Bombay High Court Allows Appointment of Arbitrator in Contract Dispute Due to Failure of Multi-Tier Dispute Resolution Mechanism. Failure to Appoint Arbitrator Within 30 Days Triggers Section 11(6) of Arbitration and Conciliation Act, 1996.

High Court: Bombay High Court Bench: AURANGABAD In Favour of Accused
  • 1
Judgement Image
Font size:
Print

Case Note & Summary

The applicant, M/s. Mehra & Company, a partnership firm, filed an application under Section 11(6) of the Arbitration and Conciliation Act, 1996, seeking appointment of an arbitrator to resolve disputes arising out of a contract with the State of Maharashtra and its officers. The contract contained a multi-tier dispute resolution clause (Clause 30) providing for decisions by the Superintending Engineer, appeal to the Chief Engineer, and further appeal to the Executive Director. The applicant contended that despite making a request for appointment of an arbitrator, the respondent failed to appoint one within 30 days, thereby triggering the court's power under Section 11(6). The respondent argued that the multi-tier clause was a complete mechanism and the court should not intervene. The court, relying on the judgment in B.T. Patil Construction Vs. Maharashtra Krishna Valley Development Corporation, held that the respondent's failure to appoint an arbitrator within 30 days of the request constituted a deemed failure of the mechanism, and thus the court could appoint an arbitrator. The court appointed a retired District Judge as the sole arbitrator to adjudicate the disputes.

Headnote

A) Arbitration Law - Appointment of Arbitrator - Section 11(6) of the Arbitration and Conciliation Act, 1996 - Multi-tier Dispute Resolution Clause - The applicant contractor sought appointment of an arbitrator after the respondent failed to appoint one within 30 days of the request. The Court held that the multi-tier clause did not oust the jurisdiction of the Court under Section 11(6) as the respondent failed to act within the stipulated time. The Court appointed a retired District Judge as the sole arbitrator. (Paras 1-5)

B) Arbitration Law - Deemed Failure of Mechanism - Section 11(6) of the Arbitration and Conciliation Act, 1996 - Failure to Appoint Arbitrator - The Court held that the respondent's failure to appoint an arbitrator within 30 days of the request constituted a deemed failure of the appointment mechanism, entitling the applicant to invoke Section 11(6). (Paras 4-5)

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the Court can appoint an arbitrator under Section 11(6) of the Arbitration and Conciliation Act, 1996 when the agreement provides a multi-tier dispute resolution mechanism but the respondent failed to appoint an arbitrator within 30 days of the request.

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

The court allowed the application and appointed a retired District Judge as the sole arbitrator to adjudicate the disputes between the parties.

Law Points

  • Section 11(6) of the Arbitration and Conciliation Act
  • 1996
  • appointment of arbitrator
  • multi-tier dispute resolution clause
  • failure to appoint arbitrator within 30 days
  • deemed failure of mechanism
Subscribe to unlock Law Points Subscribe Now

Case Details

2022 LawText (BOM) (12) 25

Arbitration Application No. 4 of 2016

2022-12-02

Sandeep V. Marne, J.

Mr Girish K. (Naik) Thigale for Applicant, Mr S.S. Dande, A.G.P. for State, Mr B.R. Surwase for Respondent Nos. (B) and (D)

M/s. Mehra & Company

The State of Maharashtra through Executive Director, GMIDC; Chief Engineer, Nanded Irrigation Circle; Superintending Engineer, Nanded Irrigation Circle; Executive Engineer, Degloor Lendi Project Division

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Application under Section 11(6) of the Arbitration and Conciliation Act, 1996 for appointment of an arbitrator.

Remedy Sought

Appointment of an arbitrator by the court to resolve disputes arising out of a contract.

Filing Reason

The respondent failed to appoint an arbitrator within 30 days of the applicant's request, despite the existence of a multi-tier dispute resolution clause.

Issues

Whether the court can appoint an arbitrator under Section 11(6) when the agreement provides a multi-tier dispute resolution mechanism but the respondent failed to appoint an arbitrator within 30 days.

Submissions/Arguments

Applicant argued that the respondent failed to appoint an arbitrator within 30 days of the request, entitling the applicant to invoke Section 11(6). Respondent argued that the multi-tier clause in the agreement provided a complete mechanism and the court should not intervene.

Ratio Decidendi

The failure of the respondent to appoint an arbitrator within 30 days of the request constitutes a deemed failure of the appointment mechanism, and the court can appoint an arbitrator under Section 11(6) of the Arbitration and Conciliation Act, 1996.

Judgment Excerpts

This application is filed for appointment of arbitrator under sub section 6 of section 11 of the Arbitration and Conciliation Act, 1996. Mr Surwase, the learned counsel appearing for respondent Nos. (B) and (D) has relied upon judgment of this Court in B.T. Patil Construction Vs. Maharashtra Krishna Valley Development Corporation.

Procedural History

The applicant filed Arbitration Application No. 4 of 2016 under Section 11(6) of the Arbitration and Conciliation Act, 1996. The court reserved judgment on 28th November 2022 and delivered it on 2nd December 2022.

Acts & Sections

  • Arbitration and Conciliation Act, 1996: Section 11(6)
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
High Court Bombay High Court Allows Appointment of Arbitrator in Contract Dispute Due to Failure of Multi-Tier Dispute Resolution Mechanism. Failure to Appoint Arbitrator Within 30 Days Triggers Section 11(6) of Arbitration and Conciliation Act, 1996.
Related Judgement
High Court Bombay High Court Allows Writ Petition Challenging SVLDRS-3 Demand for Interest Component Under Sabka Vishwas Scheme. Interest paid under protest prior to show cause notice is part of tax dues under Section 124(2) of Finance Act, 2019.