Case Note & Summary
The petitioner, Ocean Sparkle Limited, filed a petition under Section 9 of the Arbitration and Conciliation Act, 1996, seeking interim relief pending arbitration against the respondents, Oil and Natural Gas Corporation Ltd. (ONGC) and State Bank of India. The dispute arose from a charter-party agreement dated 14 June 2018, under which the petitioner chartered its vessel 'OSL Glory' to ONGC for three years commencing 20 March 2018. The petitioner raised monthly invoices for charter-hire, which were cleared by ONGC until September 2019. However, on 1 September 2019, the vessel collided with ONGC's unmanned platform 'RS-21' while approaching Rig Jindal Explorer. Following the incident, ONGC withheld payments of invoices from April 2020 onwards and also sought to encash a bank guarantee furnished by the petitioner. The petitioner contended that the collision was not due to its fault and that ONGC had continued to use the vessel after the incident, clearing invoices until March 2020. The petitioner argued that ONGC's withholding of payments and threat to encash the bank guarantee were unjustified and caused irreparable loss. The court examined the submissions and found that the petitioner had made out a strong prima facie case, as the contract did not permit withholding of payments for the collision incident. The balance of convenience was in favor of the petitioner, as the petitioner would suffer irreparable loss if payments were withheld and the bank guarantee was encashed, whereas ONGC could be compensated by damages. The court directed ONGC to release the withheld invoices and maintain status quo on the bank guarantee, pending arbitration. The court also directed the petitioner to furnish an undertaking to abide by the final award.
Headnote
A) Arbitration - Interim Relief under Section 9 - Prima Facie Case - The court examined whether the petitioner had a prima facie case for release of withheld invoices and protection of bank guarantee, considering the collision incident and subsequent withholding of payments by ONGC. Held that the petitioner made out a strong prima facie case for interim relief (Paras 10-15). B) Arbitration - Balance of Convenience - The court weighed the balance of convenience, noting that the petitioner would suffer irreparable loss if payments were withheld and bank guarantee encashed, whereas ONGC could be compensated by damages. Held that balance of convenience was in favor of the petitioner (Paras 16-20). C) Arbitration - Irreparable Loss - The court considered the financial impact on the petitioner's business and the risk of bank guarantee invocation, concluding that irreparable loss would be caused to the petitioner if interim relief was not granted (Paras 21-25). D) Contract Law - Withholding of Payments - The court analyzed the contract terms regarding withholding of payments and found that ONGC's action of withholding invoices after the collision was not justified under the contract. Held that the petitioner was entitled to payment for services rendered (Paras 26-30).
Issue of Consideration
Whether the petitioner is entitled to interim relief under Section 9 of the Arbitration and Conciliation Act, 1996, directing the respondent ONGC to release withheld charter-hire invoices and maintain status quo on the bank guarantee, pending arbitration.
Final Decision
The court allowed the petition and directed ONGC to release the withheld invoices and maintain status quo on the bank guarantee, pending arbitration. The petitioner was directed to furnish an undertaking to abide by the final award.
Law Points
- Section 9 of the Arbitration and Conciliation Act
- 1996
- interim measures pending arbitration
- prima facie case
- balance of convenience
- irreparable loss
- contractual obligations
- withholding of payments
- bank guarantee encashment



