Bombay High Court Grants Interim Relief to Housing Society Against Developer Under Section 9 of Arbitration Act — Developer Restrained from Creating Third Party Rights and Directed to Remove Barricades. The court held that the society made out a strong prima facie case for interim measures pending arbitration due to the developer's failure to complete the project and the members' prolonged displacement.

High Court: Bombay High Court Bench: BOMBAY In Favour of Prosecution
  • 1
Judgement Image
Font size:
Print

Case Note & Summary

The petitioner, Nehru Nagar Ratnadeep Co-operative Housing Society Ltd., filed a petition under Section 9 of the Arbitration and Conciliation Act, 1996, seeking interim measures against the respondent, S.D. Bhalerao Constructions, a developer. The society had 40 members whose building was demolished in January 2015, and they had been suffering since 2011 when 39 members vacated their tenements. The society entered into a development agreement with the respondent, but the respondent failed to complete the project and allegedly attempted to create third party rights over the property. The society sought orders restraining the respondent from holding itself out as developer, from transferring or encumbering the property, and directing removal of barricades and materials from the site. The court examined the prima facie case, balance of convenience, and irreparable injury. It noted that the society's members were literally on the street and the developer had not fulfilled its obligations. The court found that the society had a strong prima facie case and that the balance of convenience was in its favor, as the developer's actions would cause irreparable harm. The court granted interim relief restraining the respondent from creating any third party rights and directed the respondent to remove its barricades and materials from the property within two weeks. The court also appointed a Court Receiver to take symbolic possession of the property if the respondent failed to comply. The petition was disposed of accordingly.

Headnote

A) Arbitration - Interim Measures - Section 9 of the Arbitration and Conciliation Act, 1996 - Prima Facie Case - The court considered whether a housing society whose building was demolished and whose members were displaced since 2011 was entitled to interim relief against the developer for breach of development agreement - Held that the society made out a strong prima facie case for grant of interim relief as the developer had failed to complete the project and was attempting to create third party rights (Paras 1-10).

B) Arbitration - Balance of Convenience - Section 9 of the Arbitration and Conciliation Act, 1996 - Irreparable Injury - The court held that the balance of convenience was in favor of the society as the members were suffering for over a decade and the developer's actions would cause irreparable injury if not restrained - Held that interim protection was necessary to protect the society's rights pending arbitration (Paras 11-15).

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the petitioner society is entitled to interim measures under Section 9 of the Arbitration and Conciliation Act, 1996, restraining the respondent developer from creating third party rights and directing removal of barricades from the subject property pending arbitration.

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

The court allowed the petition and granted interim relief restraining the respondent from creating any third party rights over the property and directed the respondent to remove its barricades and materials within two weeks. The court also appointed a Court Receiver to take symbolic possession if the respondent failed to comply.

Law Points

  • Section 9 of the Arbitration and Conciliation Act
  • 1996
  • Prima Facie Case
  • Balance of Convenience
  • Irreparable Injury
  • Interim Measures
  • Breach of Development Agreement
Subscribe to unlock Law Points Subscribe Now

Case Details

2022 LawText (BOM) (07) 54

Commercial Arbitration Petition No. 621 of 2021

2022-07-07

G.S. Kulkarni

2022:BHC-OS:5532

Mr. Aakash Rebello with Ms. Sunitha Perumal i/b. Mr. Sachin Masurkar for Petitioner, Mr. Vaibhav Krishna with Mr. Tahir Prande i/b. Juris Consillis for Respondent

Nehru Nagar Ratnadeep Co.op. Hsg. Soc. Ltd.

S.D. Bhalerao Constructions

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Petition under Section 9 of the Arbitration and Conciliation Act, 1996 seeking interim measures pending arbitration.

Remedy Sought

The petitioner sought orders restraining the respondent from holding itself out as developer, from transferring or encumbering the property, and directing removal of barricades and materials from the site.

Filing Reason

The respondent developer failed to complete the redevelopment project and allegedly attempted to create third party rights over the property, causing the society members to suffer displacement since 2011.

Issues

Whether the petitioner society is entitled to interim measures under Section 9 of the Arbitration and Conciliation Act, 1996.

Submissions/Arguments

The petitioner argued that the respondent had breached the development agreement and was attempting to create third party rights, causing irreparable harm to the society members who were displaced. The respondent contended that the petition was not maintainable and that the society had no prima facie case.

Ratio Decidendi

The court held that a strong prima facie case, balance of convenience, and irreparable injury in favor of the society justified the grant of interim measures under Section 9 of the Arbitration and Conciliation Act, 1996 to protect the society's rights pending arbitration.

Judgment Excerpts

The present proceeding is another case of a co-operative housing society having 40 members who are literally on the street. This is a petition filed under Section 9 of the Arbitration and Conciliation Act, 1996 whereby the petitioner/a co-operative society is before the court praying for the following interim measures pending the arbitral proceedings.

Procedural History

The petitioner filed Commercial Arbitration Petition No. 621 of 2021 under Section 9 of the Arbitration and Conciliation Act, 1996 before the Bombay High Court. The court heard the parties and passed the oral judgment on July 7, 2022.

Acts & Sections

  • Arbitration and Conciliation Act, 1996: Section 9
  • Code of Civil Procedure, 1908: Order 40 Rule 1
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
High Court Bombay High Court Grants Interim Relief to Housing Society Against Developer Under Section 9 of Arbitration Act — Developer Restrained from Creating Third Party Rights and Directed to Remove Barricades. The court held that the society made out a st...
Related Judgement
High Court High Court of Karnataka Quashes Bar Council Resolution Recognizing Rival Advocates Association — Unregistered Association Cannot Be Recognized Over Registered One. Resolution BCM Res. No.52/10 dated 12-13/06/2010 quashed as arbitrary and illegal.