Case Note & Summary
The dispute arose from a contract awarded by the State of Kerala to the appellants for highway upgradation, executed on 7 November 2002. The appellants claimed interest on delayed payments under Clause 60.8 of the agreement, which provided for interest on unpaid sums, with the rate for local currency left blank in the bid appendix while foreign currency specified LIBOR plus 2%. Disputes on three counts were referred to arbitration after unresolved DRB recommendations. The Arbitral Tribunal, by majority award, directed interest on delayed payment in local currency, but one member dissented. The State challenged this under Section 34 of the Arbitration and Conciliation Act, 1996 before the District Court at Ernakulam, which set aside the interest award. The Kerala High Court Division Bench upheld this on 17 September 2009. The appellants appealed to the Supreme Court, seeking restoration of the Tribunal's award. The core legal issues were the interpretation of Clause 60.8 regarding interest entitlement and whether the appellants had waived their claim through letters dated 14 July 2004 and 3 August 2004. The appellants argued that the contract provided for interest, the blank rate did not imply zero interest, and the waiver letters were issued under coercion and limited to specific payments. The State contended that the blank rate meant zero interest and that the letters constituted a waiver. The court analyzed the contractual terms, the Tribunal's findings on waiver and coercion, and referenced the Constitution Bench judgment in Secretary, Irrigation Department, Government of Orissa & Ors. vs. G.C. Roy on compensation for deprivation of money. The decision involved examining whether the lower courts erred in setting aside the Tribunal's award on interest.
Headnote
A) Contract Law - Interest on Delayed Payment - Clause 60.8 of Contract Agreement - The dispute centered on the contractor's entitlement to interest on delayed payments under Clause 60.8 of the contract agreement dated 7 November 2002. The appellants had left the interest rate for local currency payments blank in the bid appendix, while foreign currency payments specified LIBOR plus 2%. The Tribunal awarded interest, but lower courts set it aside. Held that the contractor was entitled to interest as per contractual provisions and general principles of compensation for deprivation of money. (Paras 1-5) B) Contract Law - Waiver of Rights - Intentional Relinquishment - The respondent State argued that the appellants had waived their interest claim through letters dated 14 July 2004 and 3 August 2004. The Tribunal found no valid waiver, noting that the letters were issued under coercion and related only to specific payments (IPC I), not all claims. The Supreme Court considered this issue in the appeal. (Paras 5-8) C) Arbitration Law - Award Setting Aside - Section 34 Arbitration and Conciliation Act, 1996 - The State challenged the Tribunal's award under Section 34 before the District Court at Ernakulam, which partially set aside the interest award. The High Court upheld this decision. The Supreme Court examined the correctness of this setting aside in the appeal. (Paras 2-3)
Issue of Consideration
Whether the appellants were entitled to receive interest on delayed payment under the contract terms, and whether any waiver of such interest claim was valid
Law Points
- Contractual interpretation of interest clauses
- waiver of rights under contract law
- principles of arbitration under Arbitration and Conciliation Act
- 1996
- entitlement to interest on delayed payments as per contract terms



