribunal would have power under Section 17? Whether the Appellant is entitled to interim relief under Section 9 pending the constitution of the arbitral tribunal?

Submissions/Arguments

The Appellant argued that the court's jurisdiction under Section 9 is independent and not ousted by Section 17, and that urgent interim relief was necessary to prevent irreparable harm before the tribunal is constituted. The Respondents argued that the Section 9 petition was premature as the arbitral tribunal could grant relief under Section 17, and that the Appellant had not made out a prima facie case.

Ratio Decidendi

The court's jurisdiction under Section 9 of the Arbitration and Conciliation Act, 1996 to grant interim relief is not ousted by the existence of Section 17, which empowers the arbitral tribunal to grant interim relief. The court can grant interim relief under Section 9 even if the tribunal may later be constituted, especially when the tribunal is not yet constituted and urgent relief is necessary to prevent irreparable harm. The court must consider the prima facie case, balance of convenience, and irreparable injury.

Judgment Excerpts

By this Appeal fled under Section 37 of the Arbitration and Conciliation Act, 1996, the Appellant – Aniket SA Investments LLC has challenged an Order of the Learned Single Judge dated 22nd October 2019. The court has the power to grant interim relief under Section 9 even if the arbitral tribunal may later be constituted and have power under Section 17. The Appellant has made out a strong prima facie case, balance of convenience is in its favor, and irreparable injury would be caused if relief is not granted.

Procedural History

The Appellant filed a Section 9 petition (Commercial Arbitration Petition (L) No. 1244 of 2019) before the Learned Single Judge of the Bombay High Court seeking interim relief. The Learned Single Judge rejected the petition on 22nd October 2019. The Appellant then filed the present Commercial Appeal No. 504 of 2019 under Section 37 of the Arbitration and Conciliation Act, 1996 before the Division Bench. The appeal was reserved on 18th September 2019 and pronounced on 29th January 2021.

Acts & Sections

  • Arbitration and Conciliation Act, 1996: Section 9, Section 17, Section 37
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
High Court Bombay High Court Upholds Life Conviction for Murder of Minor Girl in Eve-Teasing Revenge Case. Conviction under Section 302 IPC confirmed based on credible eyewitness testimony and motive established by prior eve-teasing incident and father's interv...
Related Judgement
High Court Bombay High Court Allows Appeal Under Section 37 of Arbitration Act Against Rejection of Section 9 Petition — Interim Relief Granted to Foreign Investor in Shareholder Dispute. Court holds that the arbitral tribunal's jurisdiction to decide on inte...