Bombay High Court Grants Interim Relief to Flat Purchaser Under Section 9 of Arbitration Act for Incomplete Flat Due to Struts. Developer directed to remove struts and complete flat within 12 weeks or pay compensation.

High Court: Bombay High Court Bench: BOMBAY In Favour of Prosecution
  • 2
Judgement Image
Font size:
Print

Case Note & Summary

The petitioners, Shahveer Padam Kapadia and another, filed a petition under Section 9 of the Arbitration and Conciliation Act, 1996, seeking interim relief against the respondents, Omkar Realtors and Developers Pvt. Ltd. and another. The dispute arose from a contract dated 20 June 2017 for the sale of a flat (Flat 6501) in a high-rise building known as 'Omkar 1973, Worli.' The petitioners paid a substantial amount of Rs. 22,41,00,000 towards the purchase price. However, the flat was not delivered in a habitable condition because the developer had left structural struts inside the flat, which were required for ongoing construction of the building's lift shaft. The petitioners sought a mandatory injunction directing the respondents to remove the struts and make the flat habitable, or alternatively, to allow the petitioners to remove the struts at the respondents' cost, and to pay default interest for the delay. The court considered the principles for granting interim relief under Section 9 of the Act, including the existence of a prima facie case, balance of convenience, and irreparable loss. The court noted that the petitioners had a strong prima facie case as they had paid almost the entire consideration and were unable to use the flat. The balance of convenience was in favor of the petitioners, as the developer's inconvenience in removing the struts was minimal compared to the petitioners' hardship. The court also found that the petitioners would suffer irreparable loss if the relief was not granted. Consequently, the court directed the respondents to remove the struts and complete the flat within 12 weeks, failing which the respondents would pay compensation of Rs. 5 lakhs per month to the petitioners until the flat was made habitable. The petition was disposed of accordingly.

Headnote

A) Arbitration - Interim Measures - Section 9 of Arbitration and Conciliation Act, 1996 - Prima Facie Case - The petitioners purchased a flat in a high-rise building and paid substantial consideration. The flat was not habitable due to struts left by the developer. The court held that the petitioners have a strong prima facie case for relief as the developer failed to deliver the flat in habitable condition. (Paras 1-10)

B) Arbitration - Interim Measures - Balance of Convenience - Section 9 of Arbitration and Conciliation Act, 1996 - The balance of convenience was in favor of the petitioners as they had paid over Rs. 22 crores and were unable to use the flat. The developer's inconvenience in removing struts was outweighed by the petitioners' hardship. (Paras 11-20)

C) Arbitration - Interim Measures - Irreparable Loss - Section 9 of Arbitration and Conciliation Act, 1996 - The court found that the petitioners would suffer irreparable loss if the struts were not removed and the flat made habitable, as they had invested a large sum and could not use the property. (Paras 21-25)

D) Arbitration - Interim Measures - Mandatory Injunction - Section 9 of Arbitration and Conciliation Act, 1996 - The court granted a mandatory injunction directing the developer to remove struts and complete the flat within 12 weeks, failing which the developer must pay compensation of Rs. 5 lakhs per month. (Paras 26-30)

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the petitioners are entitled to interim relief under Section 9 of the Arbitration and Conciliation Act, 1996, directing the respondent developer to remove struts from the flat and make it habitable, pending arbitration.

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

The court allowed the petition and directed the respondents to remove the struts and complete the flat within 12 weeks. In default, respondents to pay compensation of Rs. 5 lakhs per month to the petitioners until the flat is made habitable.

Law Points

  • Interim measures under Section 9 of Arbitration and Conciliation Act
  • 1996
  • Prima facie case
  • Balance of convenience
  • Irreparable loss
  • Mandatory injunction
  • Specific performance of contract for sale of flat
  • Compensation for delay
Subscribe to unlock Law Points Subscribe Now

Case Details

2022 LawText (BOM) (11) 64

Commercial Arbitration Petition (L) No. 25612 of 2021

2022-11-04

G.S. Kulkarni

Haresh Jagtiani, Suprabh Jain, Vandana Kumavat, Mohammed Shariq Shaikh for petitioners; Mayur Khandeparkar, Jamshed Master, Ashraf Diamondwala for respondent no. 1; Abhijit Patil for SRA; Kanchan Rane, 1st Assistant to Court Receiver

Shahveer Padam Kapadia & Anr.

Omkar Realtors and Developers Pvt. Ltd. & Anr.

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Commercial arbitration petition seeking interim relief under Section 9 of the Arbitration and Conciliation Act, 1996.

Remedy Sought

Petitioners sought mandatory injunction directing respondents to remove struts from flat 6501 and make it habitable, or alternatively allow petitioners to remove struts at respondents' cost, and to pay default interest for delay.

Filing Reason

Respondent developer failed to deliver flat in habitable condition due to struts left inside the flat, causing inconvenience and loss to petitioners.

Issues

Whether the petitioners are entitled to interim relief under Section 9 of the Arbitration and Conciliation Act, 1996, directing the respondent developer to remove struts from the flat and make it habitable, pending arbitration.

Submissions/Arguments

Petitioners argued that they paid substantial consideration for the flat but it was not habitable due to struts, causing irreparable loss and inconvenience. Respondents contended that the struts were necessary for ongoing construction and removal would cause structural issues and delay.

Ratio Decidendi

Under Section 9 of the Arbitration and Conciliation Act, 1996, interim relief can be granted if the applicant shows a prima facie case, balance of convenience in their favor, and irreparable loss. Here, the petitioners had a strong prima facie case as they paid almost full consideration for a flat that was not habitable. The balance of convenience favored the petitioners as the developer's inconvenience was minimal compared to the petitioners' hardship. Irreparable loss would occur if the flat remained unusable. Hence, a mandatory injunction was granted.

Judgment Excerpts

This petition filed under Section 9 of the Arbitration and Conciliation Act, 1996 prays for interim measures in relation to disputes under a contract dated 20 June 2017 as entered between respondent (Builder/Developer) and the petitioners for sale of flat in a high rise building known as 'Omkar 1973, Worli.' The court directed the respondents to remove the struts and complete the flat within 12 weeks, failing which the respondents would pay compensation of Rs. 5 lakhs per month to the petitioners until the flat was made habitable.

Procedural History

The petition was filed under Section 9 of the Arbitration and Conciliation Act, 1996, seeking interim relief. The court reserved judgment on April 11, 2022, and pronounced it on November 4, 2022.

Acts & Sections

  • Arbitration and Conciliation Act, 1996: Section 9
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
High Court Bombay High Court Grants Interim Relief to Flat Purchaser Under Section 9 of Arbitration Act for Incomplete Flat Due to Struts. Developer directed to remove struts and complete flat within 12 weeks or pay compensation.
Related Judgement
High Court Bombay High Court Dismisses Appeal Against Injunction in Property Suit — Appellants Failed to Establish Prima Facie Case for Possession. Court upheld trial court's finding that respondents were in possession of suit property and appellants' claim b...