Case Note & Summary
The Appellant, Reliance Infrastructure Limited, entered into a contract with Respondent No.1, NLC India Limited, for the supply of coal under a Letter of Award dated 21st November 2016. As part of the contract, the Appellant furnished mobilization advance bank guarantees issued by Respondent Nos.2 to 4 banks in favour of Respondent No.1. Disputes arose between the parties regarding the performance of the contract, and Respondent No.1 terminated the contract and invoked the bank guarantees. The Appellant filed a Commercial Suit seeking a permanent injunction against the encashment of the bank guarantees and filed an Interim Application for ad-interim relief. The Learned Single Judge rejected the Interim Application, holding that the Appellant had not made out a case of fraud or irretrievable injustice. The Appellant appealed against this order. The main legal issues were whether the invocation of the bank guarantees could be restrained on grounds of alleged breach of contract and whether the Appellant would suffer irretrievable injustice. The Appellant argued that the termination was wrongful and that the bank guarantees were not unconditional, while the Respondents contended that the guarantees were unconditional and that the fraud exception did not apply. The court analyzed the law on bank guarantees, emphasizing the principle of autonomy and the narrow exceptions of fraud and irretrievable injustice. The court found that the Appellant had not established any fraud that would vitiate the entire transaction, and that the disputes regarding the contract termination were matters for arbitration or damages, not for injuncting the bank guarantees. The court also held that the Appellant had not demonstrated irretrievable injustice, as the Respondent No.1 was a government company capable of repaying any amounts if ultimately found liable. The court dismissed the appeal, upholding the order of the Learned Single Judge.
Headnote
A) Bank Guarantee - Injunction against encashment - Fraud exception - The court considered whether invocation of unconditional bank guarantees can be restrained on grounds of alleged breach of contract and disputes regarding termination of the underlying contract. Held that the fraud exception to the autonomy of bank guarantees requires clear evidence of fraud that vitiates the entire transaction, and mere contractual disputes or allegations of breach do not constitute fraud. (Paras 1-46) B) Bank Guarantee - Irretrievable injustice - The court examined whether the Appellant would suffer irretrievable injustice if the guarantees were encashed. Held that financial hardship or inability to recover amounts from the beneficiary does not amount to irretrievable injustice; the exception is limited to cases where the beneficiary is insolvent or cannot be made to repay. (Paras 1-46) C) Contract Law - Termination of contract - Disputes regarding termination of a contract for supply of coal do not justify injunction against bank guarantees. The court held that the Appellant's remedy lies in damages for wrongful termination, not in restraining the bank guarantees. (Paras 1-46)
Issue of Consideration
Whether the Appellant is entitled to an injunction restraining the Respondent No.1 from encashing the mobilization advance bank guarantees, and whether the Learned Single Judge erred in rejecting the Interim Application.
Final Decision
The appeal is dismissed. The order of the Learned Single Judge dated 29th December 2021 rejecting the Interim Application is upheld. No order as to costs.
Law Points
- Bank Guarantee
- Irretrievable Injustice
- Fraud Exception
- Commercial Contract
- Injunction
- Mobilization Advance
- Letter of Award
- Termination
- Unconditional Guarantee
- Autonomy of Bank Guarantee


