Bombay High Court Allows Section 9 Petition for Interim Relief and Appoints Sole Arbitrator in Waste Management Contract Dispute — Petitioner Granted Protection Against Termination and Bank Guarantee Invocation Pending Arbitration.

High Court: Bombay High Court Bench: BOMBAY
  • 2
Judgement Image
Font size:
Print

Case Note & Summary

The petitioner, PMP Infratech Pvt Ltd, an AA Class Government Registered Civil Contractor, was engaged by the respondent, Bharat Petro Resources Ltd (BPRL), for waste management services in an operatorship block in Gujarat. The petitioner executed an MOU with Eco Care Infrastructure Pvt Ltd, the sole operator in Gujarat, to transport and dispose drill cutting waste. A Letter of Award dated 24/1/2020 was issued for a contract value of Rs.6.84 crores for twelve months. Due to the Covid-19 pandemic, the contract could not be completed within the stipulated period; the petitioner completed 80% of the work but the remaining 20% (transportation of waste) was pending due to technical issues regarding the operator requirement. The respondent terminated the contract and by notice dated 24/7/2021 called upon the petitioner to withdraw the termination or refer the dispute to an independent arbitrator. The petitioner filed Arbitration Petition (L) No. 16074/2021, and by consent, Shri S.C. Gupte (Retd Judge of Bombay High Court) was appointed as Sole Arbitrator on 10/5/2021. Subsequently, the respondent invoked the bank guarantee furnished by the petitioner, and HDFC Bank debited the amount despite the pending arbitration. The petitioner then filed the present petition under Section 9 of the Arbitration and Conciliation Act, 1996, along with an application under Section 11 for appointment of an arbitrator. The court, noting that an arbitrator was already appointed by consent, disposed of the Section 11 application as not pressed and granted interim relief under Section 9, protecting the petitioner from further coercive action pending the arbitration proceedings.

Headnote

A) Arbitration - Interim Relief under Section 9 - Appointment of Arbitrator under Section 11 - The petitioner sought interim protection against termination of contract and invocation of bank guarantee, and appointment of an independent arbitrator. The court held that since the arbitration was already pending before a sole arbitrator, the Section 9 petition was maintainable for interim relief, and the appointment of arbitrator was already made by consent. (Paras 1-3)

B) Contract Law - Termination of Contract - Bank Guarantee Invocation - The contract was terminated due to alleged non-completion of work, and the bank guarantee was invoked during pendency of arbitration. The court noted that the disputes were already before the arbitrator and did not delve into merits, but granted interim relief to maintain status quo. (Paras 2-3)

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the petitioner is entitled to interim relief under Section 9 of the Arbitration and Conciliation Act, 1996, and whether a sole arbitrator should be appointed under Section 11 of the Act to adjudicate disputes arising from the termination of the contract and invocation of bank guarantee.

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

The court allowed the Section 9 petition for interim relief, protecting the petitioner from further coercive action pending arbitration. The Section 11 application was disposed of as not pressed since an arbitrator was already appointed by consent.

Law Points

  • Section 9 of the Arbitration and Conciliation Act
  • 1996
  • Section 11 of the Arbitration and Conciliation Act
  • Interim measures
  • Appointment of arbitrator
  • Termination of contract
  • Bank guarantee invocation
  • Covid-19 pandemic as force majeure
Subscribe to unlock Law Points Subscribe Now

Case Details

2023 LawText (BOM) (07) 68

Arbitration Petition (L) No. 30250 of 2022 with Arbitration Application (L) No. 32620 of 2022

2023-07-05

Bharati Dangre, J.

Mr. Kamlesh Sukhwani with Mr. Chirag Sukhwani i/b Suvarna Joshi for the petitioner; Mr. Mustafa Doctor, Sr. Counsel with Roopadaksha Basu and Heenal Wadhwa for the respondent.

PMP Infratech Pvt Ltd

Bharat Petro Resources Ltd

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Arbitration petition under Section 9 and application under Section 11 of the Arbitration and Conciliation Act, 1996 seeking interim relief and appointment of arbitrator in a dispute arising from termination of a waste management services contract and invocation of bank guarantee.

Remedy Sought

The petitioner sought interim protection against the termination of the contract and invocation of bank guarantee, and appointment of an independent and impartial sole arbitrator.

Filing Reason

The respondent terminated the contract and invoked the bank guarantee despite the pendency of arbitration proceedings, prompting the petitioner to seek interim relief and appointment of arbitrator.

Previous Decisions

Earlier, in Arbitration Petition (L) No. 16074/2021, by order dated 10/5/2021, Shri S.C. Gupte (Retd Judge of Bombay High Court) was appointed as Sole Arbitrator by consent of parties.

Issues

Whether the petitioner is entitled to interim relief under Section 9 of the Arbitration and Conciliation Act, 1996? Whether a sole arbitrator should be appointed under Section 11 of the Act?

Submissions/Arguments

The petitioner argued that due to the Covid-19 pandemic, the contract could not be completed within the stipulated period, and the termination and bank guarantee invocation were unjustified. The respondent contended that the contract was terminated due to non-completion of work and the bank guarantee was validly invoked.

Ratio Decidendi

The court held that since arbitration was already pending before a sole arbitrator appointed by consent, the Section 9 petition for interim relief was maintainable, and the court granted interim protection to maintain status quo pending arbitration.

Judgment Excerpts

The petitioner is 'AA' Class Government Registered Civil Contractor and its services were engaged by the respondent – Bharat Petro Resources Limited, (for short 'BPRL') for hiring of Waste Management Services in Operatorship Block, CB-ONN 2010/8, Cambay Basin, Gujarat India. By the letter of Award dated 24/1/2020, he was awarded a total estimated contract value of Rs.6.84 crores (including taxes), the contract period being twelve months from the date of Letter of Authority (LOA). The respondent invoked the bank guarantee furnished by the petitioner and the HDFC Bank debited the amount of bank guarantee from the account of the petitioner and paid the same to BPRL despite pendency of the disputes before the Sole Arbitrator.

Procedural History

The petitioner initially filed Arbitration Petition (L) No. 16074/2021, and by consent, Shri S.C. Gupte was appointed as Sole Arbitrator on 10/5/2021. Subsequently, the respondent invoked the bank guarantee, leading the petitioner to file the present petition under Section 9 and application under Section 11. The court disposed of the Section 11 application as not pressed and granted interim relief under Section 9.

Acts & Sections

  • Arbitration and Conciliation Act, 1996: Section 9, Section 11
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
Supreme Court Supreme Court Dismisses Appeal in Customs Pre-Deposit Dispute Under Section 129E of Customs Act, 1962. Appellant's Claim for Discretionary Relief Under Pre-Substitution Provision Rejected as Order and Appeal Were Post-Substitution, with Legislative I...
Related Judgement
High Court Bombay High Court Allows Petition Challenging Seniority List in Agricultural University — Directs Reassignment of Placement Based on Continuous Length of Service. Seniority Determined by Continuous Service from Date of Appointment, Not Date of Conf...