Case Note & Summary
The petitioner, M/s Viraj Kamman Real Estate Developers Pvt Ltd, a real estate development company, entered into a Development Agreement dated 3/2/2018 with the respondent, Gopal Terrace Co-operative Housing Society Ltd, for development of a plot in Borivali, Mumbai. Disputes arose between the parties, and the petitioner filed arbitration petitions under Section 9 of the Arbitration and Conciliation Act, 1996, seeking interim relief. The court permitted conversion of these petitions into applications under Section 17 of the Act before the Sole Arbitrator. The arbitrator, by order dated 9/11/2022, refused interim relief to the petitioner, recording that the balance of convenience was in favour of the respondent Society and that the petitioner could prove its alleged monetary loss/damages at trial. The petitioner challenged this order under Section 37 of the Act, arguing that the order was patently illegal, erroneous, manifestly arbitrary, and perverse. The High Court, after hearing submissions, dismissed the appeal, holding that the arbitrator had exercised discretion judiciously and that there was no ground for interference under Section 37. The court noted that the arbitrator had considered the rival contentions and applied the correct legal principles regarding prima facie case, balance of convenience, and irreparable loss. The court also dismissed the connected Section 9 petition as infructuous.
Headnote
A) Arbitration Law - Interim Relief under Section 17 - Refusal of Injunction - The arbitrator refused interim relief to the developer claimant, holding that balance of convenience was in favour of the respondent Society and that the developer could prove monetary loss/damages at trial. The High Court found no patent illegality or perversity in the arbitrator's exercise of discretion, as the arbitrator had considered the rival contentions and applied the correct legal principles. (Paras 1-2) B) Arbitration Law - Appeal under Section 37 - Scope of Interference - The court reiterated that the scope of interference under Section 37 of the Arbitration and Conciliation Act, 1996 is limited to cases of patent illegality, perversity, or manifest arbitrariness. The appellate court cannot re-appreciate evidence or substitute its own view for that of the arbitrator. (Paras 1-2) C) Contract Law - Development Agreement - Interim Protection - The dispute arose from a Development Agreement dated 3/2/2018 between the developer and the cooperative housing society. The developer sought interim relief to protect its rights under the agreement, but the arbitrator found that the balance of convenience did not favour granting such relief. (Paras 1-2)
Issue of Consideration
Whether the order of the Sole Arbitrator dated 9/11/2022 refusing interim relief under Section 17 of the Arbitration and Conciliation Act, 1996 to the petitioner developer is patently illegal, erroneous, manifestly arbitrary or perverse, warranting interference under Section 37 of the Act.
Final Decision
The High Court dismissed the arbitration petition under Section 37 (CARBPL 37219/2022) and also dismissed the connected Section 9 petition (CARBPL 37197/2022) as infructuous, upholding the arbitrator's order dated 9/11/2022.
Law Points
- Section 37 of Arbitration and Conciliation Act
- 1996
- Section 17 of Arbitration and Conciliation Act
- Section 9 of Arbitration and Conciliation Act
- Balance of convenience
- Prima facie case
- Irreparable loss
- Patent illegality
- Perversity
- Manifest arbitrariness




